Mattison Contractors, Inc. submitted 16 bids on Wisconsin DOT contracts in the data, from 10 JAN 2023 to 10 FEB 2026, and was the low bidder on 11 of them (69%). When it was not low, its total sat a median +14% above the low bid.
- Owner
- Wisconsin DOT
- Low bid volume
- $21,386,634
- Latest bid
- 10 FEB 2026
- Data through
- 10 NOV 2026
By year
| Year | Bids | Low bids | Win rate |
|---|---|---|---|
| 2023 | 8 | 7 | 88% |
| 2024 | 4 | 0 | 0% |
| 2025 | 3 | 3 | 100% |
| 2026 | 1 | 1 | 100% |
By county
| County | Bids | Low bids | Win rate |
|---|---|---|---|
| St Croix | 4 | 4 | 100% |
| Statewide | 2 | 2 | 100% |
| Dunn | 2 | 1 | 50% |
| Buffalo | 2 | 1 | 50% |
| Pierce | 1 | 0 | 0% |
| Bayfield | 1 | 1 | 100% |
| Douglas | 1 | 1 | 100% |
| Northwest Region Wide | 1 | 0 | 0% |
| Clark | 1 | 0 | 0% |
| Pepin | 1 | 1 | 100% |
Pay items where it is most often lowest
| Pay item | Code | Unit | Lines bid | Lowest on the line | Its median price | All bidders' median |
|---|---|---|---|---|---|---|
| Silt fence maintenance | 628.1520 | LF | 12 | 12 (100%) | $0.01 | $0.02 |
| Mobilizations erosion control | 628.1905 | EACH | 12 | 9 (75%) | $185.00 | $233.00 |
| Traffic control | 643.5000 | EACH | 11 | 9 (82%) | $4,650.00 | $7,500.00 |
| Traffic control barricades type III | 643.0420 | DAY | 10 | 9 (90%) | $0.82 | $0.60 |
| Tack coat | 455.0605 | GAL | 9 | 9 (100%) | $4.42 | $3.85 |
| On-the-job training graduate at $5.00/HR | ASP.1T0G | HRS | 9 | 9 (100%) | $5.00 | $5.00 |
| On-the-job training apprentice at $5.00/HR | ASP.1T0A | HRS | 9 | 9 (100%) | $5.00 | $5.00 |
| Culvert pipe checks | 628.7555 | EACH | 9 | 9 (100%) | $16.00 | $20.00 |
| Traffic control signs | 643.0900 | DAY | 12 | 8 (67%) | $0.65 | $0.40 |
| Silt fence | 628.1504 | LF | 12 | 8 (67%) | $1.93 | $2.35 |
| Sawing asphalt | 690.0150 | LF | 11 | 8 (73%) | $2.25 | $1.96 |
| Fertilizer type B | 629.0210 | CWT | 11 | 8 (73%) | $90.25 | $100.00 |
A line counts when the firm priced it and at least one other bidder did too; the lowest unit price on the line counts whoever won the contract. Token prices and bids over three times the low bid are left out.
Who it meets most
| Firm | Contracts in common | That firm ranked ahead |
|---|---|---|
| Haas Sons, Inc. | 8 | 2 of 8 |
| A-1 Excavating LLC | 8 | 2 of 8 |
| McCabe Construction, Inc. | 7 | 2 of 7 |
| James Peterson Sons, Inc. | 3 | 1 of 3 |
| Chippewa Concrete Services, Inc. | 2 | 0 of 2 |
| Homer Tree Service, Inc. | 2 | 0 of 2 |
| Interstate Tree Landscaping | 2 | 1 of 2 |
| Pember Companies, Inc. | 2 | 0 of 2 |
| Hoffman Construction Company | 2 | 1 of 2 |
| Highway Landscapers, Inc. | 2 | 0 of 2 |
Latest bids
| Let | Contract | County | Project | Rank | Its bid | Against the low bid |
|---|---|---|---|---|---|---|
| 10 FEB 2026 | 20260210001 | Statewide | Statewide Type 1 Sign Replacement; Locations On Stn Per Annual Plan (VAR HWY, Statewide Statewide Type I Sign Replacement) | 1 of 3 | $696,923 | Low, 10% under the second |
| 11 NOV 2025 | 20251111026 | Pepin | Ellsworth - Durand; STH 25 N Intersection (USH 010, Pepin County Ellsworth - Durand) | 1 of 5 | $2,619,137 | Low, 0.0% under the second |
| 11 NOV 2025 | 20251111029 | Buffalo | STH 37 - Gilmanton; STH 37 to STH 88 (CTH B, Buffalo County STH 37 - Gilmanton) | 1 of 4 | $1,664,877 | Low, 6.0% under the second |
| 08 APR 2025 | 20250408021 | St Croix | 1020-00-84 | 1 of 1 | $2,995,948 | Low |
| 12 NOV 2024 | 20241112048 | Buffalo | T Buffalo, Winona Connector; T Buffalo Park-Great River St Trail (NON HWY, Buffalo County T Buffalo, Winona Connector) | 3 of 5 | $1,249,124 | +14% |
| 12 NOV 2024 | 20241112051 | Dunn | Scl - STH 25; CTH K to 420th Street (CTH D, Dunn County SCL - STH 25) | 2 of 5 | $2,293,442 | +3.0% |
| 08 OCT 2024 | 20241008015 | Clark | Globe - East County Line; CTH K Intersection (CTH H, Clark County Globe - East County Line) | 10 of 10 | $1,227,287 | +21% |
| 10 SEP 2024 | 20240910021 | Northwest Region Wide | Nw Region, Tree Clearing 2025; Nw Region Various Counties (NON HWY, Northwest Region Wide NW Region, Tree Clearing 2025) | 2 of 4 | $447,030 | +57% |
| 14 NOV 2023 | 20231114042 | Dunn | Connorsville - Bloomer; CTH O to North Jct CTH W (STH 064, Dunn County Connorsville - Bloomer) | 1 of 4 | $3,345,437 | Low, 7.0% under the second |
| 14 NOV 2023 | 20231114046 | St Croix | Hudson - New Richmond; Mccutcheon Road Intersection (CTH A, St Croix County Hudson - New Richmond) | 1 of 5 | $1,298,933 | Low, 1.0% under the second |
| 12 SEP 2023 | 20230912006 | Statewide | State Wide Tree Clearing; Various Counties (Nwr & Ncr) (NON HWY, Statewide FY23 State Wide Tree Clearing) | 1 of 3 | $296,980 | Low, 18% under the second |
| 12 SEP 2023 | 20230912016 | St Croix | Elmwood - STH 64; Ih94 (Kwik Trip) Intersection (STH 128, St. Croix County Elmwood - STH 64) | 1 of 3 | $45,969 | Low |
| 12 SEP 2023 | 20230912018 | Bayfield | Cornucopia - Superior; Bark Point Road to CTH H (STH 013, Bayfield County Cornucopia - Superior) | 1 of 4 | $1,325,947 | Low, 18% under the second |
| 12 SEP 2023 | 20230912019 | Douglas | Solon Springs - Superior; Bayfield Road to STH 13 (USH 002, Douglas County Solon Springs - Superior) | 1 of 2 | $623,268 | Low, 31% under the second |
| 11 JUL 2023 | 20230711008 | Pierce | Pepin - Hager City; Ush 63 Intersection (STH 035, Pierce County Pepin - Hager City) | 2 of 2 | $1,133,556 | +7.0% |
| 10 JAN 2023 | 20230110031 | St Croix | River Falls - New Richmond; Sth 65 Expansion/70th Av Intersect (STH 065, St Croix County River Falls - New Richmond) | 1 of 4 | $6,473,217 | Low, 0.0% under the second |
How this record was read
WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.
- Every bid counted here matched its published total to within one dollar; WisDOT's rank decides who was low.
- The gap to the low bid is the firm's total over the low total, minus one, on contracts it did not win, leaving out bids over three times the low bid.
- A record covers the lettings in the data, not every contract the firm ever bid. Coverage by year is on the state page.
A name split in two, or a figure that does not match the owner's tabulation? Write to mehdi@miragemetrics.com and we correct it.