WisDOT contract 20251111030 bid tabulation

T Gale, Smikrud Road; Grant Creek Bridge B-61-0296 (LOC STR, Trempealeau County T Gale, Smikrud Road). Let by Wisconsin DOT on November 11, 2025, Trempealeau. 5 bids received; low bid $580,841 by Larson Construction Co., Inc..

Owner
Wisconsin DOT
Letting
11 NOV 2025
Pay items
68
Data through
10 NOV 2026

4 of the 5 bids matched their published totals to within a dollar and are shown; the others are left out.

Bidders

RankBidderTotal bidAgainst the low bid
1Larson Construction Co., Inc.$580,841Low
3Radtke Contractors Inc.$666,302+15%
4Lunda Construction Company$673,297+16%
5Janke General Contractors, Inc.$774,219+33%
WisDOT contract 20251111030: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Larson Construction Co., Inc.2. Radtke Contractors Inc.3. Lunda Construction Company4. Janke General Contractors, Inc.
1Clearing (201.0105)STA2$1,486.73$1,486.73$1,486.73$500.00
2Grubbing (201.0205)STA2$1,486.73$1,486.73$1,486.73$1,000.00
3Removing structure over waterway remove debris (structure) 01. P-61- 0923 (203.0250)EACH1$24,540$32,031$5,662.28$37,000
4Removing asphaltic surface butt joints (204.0115)SY38$23.49$23.49$23.49$23.49
5Removing asphaltic surface milling (204.0120)SY265$23.49$23.49$23.49$23.49
6Excavation common (205.0100)CY1,343$13.33$13.33$13.33$13.00
7Excavation, hauling, and disposal of potential creosote contaminated soil (205.0508.S)TON252$130.73$180.73$180.73$100.00
8Excavation for structures bridges (structure) 01. B-61-0296 (206.1001)EACH1$18,540$37,653$11,284$35,000
9Borrow (208.0100)CY1,232$17.15$17.15$17.15$25.00
10Backfill structure type A (210.1500)TON800$19.21$35.72$19.21$31.00
11Finishing roadway (project) 01. 7282-00-72 (213.0100)EACH1$500.00$500.00$500.00$100.00
12Base aggregate dense 3/4-inch (305.0110)TON435$18.02$18.02$18.02$28.00
13Base aggregate dense 1 1/4-inch (305.0120)TON160$19.23$19.23$19.23$28.00
14Concrete pavement 12-inch (415.0120)SY30$171.68$169.98$169.98$160.00
15Concrete pavement approach slab (415.0410)SY82$328.03$324.78$324.78$255.00
16Tack coat (455.0605)GAL25$13.20$13.20$13.20$13.20
17Asphaltic surface (465.0105)TON75$316.00$316.00$316.00$316.00
18Concrete masonry bridges (502.0100)CY174$645.00$693.21$900.00$975.00
19Protective surface treatment (502.3200)SY205$4.50$3.60$5.00$5.02
20Bar steel reinforcement HS structures (505.0400)LB5,200$1.60$1.35$1.38$2.36
21Bar steel reinforcement HS coated structures (505.0600)LB15,370$1.60$1.44$1.53$2.27
22Railing tubular type M (513.4061)LF78$330.00$313.07$350.00$350.00
23Rubberized membrane waterproofing (516.0500)SY12$65.00$74.42$25.00$45.00
24Temporary structure (station) 01. 50+00 (526.0101)EACH1$16,400$8,036.98$8,036.98$32,000
25Piling steel HP 10-inch X 42 LB (550.1100)LF910$55.00$35.22$38.00$75.00
26Riprap heavy (606.0300)CY200$69.61$67.60$69.61$88.00
27Pipe underdrain wrapped 6-inch (612.0406)LF180$7.52$4.20$7.52$13.00
28Maintenance and repair of haul roads (project) 01. 7282-00-72 (618.0100)EACH1$1.00$500.00$1.00$100.00
29Mobilization (619.1000)EACH1$67,000$122,281$151,866$100,000
30Water (624.0100)MGAL77$32.94$32.94$32.94$10.00
31Topsoil (625.0100)SY1,395$4.55$4.55$4.55$11.00
32Mulching (627.0200)SY1,545$0.60$0.60$0.60$1.00
33Silt fence (628.1504)LF745$2.20$2.20$2.20$3.00
34Silt fence maintenance (628.1520)LF1,490$0.02$0.02$0.02$0.01
35Mobilizations erosion control (628.1905)EACH4$375.00$375.00$375.00$1.00
36Mobilizations emergency erosion control (628.1910)EACH4$200.00$200.00$200.00$1.00
37Erosion mat class II type C (628.2027)SY525$3.80$3.80$3.80$7.50
38Turbidity barriers (628.6005)SY155$43.00$43.00$43.00$32.00
39Temporary ditch checks (628.7504)LF50$8.95$8.95$8.95$9.00
40Fertilizer type B (629.0210)CWT1.30$110.00$110.00$110.00$200.00
41Seeding mixture no. 20 (630.0120)LB94$8.75$8.75$8.75$10.00
42Seeding temporary (630.0200)LB56$3.55$3.55$3.55$5.00
43Seeding borrow pit (630.0300)LB41$10.00$10.00$10.00$7.00
44Seed water (630.0500)MGAL46$1.00$1.00$1.00$20.00
45Delineators temporary (633.1100)EACH33$45.00$18.00$18.00$18.00
46Posts wood 4X6-inch X 14-FT (634.0614)EACH4$108.00$108.00$108.00$100.00
47Signs type II reflective F (637.2230)SF12$28.00$28.00$28.00$35.00
48Removing signs type II (638.2602)EACH4$41.00$41.00$41.00$50.00
49Removing small sign supports (638.3000)EACH4$34.30$34.30$34.30$50.00
50Field office type B (642.5001)EACH1$3,000.00$2,986.08$3,500.00$2,500.00
51Traffic control drums (643.0300)DAY1,260$0.50$0.50$0.50$0.50
52Traffic control barricades type III (643.0420)DAY360$1.00$1.00$1.00$1.00
53Traffic control warning lights type A (643.0705)DAY360$0.25$0.25$0.25$0.25
54Traffic control warning lights type C (643.0715)DAY900$0.35$0.35$0.35$0.35
55Traffic control signs (643.0900)DAY2,610$1.25$1.25$1.25$1.25
56Traffic control (643.5000)EACH1$2,100.00$2,100.00$2,100.00$2,100.00
57Geotextile type DF schedule A (645.0111)SY120$5.06$5.05$5.06$3.25
58Geotextile type HR (645.0120)SY370$3.64$5.26$3.64$4.25
59Geotextile type sas (645.0140)SY1,345$2.18$2.18$2.18$2.75
60Construction staking subgrade (650.4500)LF473$0.01$0.01$0.01$0.01
61Construction staking base (650.5000)LF473$0.01$0.01$0.80$0.01
62Construction staking structure layout (structure) 01. B-61-0296 (650.6501)EACH1$2,500.00$2,500.00$3,000.00$2,500.00
63Construction staking supplemental control (project) 01. 7282-00-72 (650.9911)EACH1$1,750.00$1,750.00$500.00$1,750.00
64Construction staking slope stakes (650.9920)LF473$0.01$0.01$2.00$0.01
65Sawing asphalt (690.0150)LF32$2.95$2.95$2.95$2.45
66Incentive strength concrete structures (715.0502)DOL1,044$1.00$1.00$1.00$1.00
67Installing and maintaining bird deterrent system (station) 01. 10+00 (999.2000.S)EACH1$1.00$250.00$0.01$2,500.00
68Special 01. removing existing timber piling (SPV.0090)LF120$12.00$26.74$26.74$40.00
WisDOT contract 20251111030: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.

Every contract let that day: WisDOT letting of November 11, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.