WisDOT contract 20251209012 bid tabulation

C New Lisbon - IH 90; Ltl Lemonweir Rvr Bridge B-29-0168 (CTH M, Juneau County C New Lisbon - IH 90). Let by Wisconsin DOT on December 9, 2025, Juneau. 6 bids received; low bid $928,881 by Larson Construction Co., Inc..

Owner
Wisconsin DOT
Letting
09 DEC 2025
Pay items
61
Data through
10 NOV 2026

5 of the 6 bids matched their published totals to within a dollar and are shown; the others are left out.

Bidders

RankBidderTotal bidAgainst the low bid
1Larson Construction Co., Inc.$928,881Low
2Sheet Piling Services LLC$991,584+7.0%
3Lunda Construction Company$999,063+8.0%
4Radtke Contractors Inc.$1,095,133+18%
6Zenith Tech., Inc. - Waukesha$1,493,834+61%
WisDOT contract 20251209012: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Larson Construction Co., Inc.2. Sheet Piling Services LLC3. Lunda Construction Company4. Radtke Contractors Inc.5. Zenith Tech., Inc. - Waukesha
1Removing structure over waterway remove debris (structure) .01 B-29- 14 (203.0250)EACH1$67,940$100,000$100,000$77,030$225,000
2Removing asphaltic surface milling (204.0120)SY460$23.64$23.64$23.64$23.64$23.64
3Removing guardrail (204.0165)LF210$4.40$4.40$4.40$4.40$3.00
4Excavation common (205.0100)CY184$19.51$19.32$19.32$19.32$19.32
5Excavation for structures bridges (structure) .01 B-29-168 (206.1001)EACH1$24,900$52,313$27,313$58,603$40,000
6Cofferdams (structure) .01 B-29-168 (206.5001)EACH1$38,400$50,000$80,000$141,015$147,000
7Borrow (208.0100)CY1,436$13.41$13.28$13.28$13.28$13.28
8Backfill structure type A (210.1500)TON440$16.59$16.43$16.43$37.07$16.43
9Finishing roadway (project) .01 7382-00-71 (213.0100)EACH1$300.00$0.01$500.00$1,000.00$2,600.00
10Base aggregate dense 3/4-inch (305.0110)TON163$40.77$40.37$40.37$40.37$40.37
11Base aggregate dense 1 1/4-inch (305.0120)TON580$24.30$24.06$24.06$24.06$24.06
12Tack coat (455.0605)GAL46$0.01$0.01$0.01$0.01$0.01
13Asphaltic surface (465.0105)TON176$128.95$128.95$128.95$128.95$128.95
14Concrete masonry bridges (502.0100)CY353$709.00$900.00$850.00$717.61$1,150.00
15Protective surface treatment (502.3200)SY483$3.00$2.50$5.00$3.69$4.15
16Underwater substructure inspection (structure) .01 B-29-168 (502.9000.S)EACH1$4,550.00$5,200.00$7,500.00$500.00$5,500.00
17Bar steel reinforcement HS structures (505.0400)LB8,690$1.50$1.35$1.15$1.37$1.50
18Bar steel reinforcement HS coated structures (505.0600)LB49,570$1.50$1.45$1.25$1.34$1.60
19Railing tubular type M (513.4061)LF233$351.00$325.00$300.00$256.66$315.00
20Rubberized membrane waterproofing (516.0500)SY12$61.00$18.00$25.00$64.32$60.00
21Piling steel HP 10-inch X 42 LB (550.1100)LF1,295$56.00$40.00$40.00$41.38$65.00
22Riprap heavy (606.0300)CY160$83.86$83.03$83.03$89.29$83.03
23Pipe underdrain wrapped 6-inch (612.0406)LF160$7.92$7.84$7.84$4.26$7.84
24MGS thrie beam transition (614.2500)LF157.60$94.10$94.10$94.10$94.10$98.00
25MGS guardrail terminal eat (614.2610)EACH4$3,428.00$3,428.00$3,428.00$3,428.00$4,000.00
26Maintenance and repair of haul roads (project) .01 7382-00-71 (618.0100)EACH1$1,500.00$0.01$1.00$500.00$3,800.00
27Mobilization (619.1000)EACH1$92,680$66,760$98,937$169,007$200,000
28Water (624.0100)MGAL7.60$37.46$37.09$37.09$37.09$37.09
29Salvaged topsoil (625.0500)SY1,550$1.41$1.41$1.41$1.41$1.41
30Silt fence (628.1504)LF1,200$2.15$2.15$2.15$2.15$2.25
31Silt fence maintenance (628.1520)LF1,854$0.01$0.01$0.01$0.01$0.02
32Mobilizations erosion control (628.1905)EACH5$500.00$500.00$500.00$500.00$150.00
33Mobilizations emergency erosion control (628.1910)EACH4$100.00$100.00$100.00$100.00$200.00
34Erosion mat urban class I type B (628.2008)SY1,550$2.00$2.00$2.00$2.00$1.50
35Turbidity barriers (628.6005)SY325$41.10$41.10$41.10$41.10$45.00
36Fertilizer type B (629.0210)CWT2.50$195.50$195.50$195.50$195.50$75.00
37Seeding mixture no. 30 (630.0130)LB125$14.10$14.10$14.10$14.10$7.50
38Seeding temporary (630.0200)LB75$5.00$5.00$5.00$5.00$3.50
39Seed water (630.0500)MGAL60$0.10$0.10$0.10$0.10$1.00
40Posts wood 4X6-inch X 12-FT (634.0612)EACH4$83.80$83.80$83.80$83.80$75.00
41Posts wood 4X6-inch X 14-FT (634.0614)EACH3$89.60$89.60$89.60$89.60$75.00
42Signs type II reflective F (637.2230)SF31.56$27.00$27.00$27.00$27.00$30.00
43Removing signs type II (638.2602)EACH7$22.00$22.00$22.00$22.00$25.00
44Removing small sign supports (638.3000)EACH7$22.00$22.00$22.00$22.00$25.00
45Field office type B (642.5001)EACH1$4,200.00$4,000.00$4,000.00$2,629.04$8,000.00
46Traffic control barricades type III (643.0420)DAY2,599$0.90$0.90$0.90$0.90$0.69
47Traffic control warning lights type A (643.0705)DAY5,198$0.10$0.10$0.10$0.10$0.08
48Traffic control signs (643.0900)DAY2,260$0.25$0.25$0.25$0.25$0.83
49Traffic control (643.5000)EACH1$2,000.00$2,000.00$2,000.00$3,076.10$5,999.00
50Geotextile type DF schedule A (645.0111)SY68$8.49$8.41$8.41$4.71$8.41
51Geotextile type HR (645.0120)SY302$3.72$3.68$3.68$5.10$3.68
52Marking line paint 4-inch (646.1005)LF786$4.87$4.50$6.20$4.87$6.20
53Construction staking subgrade (650.4500)LF280$0.01$0.01$0.01$0.01$0.01
54Construction staking base (650.5000)LF280$1.00$1.00$1.00$1.00$1.00
55Construction staking structure layout (structure) .01 B-29-0168 (650.6501)EACH1$3,000.00$3,000.00$3,000.00$3,000.00$3,000.00
56Construction staking supplemental control (project) .01 7382-00-71 (650.9911)EACH1$1,000.00$1,000.00$1,000.00$1,000.00$1,000.00
57Construction staking slope stakes (650.9920)LF280$1.00$1.00$1.00$1.00$1.00
58Sawing asphalt (690.0150)LF90$2.95$2.95$2.95$2.95$2.95
59Incentive strength concrete structures (715.0502)DOL2,118$1.00$1.00$1.00$1.00$1.00
60Installing and maintaining bird deterrent system (station) .01 14+00 (999.2000.S)EACH1$4,100.00$0.01$0.01$0.01$5,500.00
61Special .01 flashing stainless steel (SPV.0090)LF217$96.00$40.00$40.00$54.52$77.00
WisDOT contract 20251209012: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.

Every contract let that day: WisDOT letting of December 9, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.