WisDOT contract 20251209024 bid tabulation

STH 15 - CTH Jj; Everglade Road - CTH Jj (STH 076, Outagamie County STH 15 - CTH JJ). Let by Wisconsin DOT on December 9, 2025, Outagamie. 4 bids received; low bid $9,278,132 by Michels Road & Stone, Inc..

Owner
Wisconsin DOT
Letting
09 DEC 2025
Pay items
255
Data through
10 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Michels Road & Stone, Inc.$9,278,132Low
2Vinton Construction Company$9,294,0630.0%
3Zignego Company, Inc.$9,773,237+5.0%
4Peters Concrete Company$10,698,510+15%
WisDOT contract 20251209024: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Michels Road & Stone, Inc.2. Vinton Construction Company3. Zignego Company, Inc.4. Peters Concrete Company
1Clearing (201.0105)STA46$633.00$633.00$600.00$800.00
2Clearing (201.0120)ID206$29.54$29.54$10.00$25.00
3Grubbing (201.0205)STA46$311.23$311.23$300.00$400.00
4Grubbing (201.0220)ID206$10.55$10.55$30.00$20.00
5Removing small pipe culverts (203.0100)EACH52$350.00$342.31$150.00$200.00
6Removing concrete pavement (204.0100)SY15,100$1.00$1.50$3.20$0.50
7Removing curb & gutter (204.0150)LF1,975$4.00$3.75$3.45$3.50
8Removing concrete sidewalk (204.0155)SY70$10.00$6.57$3.90$10.00
9Removing fence (204.0170)LF690$3.00$4.00$3.00$3.00
10Removing surface drains (204.0190)EACH1$400.00$385.00$250.00$400.00
11Removing concrete bases (204.0195)EACH4$200.00$200.00$175.00$200.00
12Removing manholes (204.0210)EACH4$400.00$416.14$400.00$695.00
13Removing inlets (204.0220)EACH1$400.00$283.75$400.00$500.00
14Removing storm sewer (size) 01. 18-inch (204.0245)LF65$12.00$12.69$12.00$25.00
15Removing storm sewer (size) 02. 24-inch (204.0245)LF500$12.00$15.13$12.00$24.00
16Removing storm sewer (size) 03. 30-inch (204.0245)LF47$22.00$22.02$22.00$36.80
17Removing storm sewer (size) 04. 36-inch (204.0245)LF124$22.00$25.54$22.00$36.00
18Removing storm sewer (size) 05. 42-inch (204.0245)LF131$28.00$29.81$28.00$38.00
19Removing storm sewer (size) 06. 4- inch (204.0245)LF60$10.00$9.46$10.00$11.00
20Removing (item description) 01. business sign, sta 282+90 'RNB' (204.9060.S)EACH1$1,200.00$2,500.00$1,200.00$1,200.00
21Removing (item description) 02. flashing stop sign assembly (204.9060.S)EACH2$550.00$550.00$550.00$400.00
22Excavation common (205.0100)CY57,962$12.10$19.93$10.30$18.66
23Excavation for structures culverts (structure) 01. C-44-0140 (206.2001)EACH1$14,000$15,000$22,750$106,750
24Excavation for structures culverts (structure) 02. C-44-0141 (206.2001)EACH1$10,500$14,000$16,250$84,125
25Excavation for structures culverts (structure) 03. C-44-0142 (206.2001)EACH1$10,500$14,000$21,930$85,250
26Excavation for structures culverts (structure) 04. C-44-0143 (206.2001)EACH1$10,500$14,000$22,050$85,250
27Backfill structure type B (210.2500)TON2,018$34.00$26.70$24.00$19.75
28Finishing roadway (project) 01. 6517-16-71 (213.0100)EACH1$5,000.00$5,000.00$1,000.00$5,000.00
29Base aggregate dense 3/4-inch (305.0110)TON725$23.80$37.00$26.50$40.00
30Base aggregate dense 1 1/4-inch (305.0120)TON24,850$11.80$12.25$9.25$14.95
31Base aggregate open-graded (310.0115)CY30$90.00$57.13$50.00$40.00
32Breaker run (311.0110)TON397$21.50$33.10$16.18$17.00
33Select crushed material (312.0110)TON24,874$10.60$22.25$12.70$19.75
34Coloring concrete wisdot red (405.0100)CY435$80.00$96.25$80.00$96.25
35Concrete pavement 8-inch (415.0080)SY34,610$56.46$54.43$59.33$54.43
36Concrete pavement gaps (415.0210)EACH4$1,500.00$1,500.00$1,000.00$1,500.00
37Concrete truck apron 12-inch (415.2010)SY600$90.00$84.00$90.00$84.00
38Concrete pavement joint filling (415.4100)SY41,475$1.78$1.30$1.50$1.30
39HMA cold weather paving (450.4000)TON1,598$4.20$4.20$3.00$3.00
40Tack coat (455.0605)GAL585$5.45$5.45$3.90$3.90
41Incentive density HMA pavement (460.2000)DOL1,350$1.00$1.00$1.00$1.00
42HMA pavement 3 MT 58-28 S (460.6223)TON1,310$88.20$88.20$90.00$90.00
43HMA pavement 4 MT 58-28 H (460.6424)TON800$106.20$106.20$100.00$100.00
44Asphaltic surface (465.0105)TON28$210.00$210.00$171.00$171.00
45Asphaltic surface driveways and field entrances (465.0120)TON250$145.00$145.00$155.00$155.00
46Asphaltic flumes (465.0315)SY7$81.00$81.00$75.00$75.00
47Concrete masonry culverts (504.0100)CY261$805.00$1,100.83$805.00$0.10
48Bar steel reinforcement HS structures (505.0400)LB41,995$1.06$0.01$1.06$0.10
49Bar steel reinforcement HS coated structures (505.0600)LB2,160$1.16$0.01$1.16$0.10
50Temporary shoring (location) 01. sta. 213+50, LT (511.1300)SF1,275$39.00$0.01$39.00$30.00
51Rubberized membrane waterproofing (516.0500)SY105$49.00$49.00$49.00$20.00
52Sheet membrane waterproofing for buried structures (516.0610.S)SY225$85.00$84.00$85.00$59.00
53Apron endwalls for culvert pipe 12- inch (520.1012)EACH2$191.00$386.75$191.00$175.00
54Apron endwalls for culvert pipe 24- inch (520.1024)EACH5$442.00$647.00$442.00$400.00
55Apron endwalls for culvert pipe 36- inch (520.1036)EACH1$1,075.00$1,173.75$1,075.00$1,300.00
56Culvert pipe temporary 18-inch (520.2018)LF26$50.00$62.12$55.00$50.00
57Apron endwalls for culvert pipe sloped side drains steel 18-inch 6 to 1 (521.1518)EACH4$1,337.00$1,443.75$1,337.00$1,500.00
58Apron endwalls for culvert pipe sloped side drains steel 24-inch 6 to 1 (521.1524)EACH4$1,982.00$2,082.00$1,983.00$2,250.00
59Culvert pipe corrugated steel 18- inch (521.3118)LF61$64.00$69.35$64.00$76.00
60Culvert pipe corrugated steel 24- inch (521.3124)LF78$69.00$77.39$69.00$93.00
61Culvert pipe reinforced concrete class IV 15-inch (522.0415)LF47$69.00$84.88$69.00$98.00
62Culvert pipe reinforced concrete class IV 24-inch (522.0424)LF52$99.00$118.71$99.00$127.00
63Apron endwalls for culvert pipe reinforced concrete 12-inch (522.1012)EACH1$961.00$1,172.00$1,219.00$1,500.00
64Apron endwalls for culvert pipe reinforced concrete 15-inch (522.1015)EACH3$1,149.00$1,285.00$1,324.00$1,600.00
65Apron endwalls for culvert pipe reinforced concrete 24-inch (522.1024)EACH2$1,562.00$1,623.23$1,684.00$2,300.00
66Apron endwalls for culvert pipe reinforced concrete 36-inch (522.1036)EACH1$2,771.00$2,671.25$2,766.00$3,200.00
67Apron endwalls for culvert pipe reinforced concrete 42-inch (522.1042)EACH1$4,337.00$3,274.60$3,297.00$3,700.00
68Culvert pipe reinforced concrete horizontal elliptical class HE-III 24X38-inch (522.2324)LF125$201.00$173.28$177.00$215.00
69Culvert pipe reinforced concrete horizontal elliptical class HE-IV 19X30-inch (522.2419)LF75$169.00$163.23$180.00$213.00
70Apron endwalls for culvert pipe reinforced concrete horizontal elliptical 19X30-inch (522.2619)EACH4$1,391.00$2,065.25$1,821.00$2,400.00
71Apron endwalls for culvert pipe reinforced concrete horizontal elliptical 24X38-inch (522.2624)EACH3$1,653.00$2,511.67$2,359.00$2,950.00
72Apron endwalls for culvert pipe reinforced concrete horizontal elliptical 38X60-inch (522.2638)EACH6$5,711.00$3,926.67$3,984.00$4,400.00
73Culvert pipe salvaged 42-inch (524.0142)LF32$115.00$106.41$113.00$150.00
74Apron endwalls for culvert pipe salvaged 42-inch (524.0642)EACH4$810.00$2,021.50$810.00$1,825.00
75Concrete curb & gutter 18-inch type A (601.0405)LF233$23.00$19.75$23.00$19.75
76Concrete curb & gutter 30-inch type A (601.0409)LF19,530$20.00$21.25$21.00$21.25
77Concrete curb & gutter 30-inch type D (601.0411)LF533$24.00$37.00$24.00$37.00
78Concrete curb & gutter 4-inch sloped 36-inch type A (601.0551)LF1,945$24.50$25.70$24.50$25.70
79Concrete curb & gutter 4-inch sloped 30-inch type R (601.0581)LF333$26.00$26.00$26.00$26.00
80Concrete curb pedestrian (601.0600)LF203$58.00$45.00$58.00$45.00
81Concrete sidewalk 4-inch (602.0405)SF18,870$6.50$6.70$6.60$6.70
82Concrete sidewalk 5-inch (602.0410)SF69,030$6.65$5.90$6.70$5.90
83Curb ramp detectable warning field yellow (602.0505)SF554$52.00$34.00$52.00$34.00
84Curb ramp detectable warning field radial yellow (602.0605)SF211.83$58.00$55.00$58.00$55.00
85Concrete driveway 6-inch (602.0810)SY1,685$66.00$67.00$68.00$67.00
86Riprap light (606.0100)CY646$74.00$75.00$96.00$65.00
87Storm sewer pipe reinforced concrete class IV 12-inch (608.0412)LF815$70.00$75.51$70.00$100.50
88Storm sewer pipe reinforced concrete class IV 15-inch (608.0415)LF119$70.00$82.21$72.00$105.00
89Storm sewer pipe reinforced concrete class IV 18-inch (608.0418)LF8$78.00$88.60$74.00$150.00
90Storm sewer pipe reinforced concrete class IV 24-inch (608.0424)LF679$102.00$104.06$101.00$118.00
91Storm sewer pipe reinforced concrete class IV 36-inch (608.0436)LF1,253$282.00$274.13$302.00$323.50
92Storm sewer pipe reinforced concrete class IV 42-inch (608.0442)LF133$240.00$220.79$237.00$256.00
93Storm sewer pipe reinforced concrete horizontal elliptical class HE-IV 19X30-inch (608.2419)LF311$148.00$163.81$161.00$183.50
94Storm sewer pipe reinforced concrete horizontal elliptical class HE-IV 24X38-inch (608.2424)LF89$187.00$193.35$187.00$220.00
95Storm sewer pipe class III-A 12- inch (608.3012)LF846$57.00$65.50$58.00$87.00
96Storm sewer pipe class III-A 15- inch (608.3015)LF88$61.00$69.45$62.00$88.50
97Storm sewer pipe class III-A 18- inch (608.3018)LF122$64.00$81.98$66.00$90.50
98Storm sewer pipe class III-A 24- inch (608.3024)LF4,063$80.00$78.23$81.00$113.95
99Storm sewer pipe class III-A 36- inch (608.3036)LF712$143.00$132.12$143.00$186.50
100Storm sewer pipe class III-B 24- inch (608.3624)LF660$155.00$134.63$155.00$181.50
101Manhole covers type J (611.0530)EACH35$551.00$444.00$550.00$500.00
102Manhole covers type L (611.0545)EACH5$414.00$408.20$414.00$400.00
103Inlet covers type C (611.0612)EACH1$577.00$444.00$577.00$525.00
104Inlet covers type H (611.0624)EACH51$815.00$655.00$800.00$750.00
105Inlet covers type HM (611.0627)EACH4$815.00$655.00$800.00$750.00
106Inlet covers type HM-S (611.0636)EACH2$815.00$662.00$800.00$750.00
107Inlet covers type H-S (611.0639)EACH16$815.00$662.00$800.00$750.00
108Inlet covers type MS-A (611.0645)EACH15$588.00$497.00$588.00$500.00
109Inlet covers type T (611.0652)EACH3$1,108.00$939.00$1,100.00$1,050.00
110Manholes 4-FT diameter (611.2004)EACH19$3,165.00$4,236.26$3,524.00$3,855.00
111Manholes 5-FT diameter (611.2005)EACH18$4,626.00$6,267.53$5,800.00$5,950.00
112Manholes 6-FT diameter (611.2006)EACH3$5,816.00$7,177.17$6,750.00$6,650.00
113Manholes 7-FT diameter (611.2007)EACH2$9,630.00$11,191$9,800.00$10,010
114Inlets 4-FT diameter (611.3004)EACH12$2,945.00$4,114.75$3,300.00$3,410.00
115Inlets 2X3-FT (611.3230)EACH58$2,575.00$2,586.07$2,681.00$2,305.00
116Inlets median 1 grate (611.3901)EACH13$2,378.00$3,092.87$2,800.00$2,650.00
117Inlets median 2 grate (611.3902)EACH1$3,500.00$3,547.50$3,500.00$2,850.00
118Adjusting manhole covers (611.8110)EACH1$525.00$525.00$525.00$875.00
119Adjusting inlet covers (611.8115)EACH2$525.00$525.00$525.00$915.00
120Pipe grates (size) 01. 36-inch (611.9850.S)EACH2$1,481.00$3,331.00$1,481.00$3,775.00
121Pipe grates (size) 02. 42-inch (611.9850.S)EACH1$1,900.00$4,081.00$1,900.00$4,550.00
122Pipe grates (size) 03. 24X38-inch (611.9850.S)EACH3$950.00$2,170.00$950.00$2,525.00
123Pipe grates (size) 04. 38X60-inch (611.9850.S)EACH6$1,800.00$3,896.00$1,800.00$4,275.00
124Pipe underdrain 6-inch (612.0106)LF500$11.70$20.19$18.00$29.50
125Apron endwalls for underdrain reinforced concrete 6-inch (612.0806)EACH2$500.00$305.25$375.00$400.00
126Maintenance and repair of haul roads (project) 01. 6517-16-71 (618.0100)EACH1$1.00$0.01$1.00$1,000.00
127Mobilization (619.1000)EACH1$515,314$1,000.00$935,000$737,000
128Concrete median sloped nose (620.0300)SF821$15.00$14.00$15.00$14.00
129Dust control surface treatment (623.0200)SY26,195$0.01$0.01$0.01$0.25
130Water (624.0100)MGAL480$65.00$0.01$35.25$40.00
131Topsoil (625.0100)SY27,300$5.30$0.01$4.55$5.83
132Salvaged topsoil (625.0500)SY28,000$2.00$3.90$3.25$5.83
133Mulching (627.0200)SY500$0.75$1.00$0.75$0.75
134Silt fence (628.1504)LF19,500$1.88$2.00$1.88$1.88
135Silt fence maintenance (628.1520)LF19,500$0.01$0.01$0.01$0.01
136Mobilizations erosion control (628.1905)EACH16$100.00$1.00$100.00$100.00
137Mobilizations emergency erosion control (628.1910)EACH8$100.00$1.00$100.00$100.00
138Erosion mat class I type B (628.2004)SY10,000$1.30$1.25$1.30$1.30
139Erosion mat urban class I type B (628.2008)SY38,300$1.65$2.00$1.65$1.65
140Erosion mat class II type C (628.2027)SY7,500$2.50$3.50$2.50$2.50
141Inlet protection type A (628.7005)EACH92$10.00$50.00$10.00$10.00
142Inlet protection type C (628.7015)EACH84$68.00$125.00$68.00$68.00
143Temporary ditch checks (628.7504)LF480$7.00$8.00$7.00$7.00
144Culvert pipe checks (628.7555)EACH85$13.00$12.00$13.00$13.00
145Tracking pads (628.7560)EACH4$2,100.00$0.01$900.00$1,500.00
146Rock bags (628.7570)EACH90$13.00$12.00$13.00$13.00
147Fertilizer type B (629.0210)CWT35$90.00$125.00$90.00$90.00
148Seeding mixture no. 40 (630.0140)LB2,450$7.65$7.00$7.65$7.65
149Seeding temporary (630.0200)LB400$4.00$2.00$4.00$4.00
150Seed water (630.0500)MGAL3,100$1.00$0.01$1.00$1.00
151Markers culvert end (633.5200)EACH22$70.00$85.00$70.00$70.00
152Posts wood 4X6-inch X 14-FT (634.0614)EACH39$86.00$125.00$86.00$86.00
153Posts wood 4X6-inch X 16-FT (634.0616)EACH29$88.00$135.00$88.00$88.00
154Posts wood 4X6-inch X 18-FT (634.0618)EACH13$92.00$145.00$92.00$92.00
155Posts tubular steel 2X2-inch X 12- FT (634.0812)EACH2$215.00$300.00$215.00$215.00
156Signs type II reflective H (637.2210)SF601.62$22.25$26.00$22.25$22.25
157Signs type II reflective F (637.2230)SF121.25$23.60$28.00$23.60$23.60
158Removing signs type II (638.2602)EACH49$30.00$50.00$30.00$30.00
159Removing small sign supports (638.3000)EACH55$30.00$50.00$30.00$30.00
160Pond liner clay (640.1303.S)CY3,030$39.00$22.73$13.75$34.00
161Field office type C (642.5201)EACH1$21,000$10,000$20,000$12,000
162Traffic control drums (643.0300)DAY2,700$0.75$0.75$0.25$0.25
163Traffic control barricades type III (643.0420)DAY6,150$1.00$1.00$0.50$0.50
164Traffic control warning lights type A (643.0705)DAY12,300$0.15$0.15$0.10$0.10
165Traffic control warning lights type C (643.0715)DAY100$0.10$0.10$0.15$0.15
166Traffic control signs (643.0900)DAY45,832$0.35$0.35$0.30$0.30
167Traffic control covering signs type II (643.0920)EACH18$25.00$25.00$100.00$100.00
168Traffic control signs PCMS (643.1050)DAY126$50.00$50.00$50.00$50.00
169Temporary marking line removable tape 6-inch (643.3180)LF600$1.25$1.25$3.00$3.00
170Temporary marking removable mask out tape 6-inch (643.3960)LF150$2.00$2.00$2.65$2.65
171Traffic control (643.5000)EACH1$10,500$10,500$5,000.00$5,000.00
172Temporary pedestrian surface asphalt (644.1410)SF1,100$15.00$8.50$7.00$5.75
173Temporary pedestrian surface plate (644.1430)SF150$7.99$7.99$5.50$30.00
174Temporary pedestrian curb ramp (644.1601)DAY20$13.00$13.00$20.00$20.00
175Temporary pedestrian detectable warning field (644.1605)SF60$10.00$10.00$5.00$5.00
176Temporary pedestrian barricade (644.1810)LF950$4.50$4.50$8.00$8.00
177Geotextile type C (645.0105)SY803$3.00$3.25$3.10$2.00
178Geotextile type DF schedule A (645.0111)SY340$8.00$2.91$7.00$2.00
179Geotextile type R (645.0130)SY2,043$4.00$3.00$2.15$3.00
180Geotextile type sas (645.0140)SY26,195$2.50$1.75$1.55$1.65
181Marking line paint 4-inch (646.1005)LF100$5.00$5.00$0.60$5.00
182Marking line epoxy 6-inch (646.2020)LF20,085$0.53$0.53$0.90$0.53
183Marking line grooved wet ref epoxy 6-inch (646.2040)LF34,370$1.57$1.57$1.85$1.57
184Marking line epoxy 10-inch (646.4020)LF200$1.18$1.18$1.60$1.18
185Marking line grooved wet ref epoxy 10-inch (646.4040)LF700$3.15$3.15$3.50$3.15
186Marking arrow paint (646.5005)EACH5$269.00$269.00$200.00$269.00
187Marking arrow epoxy (646.5020)EACH6$426.70$426.70$285.00$426.70
188Marking word epoxy (646.5120)EACH3$431.74$431.74$340.00$431.74
189Marking railroad crossing epoxy (646.5320)EACH2$4,188.48$4,188.48$2,200.00$4,188.48
190Marking outfall epoxy (646.5520)EACH2$55.52$55.52$17.00$55.52
191Marking dotted extension epoxy 18-inch (646.6320)LF88$17.87$17.87$24.00$17.87
192Cold weather marking epoxy 6-inch (646.6466)LF15,875$0.53$0.01$0.35$0.53
193Cold weather marking epoxy 10- inch (646.6470)LF200$1.18$0.01$0.60$1.18
194Marking diagonal epoxy 12-inch (646.7120)LF450$17.42$17.42$14.00$17.42
195Marking crosswalk epoxy transverse line 6-inch (646.7420)LF1,830$16.97$16.97$16.50$16.97
196Marking curb epoxy (646.8120)LF80$8.56$8.56$17.00$8.56
197Marking island nose epoxy (646.8220)EACH8$320.70$320.70$330.00$320.70
198Construction staking storm sewer (650.4000)EACH149$60.00$60.00$60.00$60.00
199Construction staking subgrade (650.4500)LF10,954$0.01$0.01$0.01$0.01
200Construction staking base (650.5000)LF2,913$0.10$0.10$0.10$0.10
201Construction staking curb gutter and curb & gutter (650.5500)LF788$2.00$2.00$2.00$2.00
202Construction staking pipe culverts (650.6000)EACH13$100.00$100.00$100.00$100.00
203Construction staking structure layout (structure) 01. C-44-0140 (650.6501)EACH1$1,500.00$1,500.00$1,500.00$1,500.00
204Construction staking structure layout (structure) 02. C-44-0141 (650.6501)EACH1$1,500.00$1,500.00$1,500.00$1,500.00
205Construction staking structure layout (structure) 03. C-44-0142 (650.6501)EACH1$1,500.00$1,500.00$1,500.00$1,500.00
206Construction staking structure layout (structure) 04. C-44-0143 (650.6501)EACH1$1,500.00$1,500.00$1,500.00$1,500.00
207Construction staking concrete pavement (650.7000)LF8,285$0.40$1.25$1.50$1.25
208Construction staking electrical installations (project) 01. 6517-16- 71 (650.8501)EACH1$2,000.00$2,000.00$2,000.00$2,000.00
209Construction staking curb ramps (650.9000)EACH38$100.00$100.00$100.00$100.00
210Construction staking sidewalk (project) 01. 6517-16-71 (650.9500)EACH1$8,000.00$3,700.00$100.00$100.00
211Construction staking supplemental control (project) 01. 6517-16-71 (650.9911)EACH1$10.00$10.00$10.00$10.00
212Construction staking slope stakes (650.9920)LF11,508$0.60$0.60$0.60$0.60
213Conduit rigid nonmetallic schedule 40 2-inch (652.0225)LF1,840$10.00$10.00$10.00$10.00
214Pull boxes non-conductive 24X42- inch (653.0164)EACH8$1,950.00$1,950.00$1,950.00$1,950.00
215Concrete bases type 5 (654.0105)EACH16$1,575.00$1,575.00$1,575.00$1,575.00
216Concrete control cabinet bases type 10 (654.0220)EACH1$2,200.00$2,200.00$2,200.00$2,200.00
217Electrical wire lighting 12 AWG (655.0610)LF2,400$0.95$0.95$0.95$0.95
218Electrical wire lighting 10 AWG (655.0615)LF7,671$1.00$1.00$1.00$1.00
219Electrical service meter breaker pedestal (location) 01. STH 76 & CTH JJ (656.0201)EACH1$1,950.00$1,950.00$1,950.00$1,950.00
220Transformer bases breakaway 11 1/2-inch bolt circle (657.0255)EACH16$620.00$620.00$620.00$620.00
221Poles type 5-aluminum (657.0322)EACH16$1,650.00$1,650.00$1,650.00$1,650.00
222Luminaire arms truss type 4 1/2- inch clamp 12-FT (657.0710)EACH16$700.00$700.00$700.00$700.00
223Luminaires utility LED B (659.1120)EACH16$365.00$365.00$356.00$365.00
224Sawing asphalt (690.0150)LF1,098$0.85$3.00$1.69$1.69
225Sawing concrete (690.0250)LF268$2.50$3.00$2.75$2.75
226Incentive strength concrete structures (715.0502)DOL2,000$1.00$1.00$1.00$1.00
227Incentive compressive strength concrete pavement (715.0720)DOL10,385$1.00$1.00$1.00$1.00
228Incentive iri ride (740.0440)DOL14,910$1.00$1.00$1.00$1.00
229On-the-job training apprentice at $5.00/HR (ASP.1T0A)HRS2,400$5.00$5.00$5.00$5.00
230On-the-job training graduate at $5.00/HR (ASP.1T0G)HRS4,400$5.00$5.00$5.00$5.00
231Special 01. foundation backfill (SPV.0035)CY170$36.00$35.00$44.00$40.00
232Special 02. streambed material (SPV.0035)CY210$60.00$68.98$48.00$44.00
233Special 01. construction staking roundabout (SPV.0060)EACH1$15,000$15,000$15,000$15,000
234Special 02. concrete pipe support (SPV.0060)EACH4$1,130.00$1,067.50$1,130.00$4,500.00
235Special 03. storm sewer plug 36- inch (SPV.0060)EACH1$380.00$449.75$380.00$450.00
236Special 04. inlets 4-FT diameter, special (SPV.0060)EACH3$3,078.00$3,840.33$3,450.00$4,250.00
237Special 05. hillview pond outlet structure (SPV.0060)EACH1$6,202.00$8,256.50$6,202.00$8,400.00
238Special 06. glen valley pond outlet structure (SPV.0060)EACH1$5,324.00$7,324.50$8,091.00$5,750.00
239Special 07. detention pond anti- seep collar (SPV.0060)EACH2$590.00$992.50$590.00$750.00
240Special 08. manhole 6-FT riser pipe grate (SPV.0060)EACH1$3,014.00$3,219.50$2,957.00$3,610.00
241Special 09. remove, salvage and reinstall snow plow blade (SPV.0060)EACH1$700.00$1,500.00$700.00$700.00
242Special 10. removing sign, foundation and landscaping (SPV.0060)EACH1$3,800.00$3,000.00$3,800.00$3,800.00
243Special 11. mini storm sewer cleanouts (SPV.0060)EACH26$525.00$691.54$525.00$575.00
244Special 12. adjusting sanitary manhole covers (SPV.0060)EACH18$615.00$675.00$615.00$900.00
245Special 13. adjusting water valve boxes (SPV.0060)EACH42$444.00$290.48$444.00$225.00
246Special 14. reconstruct sanitary manhole (SPV.0060)EACH8$975.00$1,868.75$975.00$3,250.00
247Special 15. cleaning box culvert B- 44-0262 (SPV.0060)EACH1$1,200.00$6,500.00$6,875.00$23,150
248Special 01. seeding low maintenance fescue (SPV.0085)LB25$10.00$20.00$10.00$10.00
249Special 01. culvert pipe reinforced concrete horizontal elliptical class HE-IV 38X60-inc (SPV.0090)LF258$370.00$354.72$370.00$396.00
250Special 02. concrete curb & gutter 30-inch type D special (SPV.0090)LF110$55.00$26.25$55.00$26.25
251Special 03. concrete curb & gutter 24-inch type D special (SPV.0090)LF46$55.00$53.50$55.00$53.50
252Special 04. mini storm sewer lateral 4-inch (SPV.0090)LF470$66.00$55.00$75.00$72.75
253Special 05. mini storm sewer trunk 6-inch (SPV.0090)LF2,325$31.00$30.00$60.00$65.15
254Special 06. pipe underdrain railroad 6-inch (SPV.0090)LF100$58.00$70.03$60.00$139.00
255Special 01. insulation board (2-inch) (SPV.0165)SF200$8.00$3.73$8.00$3.50
WisDOT contract 20251209024: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.

Every contract let that day: WisDOT letting of December 9, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy