WisDOT contract 20260113004 bid tabulation

T Hebron, Hagedorn Road; Duck Creek Bridge B-28-0204 (LOC STR, Jefferson County T Hebron, Hagedorn Road). Let by Wisconsin DOT on January 13, 2026, Jefferson. 5 bids received; low bid $413,001 by Radtke Contractors Inc..

Owner
Wisconsin DOT
Letting
13 JAN 2026
Pay items
59
Data through
10 NOV 2026

4 of the 5 bids matched their published totals to within a dollar and are shown; the others are left out.

Bidders

RankBidderTotal bidAgainst the low bid
1Radtke Contractors Inc.$413,001Low
3Concrete Structures, Inc.$447,170+8.0%
4R.G. Huston Company, Inc.$494,946+20%
5Lunda Construction Company$540,328+31%
WisDOT contract 20260113004: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Radtke Contractors Inc.2. Concrete Structures, Inc.3. R.G. Huston Company, Inc.4. Lunda Construction Company
1Clearing (201.0105)STA4$150.00$150.00$219.00$150.00
2Grubbing (201.0205)STA4$150.00$150.00$238.00$150.00
3Removing structure over waterway minimal debris (structure) 01. P-28- 71 (203.0260)EACH1$17,997$6,000.00$54,600$90,000
4Excavation common (205.0100)CY202$12.50$12.50$16.00$12.50
5Excavation for structures bridges (structure) 01. B-28-204 (206.1001)EACH1$17,197$5,200.00$7,700.00$5,200.00
6Borrow (208.0100)CY235$15.00$15.00$33.00$15.00
7Backfill structure type A (210.1500)TON288$19.70$19.70$39.00$19.70
8Finishing roadway (project) 01. 3634-00-75 (213.0100)EACH1$500.00$500.00$100.00$500.00
9Base aggregate dense 3/4-inch (305.0110)TON170$27.00$27.00$34.00$27.00
10Base aggregate dense 1 1/4-inch (305.0120)TON470$23.85$23.85$24.60$23.85
11Select crushed material (312.0110)TON525$23.00$23.00$21.40$23.00
12Tack coat (455.0605)GAL40$4.00$4.00$4.04$2.00
13Asphaltic surface (465.0105)TON100$150.00$150.00$151.52$147.00
14Concrete masonry bridges (502.0100)CY138$764.55$1,300.00$1,450.00$1,150.00
15Protective surface treatment (502.3200)SY143$3.69$7.00$7.80$8.00
16Pigmented surface sealer (502.3210)SY42$13.77$10.00$21.50$15.00
17Bar steel reinforcement HS structures (505.0400)LB3,960$1.39$1.30$1.47$1.10
18Bar steel reinforcement HS coated structures (505.0600)LB22,280$1.35$1.50$1.54$1.20
19Rubberized membrane waterproofing (516.0500)SY10$64.32$44.00$36.00$35.00
20Piling steel HP 10-inch X 42 LB (550.1100)LF455$37.16$60.00$52.70$58.00
21Riprap heavy (606.0300)CY65$85.00$85.00$75.55$90.00
22Pipe underdrain wrapped 6-inch (612.0406)LF138$9.00$9.00$4.20$9.00
23Anchor assemblies for steel plate beam guard (614.0150)EACH4$315.69$350.00$375.00$250.00
24MGS guardrail 3 (614.2300)LF50$27.00$27.00$34.00$27.00
25MGS thrie beam transition (614.2500)LF157.60$92.00$92.00$92.00$92.00
26MGS guardrail terminal eat (614.2610)EACH4$3,600.00$3,600.00$4,200.00$3,600.00
27Maintenance and repair of haul roads (project) 01. 3634-00-75 (618.0100)EACH1$250.00$100.00$100.00$1.00
28Mobilization (619.1000)EACH1$93,682$65,100$36,000$101,913
29Water (624.0100)MGAL20$0.01$0.01$0.01$0.01
30Salvaged topsoil (625.0500)SY1,426$3.00$3.00$1.20$3.00
31Silt fence (628.1504)LF1,265$2.00$2.00$2.50$2.00
32Silt fence maintenance (628.1520)LF1,265$0.05$0.05$0.01$0.05
33Mobilizations erosion control (628.1905)EACH5$180.00$180.00$100.00$180.00
34Mobilizations emergency erosion control (628.1910)EACH5$270.00$270.00$100.00$270.00
35Erosion mat class I type B (628.2004)SY1,245$1.00$1.00$1.45$1.00
36Turbidity barriers (628.6005)SY130$32.00$32.00$0.42$32.00
37Seeding mixture no. 20 (630.0120)LB3.70$90.00$90.00$30.00$90.00
38Seeding temporary (630.0200)LB3.70$22.50$22.50$15.00$22.50
39Seed water (630.0500)MGAL33$10.00$10.00$20.00$10.00
40Posts wood 4X6-inch X 12-FT (634.0612)EACH4$75.00$75.00$100.00$75.00
41Signs type II reflective F (637.2230)SF12$22.00$22.00$30.00$22.00
42Moving signs type II (638.2102)EACH4$50.00$50.00$200.00$50.00
43Removing signs type II (638.2602)EACH6$25.00$25.00$45.00$25.00
44Removing small sign supports (638.3000)EACH4$25.00$25.00$45.00$25.00
45Field office type B (642.5001)EACH1$2,124.20$1,500.00$1,110.00$2,500.00
46Traffic control barricades type III (643.0420)DAY1,190$0.92$0.92$0.92$0.92
47Traffic control warning lights type A (643.0705)DAY1,850$0.25$0.25$0.25$0.25
48Traffic control signs (643.0900)DAY925$0.77$0.77$0.77$0.77
49Traffic control (643.5000)EACH1$1,031.28$1,031.28$1,031.28$1,031.28
50Geotextile type DF schedule A (645.0111)SY84$8.00$8.00$2.90$8.00
51Geotextile type HR (645.0120)SY135$6.00$6.00$3.70$6.00
52Construction staking subgrade (650.4500)LF533$0.01$0.01$0.01$0.01
53Construction staking base (650.5000)LF533$0.01$0.01$0.01$2.00
54Construction staking structure layout (structure) 01. B-28-0204 (650.6501)EACH1$2,750.00$2,750.00$2,750.00$2,000.00
55Construction staking supplemental control (project) 01. 3634-00-75 (650.9911)EACH1$1,650.00$1,650.00$1,650.00$1,000.00
56Construction staking slope stakes (650.9920)LF533$0.01$0.01$0.01$2.00
57Sawing asphalt (690.0150)LF486$1.96$1.96$1.95$1.96
58Incentive strength concrete structures (715.0502)DOL828$1.00$1.00$1.00$1.00
59Installing and maintaining bird deterrent system (station) 01. sta 10+00 (999.2000.S)EACH1$0.01$1.00$1.00$1.00
WisDOT contract 20260113004: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.

Every contract let that day: WisDOT letting of January 13, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy