WisDOT contract 20260113008 bid tabulation
T Tomah, Interior Road; Lemonweir Creek Bridge, B-41-0339 (LOC STR, Monroe County T Tomah, Interior Road). Let by Wisconsin DOT on January 13, 2026, Monroe. 5 bids received; low bid $440,067 by Radtke Contractors Inc..
- Owner
- Wisconsin DOT
- Letting
- 13 JAN 2026
- Pay items
- 58
- Data through
- 10 NOV 2026
4 of the 5 bids matched their published totals to within a dollar and are shown; the others are left out.
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Radtke Contractors Inc. | $440,067 | Low |
| 3 | Lunda Construction Company | $513,536 | +17% |
| 4 | Larson Construction Co., Inc. | $516,311 | +17% |
| 5 | Sheet Piling Services LLC | $537,521 | +22% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Radtke Contractors Inc. | 2. Lunda Construction Company | 3. Larson Construction Co., Inc. | 4. Sheet Piling Services LLC |
|---|---|---|---|---|---|---|---|
| 1 | Clearing (201.0105) | STA | 2 | $2,069.62 | $500.00 | $500.00 | $500.00 |
| 2 | Grubbing (201.0205) | STA | 2 | $2,069.62 | $500.00 | $500.00 | $500.00 |
| 3 | Removing structure over waterway remove debris (structure) 01. P-41- 0180 (203.0250) | EACH | 1 | $25,248 | $14,000 | $28,000 | $32,000 |
| 4 | Removing fence (204.0170) | LF | 200 | $5.00 | $5.00 | $5.00 | $5.00 |
| 5 | Excavation common (205.0100) | CY | 184 | $39.29 | $20.00 | $20.00 | $20.00 |
| 6 | Excavation for structures bridges (structure) 01. B-41-0339 (206.1001) | EACH | 1 | $15,837 | $4,500.00 | $16,420 | $20,500 |
| 7 | Backfill structure type A (210.1500) | TON | 285 | $40.54 | $28.00 | $28.00 | $28.00 |
| 8 | Finishing roadway (project) 01. 5025-00-72 (213.0100) | EACH | 1 | $1,000.00 | $500.00 | $750.00 | $0.01 |
| 9 | Base aggregate dense 3/4-inch (305.0110) | TON | 13 | $62.91 | $100.00 | $100.00 | $100.00 |
| 10 | Base aggregate dense 1 1/4-inch (305.0120) | TON | 190 | $25.73 | $25.00 | $25.00 | $25.00 |
| 11 | Breaker run (311.0110) | TON | 180 | $21.08 | $25.00 | $25.00 | $25.00 |
| 12 | Concrete pavement approach slab (415.0410) | SY | 138 | $268.51 | $268.51 | $271.20 | $268.51 |
| 13 | Asphaltic surface (465.0105) | TON | 40 | $256.48 | $256.48 | $259.04 | $256.48 |
| 14 | Concrete masonry bridges (502.0100) | CY | 135 | $670.82 | $1,100.00 | $789.00 | $1,200.00 |
| 15 | Protective surface treatment (502.3200) | SY | 176 | $3.69 | $10.00 | $4.75 | $8.00 |
| 16 | Bar steel reinforcement HS structures (505.0400) | LB | 4,500 | $1.28 | $1.15 | $1.61 | $4.75 |
| 17 | Bar steel reinforcement HS coated structures (505.0600) | LB | 18,160 | $1.39 | $1.32 | $1.61 | $4.00 |
| 18 | Railing tubular type M (513.4061) | LF | 90 | $294.64 | $325.00 | $370.00 | $300.00 |
| 19 | Rubberized membrane waterproofing (516.0500) | SY | 12 | $64.32 | $25.00 | $67.00 | $19.00 |
| 20 | Pre-boring rock or consolidated materials (550.0020) | LF | 140 | $256.14 | $175.00 | $452.50 | $0.01 |
| 21 | Piling steel HP 10-inch X 42 LB (550.1100) | LF | 315 | $32.79 | $43.00 | $62.14 | $55.00 |
| 22 | Riprap heavy (606.0300) | CY | 130 | $73.98 | $80.00 | $80.00 | $80.00 |
| 23 | Pipe underdrain wrapped 6-inch (612.0406) | LF | 160 | $11.29 | $22.00 | $22.00 | $22.00 |
| 24 | Maintenance and repair of haul roads (project) 01. 5025-00-72 (618.0100) | EACH | 1 | $250.00 | $1.00 | $1,500.00 | $0.01 |
| 25 | Mobilization (619.1000) | EACH | 1 | $69,137 | $121,845 | $79,014 | $57,197 |
| 26 | Water (624.0100) | MGAL | 4 | $32.64 | $100.00 | $100.00 | $100.00 |
| 27 | Salvaged topsoil (625.0500) | SY | 210 | $3.72 | $4.00 | $4.00 | $4.00 |
| 28 | Silt fence (628.1504) | LF | 600 | $3.00 | $3.00 | $3.00 | $3.00 |
| 29 | Silt fence maintenance (628.1520) | LF | 1,190 | $0.01 | $0.01 | $0.01 | $0.01 |
| 30 | Mobilizations erosion control (628.1905) | EACH | 4 | $200.00 | $200.00 | $200.00 | $200.00 |
| 31 | Mobilizations emergency erosion control (628.1910) | EACH | 4 | $250.00 | $250.00 | $250.00 | $250.00 |
| 32 | Erosion mat urban class I type B (628.2008) | SY | 260 | $2.25 | $2.25 | $2.25 | $2.25 |
| 33 | Turbidity barriers (628.6005) | SY | 350 | $40.00 | $40.00 | $40.00 | $40.00 |
| 34 | Fertilizer type B (629.0210) | CWT | 0.30 | $350.00 | $350.00 | $350.00 | $350.00 |
| 35 | Seeding mixture no. 30 (630.0130) | LB | 19 | $9.25 | $9.25 | $9.25 | $9.25 |
| 36 | Seeding temporary (630.0200) | LB | 11 | $2.50 | $2.50 | $2.50 | $2.50 |
| 37 | Seed water (630.0500) | MGAL | 9.50 | $60.00 | $60.00 | $60.00 | $60.00 |
| 38 | Posts wood 4X6-inch X 12-FT (634.0612) | EACH | 4 | $85.00 | $85.00 | $85.00 | $85.00 |
| 39 | Signs type II reflective F (637.2230) | SF | 12 | $25.00 | $25.00 | $25.00 | $25.00 |
| 40 | Removing signs type II (638.2602) | EACH | 4 | $25.00 | $25.00 | $25.00 | $25.00 |
| 41 | Removing small sign supports (638.3000) | EACH | 4 | $25.00 | $25.00 | $25.00 | $25.00 |
| 42 | Field office type B (642.5001) | EACH | 1 | $2,581.46 | $3,500.00 | $3,600.00 | $1,500.00 |
| 43 | Traffic control barricades type III (643.0420) | DAY | 1,620 | $0.40 | $0.40 | $1.00 | $0.40 |
| 44 | Traffic control warning lights type A (643.0705) | DAY | 2,520 | $0.10 | $0.10 | $0.10 | $0.10 |
| 45 | Traffic control signs (643.0900) | DAY | 1,260 | $0.22 | $0.22 | $1.00 | $0.22 |
| 46 | Traffic control (643.5000) | EACH | 1 | $5,860.00 | $5,860.00 | $3,000.00 | $5,860.00 |
| 47 | Geotextile type DF schedule A (645.0111) | SY | 100 | $5.81 | $9.00 | $9.00 | $9.00 |
| 48 | Geotextile type HR (645.0120) | SY | 260 | $4.02 | $8.00 | $8.00 | $8.00 |
| 49 | Construction staking subgrade (650.4500) | LF | 157 | $0.01 | $0.01 | $0.01 | $0.01 |
| 50 | Construction staking base (650.5000) | LF | 112 | $1.00 | $1.00 | $0.01 | $0.01 |
| 51 | Construction staking structure layout (structure) 01. B-41-0339 (650.6501) | EACH | 1 | $2,000.00 | $2,000.00 | $3,000.00 | $3,000.00 |
| 52 | Construction staking concrete pavement (650.7000) | LF | 45 | $2.00 | $2.00 | $1.00 | $1.00 |
| 53 | Construction staking supplemental control (project) 01. 5025-00-72 (650.9911) | EACH | 1 | $750.00 | $750.00 | $1,000.00 | $1,000.00 |
| 54 | Construction staking slope stakes (650.9920) | LF | 157 | $1.00 | $1.00 | $3.00 | $3.00 |
| 55 | Sawing asphalt (690.0150) | LF | 38 | $2.95 | $4.00 | $4.00 | $4.00 |
| 56 | Incentive strength concrete structures (715.0502) | DOL | 810 | $1.00 | $1.00 | $1.00 | $1.00 |
| 57 | Incentive compressive strength concrete pavement (715.0720) | DOL | 500 | $1.00 | $1.00 | $1.00 | $1.00 |
| 58 | Installing and maintaining bird deterrent system (station) 01. 10+00 (999.2000.S) | EACH | 1 | $0.01 | $0.01 | $3,000.00 | $750.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.
Every contract let that day: WisDOT letting of January 13, 2026. Compiled by Mirage Metrics.