WisDOT contract 20260113011 bid tabulation
V Desoto, Mill Park Drive; Mississippi Trib Bridge B-12-0258 (LOC STR, Crawford County V Desoto, Mill Park Drive). Let by Wisconsin DOT on January 13, 2026, Crawford. 5 bids received.
- Owner
- Wisconsin DOT
- Letting
- 13 JAN 2026
- Pay items
- 76
- Data through
- 10 NOV 2026
4 of the 5 bids matched their published totals to within a dollar and are shown; the others are left out.
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 2 | Lunda Construction Company | $655,442 | 0.0% |
| 3 | Concrete Structures, Inc. | $661,337 | +1.0% |
| 4 | Brennan Construction Company | $704,744 | +8.0% |
| 5 | Radtke Contractors Inc. | $705,895 | +8.0% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Lunda Construction Company | 2. Concrete Structures, Inc. | 3. Brennan Construction Company | 4. Radtke Contractors Inc. |
|---|---|---|---|---|---|---|---|
| 1 | Clearing (201.0105) | STA | 1 | $3,000.00 | $10,000 | $3,000.00 | $9,293.93 |
| 2 | Grubbing (201.0205) | STA | 1 | $2,000.00 | $10,000 | $2,000.00 | $5,828.93 |
| 3 | Removing structure over waterway minimal debris (structure) 01. P-12- 0703 (203.0260) | EACH | 1 | $15,000 | $26,000 | $15,000 | $56,054 |
| 4 | Removing curb & gutter (204.0150) | LF | 120 | $10.00 | $15.00 | $10.00 | $5.97 |
| 5 | Removing storm sewer (size) 01. 18-inch (204.0245) | LF | 20 | $20.00 | $25.00 | $20.00 | $47.72 |
| 6 | Excavation common (205.0100) | CY | 385 | $20.00 | $17.00 | $20.00 | $41.88 |
| 7 | Excavation, hauling, and disposal of potential creosote contaminated soil (205.0508.S) | TON | 114 | $105.00 | $100.00 | $105.00 | $95.15 |
| 8 | Excavation for structures bridges (structure) 01. B-12-0258 (206.1001) | EACH | 1 | $5,000.00 | $20,000 | $5,000.00 | $34,611 |
| 9 | Backfill structure type A (210.1500) | TON | 500 | $26.00 | $25.00 | $26.00 | $38.42 |
| 10 | Finishing roadway (project) 01. 5408-00-70 (213.0100) | EACH | 1 | $500.00 | $500.00 | $2,500.00 | $500.00 |
| 11 | Base aggregate dense 3/4-inch (305.0110) | TON | 20 | $100.00 | $55.00 | $100.00 | $110.49 |
| 12 | Base aggregate dense 1 1/4-inch (305.0120) | TON | 260 | $25.00 | $35.00 | $25.00 | $38.94 |
| 13 | Select crushed material (312.0110) | TON | 400 | $25.00 | $25.00 | $25.00 | $34.07 |
| 14 | Tack coat (455.0605) | GAL | 40 | $7.85 | $7.85 | $7.85 | $7.85 |
| 15 | Incentive density HMA pavement (460.2000) | DOL | 80 | $1.00 | $1.00 | $1.00 | $1.00 |
| 16 | HMA pavement 4 LT 58-28 S (460.5224) | TON | 120 | $148.30 | $148.30 | $148.30 | $148.30 |
| 17 | Asphaltic surface driveways and field entrances (465.0120) | TON | 5 | $148.30 | $148.30 | $148.30 | $148.30 |
| 18 | Concrete masonry bridges (502.0100) | CY | 255 | $950.00 | $937.00 | $1,100.00 | $670.32 |
| 19 | Protective surface treatment (502.3200) | SY | 268 | $5.00 | $7.00 | $3.50 | $3.69 |
| 20 | Pigmented surface sealer (502.3210) | SY | 24 | $15.00 | $20.00 | $7.50 | $15.69 |
| 21 | Bar steel reinforcement HS structures (505.0400) | LB | 5,720 | $1.15 | $1.30 | $1.35 | $1.31 |
| 22 | Bar steel reinforcement HS coated structures (505.0600) | LB | 38,080 | $1.30 | $1.50 | $1.40 | $1.35 |
| 23 | Railing steel type NY4 (513.7084) | LF | 56 | $500.00 | $417.00 | $435.00 | $443.13 |
| 24 | Rubberized membrane waterproofing (516.0500) | SY | 18 | $25.00 | $44.00 | $65.00 | $64.32 |
| 25 | Piling steel HP 10-inch X 42 LB (550.1100) | LF | 800 | $40.00 | $60.00 | $70.00 | $39.07 |
| 26 | Concrete curb & gutter 30-inch type D (601.0411) | LF | 136 | $45.00 | $45.00 | $40.00 | $45.00 |
| 27 | Concrete sidewalk 4-inch (602.0405) | SF | 115 | $12.00 | $12.00 | $10.00 | $12.00 |
| 28 | Concrete driveway 6-inch (602.0810) | SY | 23 | $90.00 | $90.00 | $110.00 | $90.00 |
| 29 | Riprap heavy (606.0300) | CY | 86 | $80.00 | $75.00 | $90.00 | $75.60 |
| 30 | Storm sewer pipe reinforced concrete class IV 18-inch (608.0418) | LF | 19 | $160.00 | $180.00 | $160.00 | $97.11 |
| 31 | Manhole covers type J (611.0530) | EACH | 1 | $800.00 | $750.00 | $800.00 | $1,285.71 |
| 32 | Manholes 4-FT diameter (611.2004) | EACH | 1 | $4,000.00 | $3,500.00 | $4,000.00 | $3,823.42 |
| 33 | Pipe underdrain wrapped 6-inch (612.0406) | LF | 195 | $22.00 | $8.00 | $22.00 | $4.26 |
| 34 | Anchor assemblies for steel plate beam guard (614.0150) | EACH | 2 | $200.00 | $350.00 | $250.00 | $365.69 |
| 35 | Fence chain link salvaged 4-FT (616.0404) | LF | 24 | $200.00 | $200.00 | $185.00 | $200.00 |
| 36 | Maintenance and repair of haul roads (project) 01. 5408-00-70 (618.0100) | EACH | 1 | $1.00 | $100.00 | $500.00 | $250.00 |
| 37 | Mobilization (619.1000) | EACH | 1 | $109,747 | $67,678 | $88,000 | $136,468 |
| 38 | Water (624.0100) | MGAL | 20 | $90.00 | $25.00 | $90.00 | $50.49 |
| 39 | Salvaged topsoil (625.0500) | SY | 163 | $4.00 | $2.50 | $4.00 | $11.74 |
| 40 | Silt fence (628.1504) | LF | 217 | $3.00 | $3.00 | $3.00 | $3.00 |
| 41 | Silt fence maintenance (628.1520) | LF | 217 | $0.01 | $0.01 | $0.01 | $0.01 |
| 42 | Mobilizations erosion control (628.1905) | EACH | 3 | $300.00 | $300.00 | $300.00 | $300.00 |
| 43 | Mobilizations emergency erosion control (628.1910) | EACH | 2 | $350.00 | $350.00 | $350.00 | $350.00 |
| 44 | Erosion mat urban class I type B (628.2008) | SY | 162 | $2.25 | $2.25 | $2.25 | $2.25 |
| 45 | Turbidity barriers (628.6005) | SY | 220 | $40.00 | $40.00 | $40.00 | $40.00 |
| 46 | Inlet protection type D (628.7020) | EACH | 2 | $125.00 | $125.00 | $125.00 | $125.00 |
| 47 | Seeding mixture no. 20 (630.0120) | LB | 6 | $10.00 | $10.00 | $10.00 | $10.00 |
| 48 | Seeding temporary (630.0200) | LB | 6 | $5.00 | $5.00 | $5.00 | $5.00 |
| 49 | Posts wood 4X6-inch X 12-FT (634.0612) | EACH | 4 | $85.00 | $85.00 | $85.00 | $85.00 |
| 50 | Signs type II reflective F (637.2230) | SF | 12 | $25.00 | $25.00 | $25.00 | $25.00 |
| 51 | Removing signs type II (638.2602) | EACH | 4 | $25.00 | $25.00 | $25.00 | $25.00 |
| 52 | Removing small sign supports (638.3000) | EACH | 4 | $25.00 | $25.00 | $25.00 | $25.00 |
| 53 | Field office type B (642.5001) | EACH | 1 | $3,800.00 | $1,500.00 | $8,000.00 | $3,138.72 |
| 54 | Traffic control barricades type III (643.0420) | DAY | 1,370 | $1.00 | $1.00 | $1.00 | $1.00 |
| 55 | Traffic control warning lights type A (643.0705) | DAY | 2,130 | $0.10 | $0.10 | $0.10 | $0.10 |
| 56 | Traffic control signs (643.0900) | DAY | 1,065 | $1.00 | $1.00 | $1.00 | $1.00 |
| 57 | Traffic control (643.5000) | EACH | 1 | $2,000.00 | $2,000.00 | $2,000.00 | $2,000.00 |
| 58 | Geotextile type DF schedule A (645.0111) | SY | 70 | $8.00 | $8.00 | $8.00 | $4.71 |
| 59 | Geotextile type HR (645.0120) | SY | 130 | $8.00 | $5.00 | $8.00 | $5.10 |
| 60 | Construction staking storm sewer (650.4000) | EACH | 1 | $115.00 | $115.00 | $115.00 | $115.00 |
| 61 | Construction staking subgrade (650.4500) | LF | 142 | $0.01 | $0.01 | $0.01 | $0.01 |
| 62 | Construction staking base (650.5000) | LF | 142 | $1.00 | $1.00 | $1.00 | $1.00 |
| 63 | Construction staking curb gutter and curb & gutter (650.5500) | LF | 75 | $2.00 | $2.00 | $2.00 | $2.00 |
| 64 | Construction staking structure layout (structure) 01. B-12-0258 (650.6501) | EACH | 1 | $2,000.00 | $2,000.00 | $2,000.00 | $2,000.00 |
| 65 | Construction staking sidewalk (project) 01. 5408-00-70 (650.9500) | EACH | 1 | $750.00 | $750.00 | $750.00 | $750.00 |
| 66 | Construction staking supplemental control (project) 01. 5408-00-70 (650.9911) | EACH | 1 | $1,000.00 | $1,000.00 | $1,000.00 | $1,000.00 |
| 67 | Construction staking slope stakes (650.9920) | LF | 142 | $1.00 | $1.00 | $1.00 | $1.00 |
| 68 | Sawing asphalt (690.0150) | LF | 78 | $4.00 | $4.00 | $4.00 | $2.95 |
| 69 | Sawing concrete (690.0250) | LF | 30 | $6.00 | $10.00 | $6.00 | $2.95 |
| 70 | Incentive strength concrete structures (715.0502) | DOL | 1,530 | $1.00 | $1.00 | $1.00 | $1.00 |
| 71 | Installing and maintaining bird deterrent system (station) 01. 9+93 (999.2000.S) | EACH | 1 | $1.00 | $1.00 | $500.00 | $0.01 |
| 72 | On-the-job training apprentice at $5.00/HR (ASP.1T0A) | HRS | 1,200 | $5.00 | $5.00 | $5.00 | $5.00 |
| 73 | On-the-job training graduate at $5.00/HR (ASP.1T0G) | HRS | 600 | $5.00 | $5.00 | $5.00 | $5.00 |
| 74 | Special 01. MGS guardrail terminal eat TL-2 (SPV.0060) | EACH | 2 | $3,000.00 | $3,000.00 | $3,000.00 | $3,000.00 |
| 75 | Special 01. MGS thrie beam transition TL-2 (SPV.0090) | LF | 40.60 | $100.00 | $100.00 | $100.00 | $100.00 |
| 76 | Special 02. removing existing timber piling (SPV.0090) | LF | 75 | $50.00 | $1.00 | $50.00 | $37.59 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.
Every contract let that day: WisDOT letting of January 13, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.