WisDOT contract 20260113029 bid tabulation

Unity - Fenwood; Fenwood Creek Bridge, B-37-0486 (CTH P, Marathon County Unity - Fenwood). Let by Wisconsin DOT on January 13, 2026, Marathon. 6 bids received; low bid $705,962 by Radtke Contractors Inc..

Owner
Wisconsin DOT
Letting
13 JAN 2026
Pay items
65
Data through
10 NOV 2026

5 of the 6 bids matched their published totals to within a dollar and are shown; the others are left out.

Bidders

RankBidderTotal bidAgainst the low bid
1Radtke Contractors Inc.$705,962Low
2Larson Construction Co., Inc.$732,221+4.0%
3Sheet Piling Services LLC$745,730+6.0%
5Janke General Contractors, Inc.$845,122+20%
6Lunda Construction Company$874,644+24%
WisDOT contract 20260113029: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Radtke Contractors Inc.2. Larson Construction Co., Inc.3. Sheet Piling Services LLC4. Janke General Contractors, Inc.5. Lunda Construction Company
1Clearing (201.0105)STA2$100.00$1.00$100.00$430.00$100.00
2Grubbing (201.0205)STA2$100.00$1.00$100.00$430.00$100.00
3Removing structure over waterway minimal debris (structure) 01. B-37- 49 (203.0260)EACH1$27,204$54,178$85,000$49,600$100,000
4Removing asphaltic surface (204.0110)SY809$4.82$2.00$4.82$2.75$4.82
5Removing guardrail (204.0165)LF360$2.65$3.80$2.65$3.00$2.65
6Excavation common (205.0100)CY287$9.88$15.70$9.88$16.50$9.88
7Excavation for structures bridges (structure) 01. B-37-486 (206.1001)EACH1$15,027$19,650$50,000$18,215$50,000
8Cofferdams (structure) 01. B-37-486 (206.5001)EACH1$57,485$34,475$35,000$49,200$75,000
9Borrow (208.0100)CY518$15.59$28.20$15.59$19.50$15.59
10Backfill structure type A (210.1500)TON210$27.50$23.40$26.85$28.50$26.85
11Finishing roadway (project) 01. 6652-03-70 (213.0100)EACH1$1,000.00$520.00$1,000.00$400.00$1,000.00
12Base aggregate dense 3/4-inch (305.0110)TON150$29.20$27.90$29.20$50.00$29.20
13Base aggregate dense 1 1/4-inch (305.0120)TON915$19.85$21.77$19.85$31.00$19.85
14Tack coat (455.0605)GAL98$8.00$8.00$8.00$8.00$8.00
15Asphaltic surface (465.0105)TON310$130.20$130.20$130.20$130.00$130.20
16Concrete masonry bridges (502.0100)CY247$667.06$715.00$875.00$962.00$800.00
17Protective surface treatment (502.3200)SY343$3.60$3.50$4.00$5.00$5.00
18Underwater substructure inspection (structure) 01. B-37-486 (502.9000.S)EACH1$3,500.00$5,000.00$5,400.00$5,000.00$5,400.00
19Bar steel reinforcement HS structures (505.0400)LB5,920$1.30$1.55$1.20$2.25$1.10
20Bar steel reinforcement HS coated structures (505.0600)LB36,830$1.35$1.54$1.30$2.30$1.25
21Railing tubular type M (513.4061)LF211$274.51$379.00$260.00$371.00$300.00
22Rubberized membrane waterproofing (516.0500)SY18$58.59$59.00$30.00$44.00$25.00
23Piling steel HP 10-inch X 42 LB (550.1100)LF515$39.19$64.42$42.00$90.00$45.00
24Riprap heavy (606.0300)CY145$69.72$75.60$75.43$90.00$75.43
25Pipe underdrain wrapped 6-inch (612.0406)LF210$4.20$6.80$7.49$16.00$7.49
26MGS guardrail 3 (614.2300)LF175$27.89$24.25$27.89$38.00$27.89
27MGS thrie beam transition (614.2500)LF157.60$98.50$92.50$98.50$105.00$98.50
28MGS guardrail terminal eat (614.2610)EACH4$3,800.00$3,485.00$3,800.00$4,200.00$3,800.00
29Maintenance and repair of haul roads (project) 01. 6652-03-70 (618.0100)EACH1$250.00$1,500.00$0.01$400.00$0.01
30Mobilization (619.1000)EACH1$106,737$72,182$35,842$35,000$118,162
31Water (624.0100)MGAL22$25.00$0.50$25.00$17.35$25.00
32Salvaged topsoil (625.0500)SY1,177$3.25$2.65$3.25$8.00$3.25
33Silt fence (628.1504)LF1,340$2.89$2.05$2.89$2.25$2.89
34Silt fence maintenance (628.1520)LF1,340$0.10$0.01$0.10$0.01$0.10
35Mobilizations erosion control (628.1905)EACH5$200.00$350.00$200.00$350.00$200.00
36Mobilizations emergency erosion control (628.1910)EACH3$200.00$50.00$200.00$350.00$200.00
37Erosion mat urban class I type B (628.2008)SY1,472$1.89$1.95$1.89$2.05$1.89
38Turbidity barriers (628.6005)SY185$51.80$42.25$51.80$42.00$51.80
39Fertilizer type A (629.0205)CWT1.40$115.00$178.00$150.00$150.00$150.00
40Seeding mixture no. 20 (630.0120)LB98$7.85$13.95$7.85$25.00$7.85
41Seeding temporary (630.0200)LB59$3.50$6.20$3.50$15.00$3.50
42Seed water (630.0500)MGAL49$25.00$0.10$25.00$50.00$25.00
43Posts wood 4X6-inch X 14-FT (634.0614)EACH4$120.00$89.00$120.00$275.00$120.00
44Signs type II reflective F (637.2230)SF12$30.00$29.40$30.00$55.00$30.00
45Removing signs type II (638.2602)EACH4$15.00$21.50$15.00$50.00$15.00
46Removing small sign supports (638.3000)EACH4$15.00$21.50$15.00$50.00$15.00
47Field office type B (642.5001)EACH1$2,191.30$3,400.00$1,000.00$5,400.00$3,500.00
48Traffic control barricades type III (643.0420)DAY456$1.36$0.50$0.50$0.50$0.50
49Traffic control warning lights type A (643.0705)DAY912$0.70$0.10$0.10$0.10$0.10
50Traffic control signs (643.0900)DAY12,920$0.52$0.35$0.35$0.35$0.35
51Traffic control covering signs type II (643.0920)EACH2$104.89$20.00$20.00$20.00$20.00
52Traffic control signs fixed message (643.1000)SF36$29.45$9.20$9.20$9.20$9.20
53Traffic control (643.5000)EACH1$7,878.93$1,800.00$1,800.00$1,800.00$1,800.00
54Geotextile type DF schedule A (645.0111)SY62$4.60$4.55$9.00$3.26$9.00
55Geotextile type HR (645.0120)SY245$5.01$3.50$8.10$4.04$8.10
56Marking line epoxy 4-inch (646.1020)LF1,210$4.30$4.30$4.75$4.30$4.60
57Construction staking subgrade (650.4500)LF505$0.01$0.01$0.01$0.01$0.01
58Construction staking base (650.5000)LF505$1.00$1.00$1.00$1.00$1.00
59Construction staking structure layout (structure) 01. B-37-486 (650.6501)EACH1$3,400.00$3,400.00$3,500.00$3,500.00$3,400.00
60Construction staking supplemental control (project) 01. 6652-03-70 (650.9911)EACH1$1,200.00$1,200.00$600.00$600.00$1,200.00
61Construction staking slope stakes (650.9920)LF505$1.00$1.00$2.00$1.00$1.00
62Sawing asphalt (690.0150)LF50$5.00$2.95$5.00$3.00$5.00
63Incentive strength concrete structures (715.0502)DOL1,482$1.00$1.00$1.00$1.00$1.00
64Installing and maintaining bird deterrent system (station) 01. 13+10 (999.2000.S)EACH1$0.01$2,900.00$0.01$3,900.00$0.01
65Special 01. select crushed material for travel corridor (SPV.0195)TON20$45.69$57.25$50.00$65.00$50.00
WisDOT contract 20260113029: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.

Every contract let that day: WisDOT letting of January 13, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy