WisDOT contract 20260113035 bid tabulation
STH 86 - CTH E; Spirit River Bridge, B-35-0162 (CTH O, Lincoln County STH 86 - CTH E). Let by Wisconsin DOT on January 13, 2026, Lincoln. 4 bids received; low bid $1,249,480 by Sheet Piling Services LLC.
- Owner
- Wisconsin DOT
- Letting
- 13 JAN 2026
- Pay items
- 63
- Data through
- 10 NOV 2026
3 of the 4 bids matched their published totals to within a dollar and are shown; the others are left out.
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Sheet Piling Services LLC | $1,249,480 | Low |
| 3 | Lunda Construction Company | $1,376,189 | +10% |
| 4 | Larson Construction Co., Inc. | $1,435,419 | +15% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Sheet Piling Services LLC | 2. Lunda Construction Company | 3. Larson Construction Co., Inc. |
|---|---|---|---|---|---|---|
| 1 | Removing structure over waterway minimal debris (structure) 01. B-35- 003 (203.0260) | EACH | 1 | $275,000 | $250,000 | $148,695 |
| 2 | Excavation common (205.0100) | CY | 276 | $26.86 | $26.86 | $26.86 |
| 3 | Excavation for structures bridges (structure) 01. B-35-162 (206.1001) | EACH | 1 | $90,000 | $45,000 | $49,440 |
| 4 | Backfill structure type A (210.1500) | TON | 300 | $38.75 | $38.75 | $38.75 |
| 5 | Finishing roadway (project) 01. 9423-00-70 (213.0100) | EACH | 1 | $500.00 | $500.00 | $500.00 |
| 6 | Base aggregate dense 3/4-inch (305.0110) | TON | 98 | $36.25 | $36.25 | $36.25 |
| 7 | Base aggregate dense 1 1/4-inch (305.0120) | TON | 710 | $32.29 | $32.29 | $32.29 |
| 8 | HMA cold weather paving (450.4000) | TON | 50 | $0.01 | $0.01 | $0.01 |
| 9 | Tack coat (455.0605) | GAL | 50 | $11.20 | $11.20 | $11.20 |
| 10 | Asphaltic surface (465.0105) | TON | 200 | $124.54 | $124.54 | $124.54 |
| 11 | Asphaltic flumes (465.0315) | SY | 10 | $95.00 | $95.00 | $95.00 |
| 12 | Concrete masonry bridges (502.0100) | CY | 408 | $825.00 | $1,000.00 | $868.00 |
| 13 | Protective surface treatment (502.3200) | SY | 422 | $5.00 | $5.00 | $3.50 |
| 14 | Pigmented surface sealer (502.3210) | SY | 150 | $5.00 | $6.00 | $7.65 |
| 15 | Bar steel reinforcement HS structures (505.0400) | LB | 22,280 | $1.30 | $1.10 | $1.52 |
| 16 | Bar steel reinforcement HS coated structures (505.0600) | LB | 68,980 | $1.35 | $1.20 | $1.52 |
| 17 | Rubberized membrane waterproofing (516.0500) | SY | 12 | $30.00 | $25.00 | $60.00 |
| 18 | Piling cip concrete 12 3/4 X 0.375- inch (550.2126) | LF | 675 | $60.00 | $65.00 | $94.21 |
| 19 | Piling cip concrete 16 X 0.50-inch (550.2168) | LF | 1,485 | $85.00 | $120.00 | $168.40 |
| 20 | Riprap heavy (606.0300) | CY | 141 | $99.89 | $99.89 | $99.89 |
| 21 | Pipe underdrain wrapped 6-inch (612.0406) | LF | 160 | $7.50 | $7.50 | $7.50 |
| 22 | Anchor assemblies for steel plate beam guard (614.0150) | EACH | 4 | $300.00 | $200.00 | $255.00 |
| 23 | Maintenance and repair of haul roads (project) 01. 9423-00-70 (618.0100) | EACH | 1 | $0.01 | $0.01 | $2,500.00 |
| 24 | Mobilization (619.1000) | EACH | 1 | $56,107 | $135,617 | $211,313 |
| 25 | Water (624.0100) | MGAL | 16.10 | $25.00 | $25.00 | $25.00 |
| 26 | Topsoil (625.0100) | SY | 432 | $9.50 | $9.50 | $9.50 |
| 27 | Silt fence (628.1504) | LF | 720 | $3.25 | $3.25 | $3.25 |
| 28 | Silt fence maintenance (628.1520) | LF | 720 | $0.10 | $0.10 | $0.10 |
| 29 | Silt screen (628.1550) | LF | 220 | $70.90 | $70.90 | $70.90 |
| 30 | Mobilizations erosion control (628.1905) | EACH | 5 | $200.00 | $200.00 | $200.00 |
| 31 | Mobilizations emergency erosion control (628.1910) | EACH | 2 | $200.00 | $200.00 | $200.00 |
| 32 | Erosion mat urban class I type B (628.2008) | SY | 336 | $1.95 | $1.95 | $1.95 |
| 33 | Turbidity barriers (628.6005) | SY | 340 | $51.50 | $51.50 | $51.50 |
| 34 | Temporary ditch checks (628.7504) | LF | 20 | $15.00 | $15.00 | $15.00 |
| 35 | Rock bags (628.7570) | EACH | 88 | $10.00 | $10.00 | $10.00 |
| 36 | Fertilizer type B (629.0210) | CWT | 0.64 | $100.00 | $100.00 | $100.00 |
| 37 | Seeding mixture no. 20 (630.0120) | LB | 36 | $7.10 | $7.10 | $7.10 |
| 38 | Seeding mixture no. 40 (630.0140) | LB | 10 | $8.10 | $8.10 | $8.10 |
| 39 | Seeding temporary (630.0200) | LB | 28 | $3.50 | $3.50 | $3.50 |
| 40 | Seed water (630.0500) | MGAL | 19 | $25.00 | $25.00 | $25.00 |
| 41 | Posts wood 4X6-inch X 14-FT (634.0614) | EACH | 4 | $125.00 | $125.00 | $125.00 |
| 42 | Signs type II reflective F (637.2230) | SF | 12 | $30.00 | $30.00 | $30.00 |
| 43 | Field office type B (642.5001) | EACH | 1 | $2,000.00 | $3,500.00 | $4,750.00 |
| 44 | Traffic control barricades type III (643.0420) | DAY | 5,060 | $0.35 | $0.35 | $0.35 |
| 45 | Traffic control warning lights type A (643.0705) | DAY | 8,250 | $0.10 | $0.10 | $0.10 |
| 46 | Traffic control signs (643.0900) | DAY | 4,400 | $0.35 | $0.35 | $0.35 |
| 47 | Traffic control signs fixed message (643.1000) | SF | 36 | $10.90 | $10.90 | $10.90 |
| 48 | Traffic control (643.5000) | EACH | 1 | $1,200.00 | $1,200.00 | $1,200.00 |
| 49 | Geotextile type DF schedule A (645.0111) | SY | 64 | $7.50 | $7.50 | $7.50 |
| 50 | Geotextile type HR (645.0120) | SY | 270 | $7.50 | $7.50 | $7.50 |
| 51 | Marking line paint 4-inch (646.1005) | LF | 963 | $5.25 | $6.25 | $5.50 |
| 52 | Construction staking subgrade (650.4500) | LF | 296 | $0.10 | $0.10 | $0.10 |
| 53 | Construction staking base (650.5000) | LF | 296 | $2.00 | $2.00 | $2.00 |
| 54 | Construction staking structure layout (structure) 01. B-35-162 (650.6501) | EACH | 1 | $4,000.00 | $4,000.00 | $4,000.00 |
| 55 | Construction staking supplemental control (project) 01. 9423-00-70 (650.9911) | EACH | 1 | $1,319.40 | $1,319.40 | $1,319.40 |
| 56 | Construction staking slope stakes (650.9920) | LF | 296 | $3.50 | $3.50 | $3.50 |
| 57 | Sawing asphalt (690.0150) | LF | 44 | $6.50 | $6.50 | $6.50 |
| 58 | Incentive strength concrete structures (715.0502) | DOL | 2,450 | $1.00 | $1.00 | $1.00 |
| 59 | Seismograph (project) 01. 9423-00- 70 (999.1001.S) | EACH | 1 | $1,200.00 | $2,500.00 | $3,600.00 |
| 60 | Crack and damage survey 01. 9423-00-70 (999.1501.S) | EACH | 1 | $1,000.00 | $2,800.00 | $2,800.00 |
| 61 | Installing and maintaining bird deterrent system (station) 01. 9+97 (999.2000.S) | EACH | 1 | $0.01 | $0.01 | $6,850.00 |
| 62 | Special 01. cut-stone boulders (SPV.0165) | SF | 155 | $225.80 | $225.80 | $225.80 |
| 63 | Special 01. infill riprap - B-35-162 (SPV.0195) | TON | 66 | $53.40 | $53.40 | $53.40 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.
Every contract let that day: WisDOT letting of January 13, 2026. Compiled by Mirage Metrics.