WisDOT contract 20260113044 bid tabulation
Spring Valley - Menomonie; Red Cedar River Bridge B-17-0005 (STH 029, Dunn County Spring Valley - Menomonie). Let by Wisconsin DOT on January 13, 2026, Dunn. 4 bids received; low bid $400,000 by Zenith Tech., Inc. - Waukesha.
- Owner
- Wisconsin DOT
- Letting
- 13 JAN 2026
- Pay items
- 44
- Data through
- 10 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Zenith Tech., Inc. - Waukesha | $400,000 | Low |
| 2 | Pciroads, LLC | $407,992 | +2.0% |
| 3 | Norcon Corporation | $493,990 | +23% |
| 4 | Lunda Construction Company | $497,584 | +24% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Zenith Tech., Inc. - Waukesha | 2. Pciroads, LLC | 3. Norcon Corporation | 4. Lunda Construction Company |
|---|---|---|---|---|---|---|---|
| 1 | Finishing roadway (project) 01. 7610-00-77 (213.0100) | EACH | 1 | $1,000.00 | $100.00 | $300.00 | $0.01 |
| 2 | Expansion device (502.3101) | LF | 77 | $520.00 | $338.63 | $657.00 | $600.00 |
| 3 | Protective surface treatment (502.3200) | SY | 35 | $10.00 | $12.00 | $11.00 | $5.00 |
| 4 | Pigmented surface sealer (502.3210) | SY | 4 | $41.00 | $200.00 | $40.00 | $25.00 |
| 5 | Adhesive anchors no. 5 bar (502.4205) | EACH | 80 | $26.00 | $32.00 | $37.00 | $25.00 |
| 6 | Bar steel reinforcement HS coated structures (505.0600) | LB | 2,210 | $4.25 | $3.25 | $3.65 | $6.00 |
| 7 | Bar couplers no. 4 (505.0904) | EACH | 26 | $45.00 | $25.00 | $33.00 | $30.00 |
| 8 | Bar couplers no. 5 (505.0905) | EACH | 6 | $55.00 | $35.00 | $40.00 | $41.00 |
| 9 | Bar couplers no. 6 (505.0906) | EACH | 10 | $59.00 | $50.00 | $43.00 | $42.00 |
| 10 | Joint repair (509.1000) | SY | 37 | $2,150.00 | $1,354.00 | $2,165.00 | $2,000.00 |
| 11 | Concrete surface repair (509.1500) | SF | 45 | $220.00 | $184.00 | $215.00 | $200.00 |
| 12 | Concrete masonry deck repair (509.2100.S) | CY | 14 | $1,250.00 | $4,320.00 | $2,075.00 | $500.00 |
| 13 | Preparation and coating of top flanges (structure) 01. B-17-0005 (517.0901.S) | EACH | 1 | $7,000.00 | $7,000.00 | $15,400 | $7,000.00 |
| 14 | Structure overcoating cleaning and priming (structure) 01. B-17-0005 (517.3001.S) | EACH | 1 | $25,000 | $25,000 | $87,700 | $25,000 |
| 15 | Containment and collection of waste materials (structure) 01. B- 17-0005 (517.4001.S) | EACH | 1 | $800.00 | $800.00 | $17,600 | $800.00 |
| 16 | Portable decontamination facility (517.6001.S) | EACH | 1 | $2,000.00 | $2,000.00 | $3,800.00 | $2,000.00 |
| 17 | Concrete barrier temporary precast delivered (603.8000) | LF | 650 | $14.50 | $12.00 | $21.00 | $15.00 |
| 18 | Concrete barrier temporary precast installed (603.8125) | LF | 1,287.50 | $5.75 | $5.75 | $9.00 | $5.00 |
| 19 | Anchoring concrete barrier temporary precast (603.8500) | LF | 587.50 | $18.00 | $16.00 | $5.75 | $0.01 |
| 20 | Crash cushions temporary (614.0905) | EACH | 4 | $3,500.00 | $3,500.00 | $3,660.00 | $3,660.00 |
| 21 | Maintenance and repair of haul roads (project) 01. 7610-00-77 (618.0100) | EACH | 1 | $500.00 | $400.00 | $200.00 | $0.01 |
| 22 | Mobilization (619.1000) | EACH | 1 | $75,000 | $92,318 | $40,300 | $210,557 |
| 23 | Field office type B (642.5001) | EACH | 1 | $6,000.00 | $12,500 | $6,300.00 | $3,000.00 |
| 24 | Traffic control drums (643.0300) | DAY | 1,750 | $0.15 | $0.15 | $0.15 | $0.15 |
| 25 | Traffic control barricades type III (643.0420) | DAY | 1,306 | $0.40 | $0.40 | $0.40 | $0.40 |
| 26 | Traffic control warning lights type A (643.0705) | DAY | 1,386 | $0.10 | $0.10 | $0.10 | $0.10 |
| 27 | Traffic control warning lights type C (643.0715) | DAY | 839 | $0.12 | $0.12 | $0.12 | $0.12 |
| 28 | Traffic control signs (643.0900) | DAY | 3,889 | $0.25 | $0.25 | $0.25 | $0.25 |
| 29 | Temporary marking line removable tape 6-inch (643.3180) | LF | 2,320 | $2.15 | $2.15 | $2.15 | $2.15 |
| 30 | Temporary marking stop line removable tape 18-inch (643.3850) | LF | 61 | $6.95 | $6.95 | $6.95 | $6.95 |
| 31 | Traffic control (643.5000) | EACH | 1 | $20,530 | $20,530 | $20,530 | $20,530 |
| 32 | Temporary pedestrian curb ramp (644.1601) | DAY | 31 | $8.00 | $8.00 | $8.00 | $8.00 |
| 33 | Temporary pedestrian barricade (644.1810) | LF | 981 | $8.00 | $8.00 | $8.00 | $8.00 |
| 34 | Geotextile type HR (645.0120) | SY | 80 | $12.00 | $30.00 | $11.00 | $5.00 |
| 35 | Marking line epoxy 6-inch (646.2020) | LF | 1,740 | $3.20 | $3.84 | $3.84 | $3.20 |
| 36 | Marking removal line 4-inch (646.9000) | LF | 1,740 | $0.65 | $0.65 | $0.65 | $0.65 |
| 37 | Construction staking supplemental control (project) 01. 7610-00-77 (650.9911) | EACH | 1 | $550.00 | $550.00 | $550.00 | $550.00 |
| 38 | Temporary traffic signals for bridges (structure) 01. B-17-0005 (661.0101) | EACH | 1 | $5,200.00 | $5,200.00 | $5,200.00 | $5,200.00 |
| 39 | Installing and maintaining bird deterrent system (station) 01. 677+50 (999.2000.S) | EACH | 1 | $3,838.19 | $3,000.00 | $7,300.00 | $0.01 |
| 40 | On-the-job training apprentice at $5.00/HR (ASP.1T0A) | HRS | 300 | $5.00 | $5.00 | $5.00 | $5.00 |
| 41 | On-the-job training graduate at $5.00/HR (ASP.1T0G) | HRS | 300 | $5.00 | $5.00 | $5.00 | $5.00 |
| 42 | Special 01. partially grouted riprap (SPV.0035) | CY | 40 | $475.00 | $224.00 | $687.00 | $215.00 |
| 43 | Special 01. driveway assistance device system (SPV.0045) | DAY | 126 | $28.80 | $28.80 | $28.80 | $28.80 |
| 44 | Special 01. abutment seat cleaning and sealing (SPV.0180) | SY | 22 | $60.00 | $65.00 | $215.00 | $50.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.
Every contract let that day: WisDOT letting of January 13, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.