WisDOT contract 20260113045 bid tabulation
Foster - Augusta; Bears Grass Creek Bridge B-18-0256 (CTH VV, Eau Claire County Foster - Augusta). Let by Wisconsin DOT on January 13, 2026, Eau Claire. 4 bids received; low bid $501,281 by Larson Construction Co., Inc..
- Owner
- Wisconsin DOT
- Letting
- 13 JAN 2026
- Pay items
- 71
- Data through
- 10 NOV 2026
3 of the 4 bids matched their published totals to within a dollar and are shown; the others are left out.
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Larson Construction Co., Inc. | $501,281 | Low |
| 2 | Radtke Contractors Inc. | $525,587 | +5.0% |
| 4 | Lunda Construction Company | $598,416 | +19% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Larson Construction Co., Inc. | 2. Radtke Contractors Inc. | 3. Lunda Construction Company |
|---|---|---|---|---|---|---|
| 1 | Removing small pipe culverts (203.0100) | EACH | 1 | $360.00 | $360.00 | $360.00 |
| 2 | Removing structure over waterway minimal debris (structure) 01. P-18- 0082 (203.0260) | EACH | 1 | $26,941 | $42,127 | $75,000 |
| 3 | Removing guardrail (204.0165) | LF | 260 | $3.50 | $3.50 | $3.50 |
| 4 | Excavation common (205.0100) | CY | 360 | $9.95 | $9.95 | $9.95 |
| 5 | Excavation, hauling, and disposal of potential creosote contaminated soil (205.0508.S) | TON | 110 | $149.96 | $99.10 | $75.00 |
| 6 | Excavation for structures bridges (structure) 01. B-18-0256 (206.1001) | EACH | 1 | $15,135 | $22,034 | $35,000 |
| 7 | Borrow (208.0100) | CY | 310 | $16.25 | $16.25 | $16.25 |
| 8 | Backfill structure type A (210.1500) | TON | 422 | $17.15 | $28.47 | $17.15 |
| 9 | Finishing roadway (project) 01. 7830-00-72 (213.0100) | EACH | 1 | $725.00 | $725.00 | $725.00 |
| 10 | Base aggregate dense 3/4-inch (305.0110) | TON | 180 | $26.75 | $26.75 | $26.75 |
| 11 | Base aggregate dense 1 1/4-inch (305.0120) | TON | 665 | $29.35 | $29.35 | $29.35 |
| 12 | Tack coat (455.0605) | GAL | 65 | $10.76 | $10.76 | $10.76 |
| 13 | Asphaltic surface (465.0105) | TON | 200 | $151.04 | $151.04 | $151.04 |
| 14 | Concrete masonry bridges (502.0100) | CY | 198 | $656.00 | $603.83 | $850.00 |
| 15 | Protective surface treatment (502.3200) | SY | 191 | $4.54 | $3.69 | $5.00 |
| 16 | Pigmented surface sealer (502.3210) | SY | 50 | $8.00 | $22.19 | $6.00 |
| 17 | Bar steel reinforcement HS structures (505.0400) | LB | 4,560 | $1.60 | $1.34 | $1.10 |
| 18 | Bar steel reinforcement HS coated structures (505.0600) | LB | 33,000 | $1.50 | $1.38 | $1.25 |
| 19 | Rubberized membrane waterproofing (516.0500) | SY | 12 | $59.00 | $64.32 | $25.00 |
| 20 | Culvert pipe corrugated steel 36- inch (521.3136) | LF | 40 | $115.00 | $115.00 | $115.00 |
| 21 | Piling steel HP 10-inch X 42 LB (550.1100) | LF | 560 | $59.00 | $39.01 | $45.00 |
| 22 | Concrete curb & gutter 4-inch sloped 36-inch type TBT (601.0588) | LF | 90 | $75.45 | $75.45 | $75.45 |
| 23 | Concrete surface drains (602.3010) | CY | 1.60 | $1,504.59 | $1,504.59 | $1,504.59 |
| 24 | Riprap medium (606.0200) | CY | 35 | $78.15 | $78.15 | $78.15 |
| 25 | Riprap heavy (606.0300) | CY | 60 | $73.00 | $81.46 | $60.00 |
| 26 | Pipe underdrain wrapped 6-inch (612.0406) | LF | 146 | $7.65 | $4.26 | $7.65 |
| 27 | Anchor assemblies for steel plate beam guard (614.0150) | EACH | 4 | $225.00 | $315.69 | $150.00 |
| 28 | MGS guardrail 3 (614.2300) | LF | 97 | $29.40 | $29.40 | $29.40 |
| 29 | MGS guardrail short radius (614.2350) | LF | 24 | $31.35 | $31.35 | $31.35 |
| 30 | MGS thrie beam transition (614.2500) | LF | 118 | $98.75 | $98.75 | $98.75 |
| 31 | MGS guardrail terminal eat (614.2610) | EACH | 3 | $3,700.00 | $3,700.00 | $3,700.00 |
| 32 | MGS guardrail short radius terminal (614.2630) | EACH | 1 | $2,675.00 | $2,675.00 | $2,675.00 |
| 33 | Maintenance and repair of haul roads (project) 01. 7830-00-72 (618.0100) | EACH | 1 | $1,500.00 | $250.00 | $0.01 |
| 34 | Mobilization (619.1000) | EACH | 1 | $55,950 | $89,295 | $78,052 |
| 35 | Water (624.0100) | MGAL | 10 | $45.00 | $45.00 | $45.00 |
| 36 | Salvaged topsoil (625.0500) | SY | 1,370 | $1.45 | $1.45 | $1.45 |
| 37 | Silt fence (628.1504) | LF | 900 | $2.35 | $2.35 | $2.35 |
| 38 | Silt fence maintenance (628.1520) | LF | 900 | $0.10 | $0.10 | $0.10 |
| 39 | Mobilizations erosion control (628.1905) | EACH | 4 | $180.00 | $180.00 | $180.00 |
| 40 | Mobilizations emergency erosion control (628.1910) | EACH | 2 | $90.00 | $90.00 | $90.00 |
| 41 | Erosion mat urban class I type B (628.2008) | SY | 1,370 | $1.85 | $1.85 | $1.85 |
| 42 | Turbidity barriers (628.6005) | SY | 120 | $54.00 | $54.00 | $54.00 |
| 43 | Culvert pipe checks (628.7555) | EACH | 5 | $18.00 | $18.00 | $18.00 |
| 44 | Fertilizer type B (629.0210) | CWT | 0.90 | $155.00 | $155.00 | $155.00 |
| 45 | Seeding mixture no. 20 (630.0120) | LB | 65 | $8.90 | $8.90 | $8.90 |
| 46 | Seed water (630.0500) | MGAL | 30 | $0.01 | $0.01 | $0.01 |
| 47 | Posts wood 4X6-inch X 12-FT (634.0612) | EACH | 4 | $84.00 | $84.00 | $84.00 |
| 48 | Signs type II reflective F (637.2230) | SF | 12 | $29.75 | $29.75 | $29.75 |
| 49 | Moving signs type II (638.2102) | EACH | 3 | $120.00 | $120.00 | $120.00 |
| 50 | Removing signs type II (638.2602) | EACH | 4 | $23.00 | $23.00 | $23.00 |
| 51 | Removing small sign supports (638.3000) | EACH | 4 | $23.00 | $23.00 | $23.00 |
| 52 | Moving small sign supports (638.4000) | EACH | 2 | $65.00 | $65.00 | $65.00 |
| 53 | Field office type B (642.5001) | EACH | 1 | $3,350.00 | $2,833.88 | $3,500.00 |
| 54 | Traffic control drums (643.0300) | DAY | 665 | $0.40 | $0.40 | $0.40 |
| 55 | Traffic control barricades type III (643.0420) | DAY | 1,330 | $0.50 | $0.50 | $0.50 |
| 56 | Traffic control warning lights type A (643.0705) | DAY | 2,280 | $0.10 | $0.10 | $0.10 |
| 57 | Traffic control signs (643.0900) | DAY | 1,235 | $0.45 | $0.45 | $0.45 |
| 58 | Traffic control (643.5000) | EACH | 1 | $1,525.00 | $1,525.00 | $1,525.00 |
| 59 | Geotextile type DF schedule A (645.0111) | SY | 92 | $3.05 | $4.71 | $3.05 |
| 60 | Geotextile type HR (645.0120) | SY | 155 | $3.75 | $4.00 | $4.00 |
| 61 | Marking line epoxy 4-inch (646.1020) | LF | 1,100 | $4.90 | $4.90 | $4.90 |
| 62 | Construction staking subgrade (650.4500) | LF | 375 | $0.01 | $0.01 | $0.01 |
| 63 | Construction staking base (650.5000) | LF | 375 | $0.01 | $0.01 | $1.00 |
| 64 | Construction staking curb gutter and curb & gutter (650.5500) | LF | 90 | $1.00 | $1.00 | $2.00 |
| 65 | Construction staking structure layout (structure) 01. B-18-0256 (650.6501) | EACH | 1 | $1,726.00 | $1,726.00 | $2,000.00 |
| 66 | Construction staking supplemental control (project) 01. 7830-00-72 (650.9911) | EACH | 1 | $369.00 | $369.00 | $750.00 |
| 67 | Construction staking slope stakes (650.9920) | LF | 375 | $0.98 | $0.98 | $1.00 |
| 68 | Sawing asphalt (690.0150) | LF | 46 | $4.00 | $2.95 | $4.00 |
| 69 | Incentive strength concrete structures (715.0502) | DOL | 1,980 | $1.00 | $1.00 | $1.00 |
| 70 | Installing and maintaining bird deterrent system (station) 01. sta 16+50 (999.2000.S) | EACH | 1 | $3,000.00 | $0.01 | $0.01 |
| 71 | Special 01. MGS thrie beam transition TL-2 (SPV.0090) | LF | 22 | $55.00 | $55.00 | $55.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.
Every contract let that day: WisDOT letting of January 13, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.