WisDOT contract 20260113050 bid tabulation
C Chetek, Sumner Ave; Lake Chetek Bridge B-03-0036 (CTH D, Barron County C Chetek, Sumner Avenue). Let by Wisconsin DOT on January 13, 2026, Barron. 3 bids received; low bid $2,394,875 by Lunda Construction Company.
- Owner
- Wisconsin DOT
- Letting
- 13 JAN 2026
- Pay items
- 86
- Data through
- 10 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Lunda Construction Company | $2,394,875 | Low |
| 2 | Pciroads, LLC | $2,834,703 | +18% |
| 3 | Zenith Tech., Inc. - Waukesha | $2,992,718 | +25% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Lunda Construction Company | 2. Pciroads, LLC | 3. Zenith Tech., Inc. - Waukesha |
|---|---|---|---|---|---|---|
| 1 | Abatement of asbestos containing material (structure) 01. B-03-0036 (203.0211.S) | EACH | 1 | $6,000.00 | $8,000.00 | $25,000 |
| 2 | Debris containment over waterway (structure) 01. B-03-0036 (203.0335) | EACH | 1 | $500.00 | $110,000 | $575,000 |
| 3 | Removing asphaltic surface butt joints (204.0115) | SY | 90 | $16.14 | $26.13 | $16.14 |
| 4 | Removing asphaltic surface milling (204.0120) | SY | 430 | $16.14 | $26.13 | $16.14 |
| 5 | Removing curb & gutter (204.0150) | LF | 260 | $13.00 | $13.00 | $15.00 |
| 6 | Removing concrete sidewalk (204.0155) | SY | 16 | $35.00 | $35.00 | $35.00 |
| 7 | Prepare foundation for asphaltic paving (project) 01. 8798-00-73 (211.0101) | EACH | 1 | $1.00 | $1,500.00 | $1.00 |
| 8 | Finishing roadway (project) 01. 8798-00-73 (213.0100) | EACH | 1 | $500.00 | $500.00 | $100.00 |
| 9 | Base aggregate dense 1 1/4-inch (305.0120) | TON | 50 | $55.00 | $55.00 | $45.00 |
| 10 | Concrete pavement 7-inch (415.0070) | SY | 35 | $123.78 | $123.78 | $123.78 |
| 11 | Concrete pavement approach slab (415.0410) | SY | 120 | $279.70 | $279.70 | $279.70 |
| 12 | Tack coat (455.0605) | GAL | 26 | $16.94 | $16.94 | $16.94 |
| 13 | Asphaltic surface (465.0105) | TON | 50 | $215.60 | $215.60 | $215.60 |
| 14 | Expansion device (502.3101) | LF | 79 | $400.00 | $316.00 | $500.00 |
| 15 | Protective surface treatment (502.3200) | SY | 3,147 | $3.00 | $6.50 | $5.00 |
| 16 | Pigmented surface sealer reseal (502.3205) | SY | 373 | $5.00 | $7.00 | $25.00 |
| 17 | Pigmented surface sealer (502.3210) | SY | 5 | $8.00 | $100.00 | $25.00 |
| 18 | Protective surface treatment reseal (502.3215) | SY | 508 | $10.00 | $9.80 | $5.00 |
| 19 | Adhesive anchors no. 5 bar (502.4205) | EACH | 84 | $15.00 | $31.00 | $30.00 |
| 20 | Bar steel reinforcement HS structures (505.0400) | LB | 3,120 | $4.50 | $3.25 | $5.00 |
| 21 | Bar couplers no. 4 (505.0904) | EACH | 16 | $30.00 | $25.00 | $75.00 |
| 22 | Bar couplers no. 5 (505.0905) | EACH | 12 | $35.00 | $45.00 | $80.00 |
| 23 | Bar couplers no. 6 (505.0906) | EACH | 60 | $45.00 | $65.00 | $90.00 |
| 24 | Preparation decks type 1 (509.0301) | SY | 987 | $115.00 | $180.00 | $165.00 |
| 25 | Preparation decks type 2 (509.0302) | SY | 395 | $115.00 | $195.00 | $195.00 |
| 26 | Cleaning decks to reapply concrete masonry overlay (509.0505.S) | SY | 2,556 | $20.00 | $6.20 | $20.00 |
| 27 | Joint repair (509.1000) | SY | 37 | $850.00 | $2,462.17 | $2,500.00 |
| 28 | Curb repair (509.1200) | LF | 561 | $50.00 | $110.00 | $125.00 |
| 29 | Concrete surface repair (509.1500) | SF | 5,135 | $82.00 | $120.00 | $0.01 |
| 30 | Full-depth deck repair (509.2000) | SY | 79 | $235.00 | $695.00 | $825.00 |
| 31 | Concrete masonry overlay decks (509.2500) | CY | 246 | $2,000.00 | $1,051.38 | $1,800.00 |
| 32 | Removing concrete masonry deck overlay (structure) 01. B-03-0036 (509.9005.S) | SY | 2,556 | $17.87 | $67.09 | $25.00 |
| 33 | Removing and resetting tubular railing (structure) 01. B-03-0036 (513.9006.S) | EACH | 1 | $1,000.00 | $54,800 | $7,500.00 |
| 34 | Adjusting floor drains (514.0900) | EACH | 4 | $250.00 | $420.00 | $525.00 |
| 35 | Preparation and coating of top flanges (structure) 01. B-03-0036 (517.0901.S) | EACH | 1 | $2,000.00 | $10,000 | $10,000 |
| 36 | Structure overcoating cleaning and priming (structure) 01. B-03-0036 (517.3001.S) | EACH | 1 | $69,000 | $162,000 | $150,000 |
| 37 | Containment and collection of waste materials (structure) 01. B- 03-0036 (517.4001.S) | EACH | 1 | $26,600 | $20,000 | $100,000 |
| 38 | Portable decontamination facility 01. B-03-0036 (517.6001.S) | EACH | 1 | $2,000.00 | $4,000.00 | $5,000.00 |
| 39 | Concrete curb & gutter 30-inch type A (601.0409) | LF | 45 | $64.24 | $64.24 | $64.24 |
| 40 | Concrete curb & gutter 30-inch type D (601.0411) | LF | 215 | $64.24 | $64.24 | $64.24 |
| 41 | Concrete sidewalk 4-inch (602.0405) | SF | 325 | $15.16 | $15.16 | $15.16 |
| 42 | Concrete barrier temporary precast delivered (603.8000) | LF | 940 | $11.77 | $11.77 | $11.77 |
| 43 | Concrete barrier temporary precast installed (603.8125) | LF | 1,880 | $5.25 | $5.25 | $5.25 |
| 44 | Adjusting inlet covers (611.8115) | EACH | 2 | $650.00 | $650.00 | $550.00 |
| 45 | Crash cushions temporary (614.0905) | EACH | 2 | $4,750.00 | $4,750.00 | $3,206.92 |
| 46 | Maintenance and repair of haul roads (project) 01. 8798-00-73 (618.0100) | EACH | 1 | $0.01 | $500.00 | $250.00 |
| 47 | Mobilization (619.1000) | EACH | 1 | $784,299 | $615,037 | $715,000 |
| 48 | Water (624.0100) | MGAL | 10 | $1.00 | $1.00 | $100.00 |
| 49 | Topsoil (625.0100) | SY | 80 | $15.00 | $15.00 | $25.00 |
| 50 | Silt fence (628.1504) | LF | 280 | $4.00 | $4.00 | $4.00 |
| 51 | Silt fence maintenance (628.1520) | LF | 140 | $0.01 | $0.01 | $0.01 |
| 52 | Mobilizations erosion control (628.1905) | EACH | 2 | $775.00 | $775.00 | $420.00 |
| 53 | Mobilizations emergency erosion control (628.1910) | EACH | 2 | $50.00 | $50.00 | $100.00 |
| 54 | Erosion mat urban class I type B (628.2008) | SY | 80 | $6.00 | $6.00 | $4.00 |
| 55 | Inlet protection type B (628.7010) | EACH | 4 | $50.00 | $50.00 | $95.00 |
| 56 | Inlet protection type C (628.7015) | EACH | 2 | $50.00 | $50.00 | $95.00 |
| 57 | Fertilizer type B (629.0210) | CWT | 0.05 | $500.00 | $500.00 | $110.00 |
| 58 | Seeding mixture no. 40 (630.0140) | LB | 1.50 | $500.00 | $500.00 | $25.00 |
| 59 | Seed water (630.0500) | MGAL | 2 | $1.00 | $1.00 | $100.00 |
| 60 | Field office type B (642.5001) | EACH | 1 | $6,000.00 | $36,000 | $15,000 |
| 61 | Traffic control drums (643.0300) | DAY | 1,600 | $0.39 | $2.00 | $0.39 |
| 62 | Traffic control barricades type III (643.0420) | DAY | 50 | $2.45 | $1.00 | $2.45 |
| 63 | Traffic control warning lights type C (643.0715) | DAY | 1,600 | $0.27 | $0.25 | $0.27 |
| 64 | Traffic control signs (643.0900) | DAY | 1,200 | $0.70 | $2.50 | $0.70 |
| 65 | Temporary marking line removable tape 6-inch (643.3180) | LF | 2,110 | $3.36 | $1.70 | $3.36 |
| 66 | Temporary marking stop line removable tape 18-inch (643.3850) | LF | 40 | $12.93 | $5.25 | $12.93 |
| 67 | Traffic control (643.5000) | EACH | 1 | $6,316.22 | $6,650.00 | $50,000 |
| 68 | Temporary pedestrian curb ramp (644.1601) | DAY | 15 | $27.62 | $4.00 | $27.62 |
| 69 | Temporary pedestrian detectable warning field (644.1605) | SF | 20 | $10.45 | $5.00 | $10.45 |
| 70 | Temporary pedestrian barricade (644.1810) | LF | 1,950 | $3.58 | $5.00 | $3.58 |
| 71 | Marking line epoxy 6-inch (646.2020) | LF | 1,670 | $3.20 | $3.00 | $3.20 |
| 72 | Marking curb epoxy (646.8120) | LF | 65 | $11.00 | $12.00 | $11.00 |
| 73 | Marking removal line 4-inch (646.9000) | LF | 465 | $3.00 | $0.85 | $3.00 |
| 74 | Construction staking curb gutter and curb & gutter (650.5500) | LF | 215 | $2.00 | $2.00 | $2.00 |
| 75 | Construction staking concrete pavement (650.7000) | LF | 45 | $5.00 | $2.00 | $2.00 |
| 76 | Construction staking resurfacing reference (650.8000) | LF | 110 | $1.00 | $0.25 | $0.25 |
| 77 | Construction staking sidewalk (project) 01. 8798-00-73 (650.9500) | EACH | 1 | $2,300.00 | $550.00 | $550.00 |
| 78 | Construction staking supplemental control (project) 01. 8798-00-73 (650.9911) | EACH | 1 | $0.01 | $1,500.00 | $1,500.00 |
| 79 | Temporary traffic signals for bridges (structure) 01. B-03-0036 (661.0101) | EACH | 1 | $15,184 | $17,100 | $50,000 |
| 80 | Sawing concrete (690.0250) | LF | 30 | $2.95 | $2.95 | $2.95 |
| 81 | Incentive compressive strength concrete pavement (715.0720) | DOL | 150 | $1.00 | $1.00 | $1.00 |
| 82 | Installing and maintaining bird deterrent system (station) 01. station 16+00 (999.2000.S) | EACH | 1 | $0.01 | $3,000.00 | $10,000 |
| 83 | On-the-job training apprentice at $5.00/HR (ASP.1T0A) | HRS | 800 | $5.00 | $5.00 | $5.00 |
| 84 | On-the-job training graduate at $5.00/HR (ASP.1T0G) | HRS | 600 | $5.00 | $5.00 | $5.00 |
| 85 | Special 01. embedded galvanic anodes (SPV.0060) | EACH | 40 | $40.00 | $540.00 | $55.00 |
| 86 | Special 02. clean deck drains (SPV.0060) | EACH | 4 | $250.00 | $500.00 | $500.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.
Every contract let that day: WisDOT letting of January 13, 2026. Compiled by Mirage Metrics.