WisDOT contract 20260210004 bid tabulation

CTH I - USH 12 (CTH W); Skillet Creek Bridge B-56-0246 (CTH W, Sauk County CTH I - USH 12 (CTH W)). Let by Wisconsin DOT on February 10, 2026, Sauk. 5 bids received; low bid $889,392 by R.G. Huston Company, Inc..

Owner
Wisconsin DOT
Letting
10 FEB 2026
Pay items
75
Data through
10 NOV 2026

4 of the 5 bids matched their published totals to within a dollar and are shown; the others are left out.

Bidders

RankBidderTotal bidAgainst the low bid
1R.G. Huston Company, Inc.$889,392Low
2Sheet Piling Services LLC$963,853+8.0%
3Concrete Structures, Inc.$980,815+10%
5Lunda Construction Company$1,130,227+27%
WisDOT contract 20260210004: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. R.G. Huston Company, Inc.2. Sheet Piling Services LLC3. Concrete Structures, Inc.4. Lunda Construction Company
1Clearing (201.0105)STA4$215.00$1,084.48$100.00$1,084.48
2Grubbing (201.0205)STA4$235.00$626.20$100.00$626.20
3Removing structure over waterway minimal debris (structure) 01. B-56- 0595 (203.0260)EACH1$44,600$100,000$64,300$100,000
4Removing guardrail (204.0165)LF161$3.00$5.00$5.00$5.00
5Excavation common (205.0100)CY734$14.15$19.71$17.00$19.71
6Excavation for structures bridges (structure) 01. B-56-0246 (206.1001)EACH1$12,000$47,641$20,000$19,641
7Backfill structure type A (210.1500)TON640$27.00$19.89$22.50$19.89
8Finishing roadway (project) 01. 5678-00-74 (213.0100)EACH1$200.00$1.00$500.00$500.00
9Base aggregate dense 3/4-inch (305.0110)TON120$48.00$35.88$23.00$35.88
10Base aggregate dense 1 1/4-inch (305.0120)TON1,125$21.00$19.91$19.25$19.91
11Concrete pavement 6-inch (415.0060)SY35$140.00$50.00$50.00$50.00
12Concrete pavement approach slab (415.0410)SY135$175.00$230.00$230.00$230.00
13Tack coat (455.0605)GAL48$4.04$4.00$4.00$4.00
14Asphaltic surface (465.0105)TON270$95.71$94.75$94.75$94.75
15Concrete masonry bridges (502.0100)CY257$861.00$850.00$1,000.00$850.00
16Protective surface treatment (502.3200)SY421$7.00$2.50$7.00$10.00
17Prestressed girder type I 36W-inch (503.0137)LF324$413.00$325.00$297.00$300.00
18Bar steel reinforcement HS structures (505.0400)LB7,950$1.60$2.25$1.30$1.35
19Bar steel reinforcement HS coated structures (505.0600)LB26,090$1.60$2.35$1.50$1.47
20Bearing pads elastomeric non- laminated (506.2605)EACH8$195.00$125.00$200.00$150.00
21Steel diaphragms (structure) 01. B- 56-0246 (506.4000)EACH3$1,221.39$1,500.00$2,000.00$1,500.00
22Railing tubular type M (513.4061)LF247$365.00$275.00$329.00$300.00
23Rubberized membrane waterproofing (516.0500)SY25$35.00$18.00$44.00$25.00
24Pre-boring rock or consolidated materials (550.0020)LF240$145.00$30.00$219.00$200.00
25Piling steel HP 10-inch X 42 LB (550.1100)LF280$83.00$40.00$60.00$40.00
26Riprap heavy (606.0300)CY210$53.00$81.17$75.00$81.17
27Pipe underdrain wrapped 6-inch (612.0406)LF220$3.85$6.94$9.00$6.94
28MGS thrie beam transition (614.2500)LF157.60$92.00$95.00$95.00$95.00
29MGS guardrail terminal eat (614.2610)EACH4$3,750.00$3,500.00$3,500.00$3,500.00
30Maintenance and repair of haul roads (project) 01. 5678-00-74 (618.0100)EACH1$393.64$0.01$500.00$6,650.00
31Mobilization (619.1000)EACH1$49,000$90,972$111,657$263,666
32Water (624.0100)MGAL12.50$12.00$48.08$0.01$48.08
33Salvaged topsoil (625.0500)SY750$2.30$3.23$3.50$3.23
34Mulching (627.0200)SY685$0.65$0.50$0.50$0.50
35Erosion bales (628.1104)EACH8$15.00$20.00$20.00$20.00
36Silt fence (628.1504)LF800$2.20$3.00$3.00$3.00
37Silt fence maintenance (628.1520)LF1,280$0.01$0.01$0.01$0.01
38Mobilizations erosion control (628.1905)EACH5$400.00$250.00$250.00$250.00
39Mobilizations emergency erosion control (628.1910)EACH3$200.00$100.00$100.00$100.00
40Erosion mat class I type B (628.2004)SY75$1.70$1.50$1.50$1.50
41Turbidity barriers (628.6005)SY425$42.00$40.00$40.00$40.00
42Fertilizer type B (629.0210)CWT1$110.00$100.00$100.00$100.00
43Seeding mixture no. 80 (630.0180)LB10$75.00$115.00$115.00$115.00
44Seeding temporary (630.0200)LB43$4.00$3.00$3.00$3.00
45Seeding nurse crop (630.0400)LB10$4.00$3.00$3.00$3.00
46Seed water (630.0500)MGAL35$25.00$1.00$1.00$1.00
47Posts wood 4X6-inch X 12-FT (634.0612)EACH4$75.00$125.00$125.00$125.00
48Signs type II reflective F (637.2230)SF12$22.00$30.00$30.00$30.00
49Moving signs type II (638.2102)EACH8$75.00$50.00$50.00$50.00
50Removing signs type II (638.2602)EACH4$20.00$25.00$25.00$25.00
51Removing small sign supports (638.3000)EACH4$20.00$25.00$25.00$25.00
52Moving small sign supports (638.4000)EACH4$100.00$50.00$50.00$50.00
53Field office type B (642.5001)EACH1$1,100.00$3,500.00$1,500.00$4,500.00
54Traffic control drums (643.0300)DAY70$1.00$1.00$1.00$1.00
55Traffic control barricades type III (643.0420)DAY2,254$0.50$0.50$0.50$0.50
56Traffic control warning lights type A (643.0705)DAY4,508$0.25$0.25$0.25$0.25
57Traffic control signs (643.0900)DAY1,764$0.25$0.25$0.25$0.25
58Traffic control signs PCMS (643.1050)DAY14$69.99$69.99$69.99$69.99
59Traffic control (643.5000)EACH1$3,000.00$3,000.00$3,000.00$3,000.00
60Geotextile type DF schedule A (645.0111)SY77$3.10$8.38$8.00$8.38
61Geotextile type HR (645.0120)SY372$3.00$3.68$8.00$3.68
62Marking line paint 4-inch (646.1005)LF1,576$2.85$2.95$2.85$2.95
63Construction staking subgrade (650.4500)LF312$0.01$0.01$0.01$3.00
64Construction staking base (650.5000)LF262$3.00$0.01$0.01$3.00
65Construction staking structure layout (structure) 01. B-56-0246 (650.6501)EACH1$2,000.00$3,000.00$3,000.00$2,000.00
66Construction staking concrete pavement (650.7000)LF51$10.00$0.01$0.01$10.00
67Construction staking supplemental control (project) 01. 5678-00-74 (650.9911)EACH1$1,000.00$1,200.00$1,200.00$1,000.00
68Construction staking slope stakes (650.9920)LF420$1.50$1.00$1.00$1.50
69Sawing asphalt (690.0150)LF60$2.95$2.95$6.00$2.95
70Incentive strength concrete structures (715.0502)DOL1,542$1.00$1.00$1.00$1.00
71Incentive compressive strength concrete pavement (715.0720)DOL500$1.00$1.00$1.00$1.00
72Installing and maintaining bird deterrent system (station) 01. 13+50 (999.2000.S)EACH1$2.00$0.01$1.00$1.00
73On-the-job training apprentice at $5.00/HR (ASP.1T0A)HRS1,200$5.00$5.00$5.00$5.00
74On-the-job training graduate at $5.00/HR (ASP.1T0G)HRS600$5.00$5.00$5.00$5.00
75Special 01. select crushed material for travel corridor (SPV.0195)TON21$130.00$39.84$50.00$39.84
WisDOT contract 20260210004: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.

Every contract let that day: WisDOT letting of February 10, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy