WisDOT contract 20260210019 bid tabulation
T Linn - Hillside Road; Bridge Over Cmstpp Railroad P64-101 (LOC STR, Walworth County T Linn - Hillside Road). Let by Wisconsin DOT on February 10, 2026, Walworth. 4 bids received.
- Owner
- Wisconsin DOT
- Letting
- 10 FEB 2026
- Pay items
- 72
- Data through
- 10 NOV 2026
3 of the 4 bids matched their published totals to within a dollar and are shown; the others are left out.
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 2 | Concrete Structures, Inc. | $1,969,932 | +5.0% |
| 3 | Lunda Construction Company | $2,050,278 | +9.0% |
| 4 | Zenith Tech., Inc. - Waukesha | $2,093,932 | +11% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Concrete Structures, Inc. | 2. Lunda Construction Company | 3. Zenith Tech., Inc. - Waukesha |
|---|---|---|---|---|---|---|
| 1 | Grubbing (201.0205) | STA | 5 | $800.00 | $600.00 | $800.00 |
| 2 | Removing small pipe culverts (203.0100) | EACH | 3 | $400.00 | $400.00 | $400.00 |
| 3 | Removing structure (structure) 01. P-64-101 (203.0220) | EACH | 1 | $100,000 | $200,000 | $80,000 |
| 4 | Debris containment (structure) 01. P-64-101 (203.0330) | EACH | 1 | $10,000 | $500.00 | $2,900.00 |
| 5 | Excavation common (205.0100) | CY | 455 | $18.00 | $18.00 | $18.00 |
| 6 | Excavation for structures bridges (structure) 01. B-64-215 (206.1001) | EACH | 1 | $40,000 | $69,750 | $40,500 |
| 7 | Borrow (208.0100) | CY | 609 | $23.00 | $23.00 | $23.00 |
| 8 | Backfill structure type A (210.1500) | TON | 370 | $18.00 | $22.00 | $22.00 |
| 9 | Finishing roadway (project) 01. 3846-00-74 (213.0100) | EACH | 1 | $500.00 | $500.00 | $500.00 |
| 10 | Base aggregate dense 3/4-inch (305.0110) | TON | 100 | $31.00 | $31.00 | $31.00 |
| 11 | Base aggregate dense 1 1/4-inch (305.0120) | TON | 460 | $24.50 | $24.50 | $24.50 |
| 12 | Concrete pavement approach slab (415.0410) | SY | 132 | $275.00 | $275.00 | $291.75 |
| 13 | Tack coat (455.0605) | GAL | 46 | $5.00 | $5.00 | $5.00 |
| 14 | Asphaltic surface (465.0105) | TON | 307 | $98.15 | $98.15 | $98.15 |
| 15 | Asphaltic surface driveways and field entrances (465.0120) | TON | 34 | $115.00 | $115.00 | $115.00 |
| 16 | Concrete masonry bridges (502.0100) | CY | 417 | $1,200.00 | $1,875.00 | $1,600.00 |
| 17 | Protective surface treatment (502.3200) | SY | 648 | $7.00 | $5.00 | $3.90 |
| 18 | Prestressed girder type I 28-inch (503.0128) | LF | 863 | $252.00 | $230.00 | $250.00 |
| 19 | Bar steel reinforcement HS structures (505.0400) | LB | 36,800 | $1.30 | $1.45 | $2.00 |
| 20 | Bar steel reinforcement HS coated structures (505.0600) | LB | 38,870 | $1.50 | $1.55 | $2.00 |
| 21 | Bearing pads elastomeric non- laminated (506.2605) | EACH | 30 | $150.00 | $150.00 | $125.00 |
| 22 | Steel diaphragms (structure) 01. B- 64-215 (506.4000) | EACH | 12 | $1,000.00 | $1,250.00 | $1,450.00 |
| 23 | Temporary shoring (structure) 01. B-64-215 (511.1200) | SF | 1,590 | $50.00 | $0.01 | $65.00 |
| 24 | Railing tubular type M (513.4061) | LF | 358 | $282.00 | $275.00 | $275.00 |
| 25 | Rubberized membrane waterproofing (516.0500) | SY | 14 | $44.00 | $35.00 | $95.00 |
| 26 | Apron endwalls for culvert pipe 24- inch (520.1024) | EACH | 2 | $475.00 | $475.00 | $475.00 |
| 27 | Culvert pipe class III-B 24-inch (520.3524) | LF | 62 | $100.00 | $100.00 | $100.00 |
| 28 | Piling steel HP 10-inch X 42 LB (550.1100) | LF | 1,730 | $60.00 | $42.00 | $75.00 |
| 29 | Slope paving crushed aggregate (604.0500) | SY | 379 | $120.00 | $60.00 | $28.00 |
| 30 | Pipe underdrain wrapped 6-inch (612.0406) | LF | 170 | $8.00 | $9.00 | $9.00 |
| 31 | Maintenance and repair of haul roads (project) 01. 3846-00-74 (618.0100) | EACH | 1 | $500.00 | $1.00 | $3,900.00 |
| 32 | Mobilization (619.1000) | EACH | 1 | $393,985 | $203,869 | $292,000 |
| 33 | Water (624.0100) | MGAL | 5 | $0.01 | $0.01 | $0.01 |
| 34 | Salvaged topsoil (625.0500) | SY | 2,700 | $3.50 | $3.50 | $3.50 |
| 35 | Mulching (627.0200) | SY | 1,650 | $0.50 | $0.50 | $0.50 |
| 36 | Silt fence (628.1504) | LF | 800 | $2.50 | $2.50 | $2.50 |
| 37 | Silt fence maintenance (628.1520) | LF | 1,290 | $0.01 | $0.01 | $0.01 |
| 38 | Mobilizations erosion control (628.1905) | EACH | 4 | $170.00 | $170.00 | $170.00 |
| 39 | Mobilizations emergency erosion control (628.1910) | EACH | 3 | $280.00 | $280.00 | $280.00 |
| 40 | Erosion mat urban class I type B (628.2008) | SY | 1,050 | $2.00 | $2.00 | $2.00 |
| 41 | Temporary ditch checks (628.7504) | LF | 100 | $9.50 | $9.50 | $9.50 |
| 42 | Culvert pipe checks (628.7555) | EACH | 13 | $25.00 | $25.00 | $25.00 |
| 43 | Fertilizer type B (629.0210) | CWT | 2.50 | $100.00 | $100.00 | $100.00 |
| 44 | Seeding mixture no. 30 (630.0130) | LB | 200 | $8.00 | $8.00 | $8.00 |
| 45 | Seeding temporary (630.0200) | LB | 130 | $4.00 | $4.00 | $4.00 |
| 46 | Seed water (630.0500) | MGAL | 92 | $1.00 | $1.00 | $1.00 |
| 47 | Markers culvert end (633.5200) | EACH | 2 | $200.00 | $200.00 | $200.00 |
| 48 | Posts wood 4X6-inch X 12-FT (634.0612) | EACH | 4 | $125.00 | $125.00 | $125.00 |
| 49 | Signs type II reflective F (637.2230) | SF | 12 | $35.00 | $35.00 | $35.00 |
| 50 | Removing signs type II (638.2602) | EACH | 9 | $30.00 | $30.00 | $30.00 |
| 51 | Removing small sign supports (638.3000) | EACH | 10 | $30.00 | $30.00 | $30.00 |
| 52 | Field office type B (642.5001) | EACH | 1 | $1,500.00 | $6,000.00 | $10,800 |
| 53 | Traffic control drums (643.0300) | DAY | 70 | $3.00 | $3.00 | $2.00 |
| 54 | Traffic control barricades type III (643.0420) | DAY | 3,151 | $0.75 | $0.75 | $0.55 |
| 55 | Traffic control warning lights type A (643.0705) | DAY | 6,302 | $0.25 | $0.25 | $0.10 |
| 56 | Traffic control signs (643.0900) | DAY | 2,466 | $0.50 | $0.50 | $0.45 |
| 57 | Traffic control signs PCMS (643.1050) | DAY | 14 | $65.00 | $65.00 | $75.00 |
| 58 | Traffic control (643.5000) | EACH | 1 | $1,500.00 | $1,500.00 | $4,833.00 |
| 59 | Geotextile type DF schedule A (645.0111) | SY | 70 | $8.00 | $8.00 | $8.00 |
| 60 | Marking line paint 4-inch (646.1005) | LF | 1,180 | $2.85 | $2.85 | $4.00 |
| 61 | Construction staking subgrade (650.4500) | LF | 414 | $0.01 | $0.01 | $0.01 |
| 62 | Construction staking base (650.5000) | LF | 494 | $0.01 | $2.00 | $2.00 |
| 63 | Construction staking pipe culverts (650.6000) | EACH | 1 | $600.00 | $300.00 | $300.00 |
| 64 | Construction staking structure layout (structure) 01. B-64-215 (650.6501) | EACH | 1 | $5,000.00 | $6,000.00 | $6,000.00 |
| 65 | Construction staking supplemental control (project) 01. 3846-00-74 (650.9911) | EACH | 1 | $2,750.00 | $1,500.00 | $1,500.00 |
| 66 | Construction staking slope stakes (650.9920) | LF | 537 | $0.01 | $2.00 | $2.00 |
| 67 | Sawing asphalt (690.0150) | LF | 62 | $6.00 | $6.00 | $2.95 |
| 68 | Incentive strength concrete structures (715.0502) | DOL | 2,502 | $1.00 | $1.00 | $1.00 |
| 69 | Incentive compressive strength concrete pavement (715.0720) | DOL | 40 | $1.00 | $1.00 | $1.00 |
| 70 | Railroad flagging reimbursement (801.0117) | DOL | 31,200 | $1.00 | $1.00 | $1.00 |
| 71 | Installing and maintaining bird deterrent system (station) 01. 13+50 (999.2000.S) | EACH | 1 | $1.00 | $0.01 | $1.00 |
| 72 | Special 01. temporary shoring railroad (SPV.0165) | SF | 560 | $80.00 | $95.00 | $90.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.
Every contract let that day: WisDOT letting of February 10, 2026. Compiled by Mirage Metrics.