WisDOT contract 20260210041 bid tabulation
STH 40 - STH 27; Chippewa River Bridge B-57-0018 (CTH D, Sawyer County STH 40 - STH 27). Let by Wisconsin DOT on February 10, 2026, Sawyer. 5 bids received; low bid $1,080,394 by Larson Construction Co., Inc..
- Owner
- Wisconsin DOT
- Letting
- 10 FEB 2026
- Pay items
- 69
- Data through
- 10 NOV 2026
4 of the 5 bids matched their published totals to within a dollar and are shown; the others are left out.
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Larson Construction Co., Inc. | $1,080,394 | Low |
| 2 | Sheet Piling Services LLC | $1,288,935 | +19% |
| 4 | Lunda Construction Company | $1,496,889 | +39% |
| 5 | Zenith Tech., Inc. - Waukesha | $1,515,386 | +40% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Larson Construction Co., Inc. | 2. Sheet Piling Services LLC | 3. Lunda Construction Company | 4. Zenith Tech., Inc. - Waukesha |
|---|---|---|---|---|---|---|---|
| 1 | Clearing (201.0105) | STA | 2 | $250.00 | $250.00 | $1,515.00 | $1,515.00 |
| 2 | Grubbing (201.0205) | STA | 2 | $250.00 | $250.00 | $750.00 | $750.00 |
| 3 | Removing structure over waterway debris capture (structure) 01. B-57- 0018 (203.0270) | EACH | 1 | $193,400 | $425,000 | $250,000 | $330,000 |
| 4 | Removing asphaltic surface butt joints (204.0115) | SY | 25 | $37.25 | $37.25 | $37.25 | $37.25 |
| 5 | Removing asphaltic surface milling (204.0120) | SY | 300 | $37.25 | $37.25 | $37.25 | $37.25 |
| 6 | Removing guardrail (204.0165) | LF | 482 | $2.50 | $2.50 | $3.15 | $3.15 |
| 7 | Excavation common (205.0100) | CY | 411 | $17.73 | $17.73 | $31.00 | $31.00 |
| 8 | Excavation for structures bridges (structure) 01. B-57-0018 (206.1001) | EACH | 1 | $6,600.00 | $50,000 | $15,000 | $8,800.00 |
| 9 | Backfill structure type A (210.1500) | TON | 150 | $31.31 | $31.31 | $25.00 | $24.30 |
| 10 | Finishing roadway (project) 01. 8460-00-70 (213.0100) | EACH | 1 | $1,000.00 | $1,000.00 | $500.00 | $500.00 |
| 11 | Base aggregate dense 3/4-inch (305.0110) | TON | 205 | $30.40 | $30.40 | $25.65 | $25.65 |
| 12 | Base aggregate dense 1 1/4-inch (305.0120) | TON | 900 | $22.76 | $22.76 | $24.00 | $24.00 |
| 13 | Tack coat (455.0605) | GAL | 92 | $8.51 | $8.51 | $8.51 | $8.51 |
| 14 | Asphaltic surface (465.0105) | TON | 330 | $130.00 | $130.00 | $130.00 | $130.00 |
| 15 | Concrete masonry bridges (502.0100) | CY | 353.90 | $942.00 | $850.00 | $850.00 | $1,625.00 |
| 16 | Protective surface treatment (502.3200) | SY | 860 | $3.00 | $2.50 | $5.00 | $4.30 |
| 17 | Pigmented surface sealer (502.3210) | SY | 260 | $8.00 | $2.50 | $10.00 | $13.75 |
| 18 | Adhesive anchors no. 4 bar (502.4204) | EACH | 66 | $22.00 | $10.00 | $25.00 | $27.00 |
| 19 | Adhesive anchors no. 5 bar (502.4205) | EACH | 148 | $24.00 | $20.00 | $30.00 | $31.00 |
| 20 | Bar steel reinforcement HS coated structures (505.0600) | LB | 80,780 | $2.00 | $2.00 | $1.52 | $1.50 |
| 21 | Bearing pads elastomeric non- laminated (506.2605) | EACH | 8 | $125.00 | $150.00 | $150.00 | $124.00 |
| 22 | Steel diaphragms (structure) 01. B- 57-0018 (506.4000) | EACH | 9 | $2,200.00 | $1,800.00 | $2,000.00 | $3,300.00 |
| 23 | Removing bearings (structure) 01. B-57-0018 (506.7050.S) | EACH | 8 | $100.00 | $100.00 | $1,000.00 | $1,200.00 |
| 24 | Concrete surface repair (509.1500) | SF | 100 | $111.40 | $50.00 | $125.00 | $250.00 |
| 25 | Rubberized membrane waterproofing (516.0500) | SY | 18 | $55.00 | $18.00 | $25.00 | $65.00 |
| 26 | Pipe underdrain wrapped 6-inch (612.0406) | LF | 150 | $7.50 | $7.50 | $8.00 | $8.00 |
| 27 | Anchor assemblies for steel plate beam guard (614.0150) | EACH | 4 | $225.00 | $250.00 | $200.00 | $300.00 |
| 28 | MGS guardrail 3 (614.2300) | LF | 50 | $31.75 | $31.75 | $25.50 | $25.50 |
| 29 | MGS thrie beam transition (614.2500) | LF | 160 | $97.50 | $97.50 | $94.00 | $94.00 |
| 30 | MGS guardrail terminal eat (614.2610) | EACH | 4 | $3,800.00 | $3,800.00 | $3,750.00 | $3,750.00 |
| 31 | Maintenance and repair of haul roads (project) 01. 8460-00-70 (618.0100) | EACH | 1 | $500.00 | $0.01 | $0.01 | $2,100.00 |
| 32 | Mobilization (619.1000) | EACH | 1 | $133,000 | $121,874 | $559,587 | $150,000 |
| 33 | Water (624.0100) | MGAL | 28 | $25.00 | $25.00 | $1.00 | $1.00 |
| 34 | Topsoil (625.0100) | SY | 945 | $8.50 | $8.50 | $4.00 | $4.00 |
| 35 | Mulching (627.0200) | SY | 1,155 | $0.50 | $0.50 | $0.60 | $0.60 |
| 36 | Silt fence (628.1504) | LF | 1,425 | $3.75 | $3.75 | $2.00 | $2.00 |
| 37 | Silt fence maintenance (628.1520) | LF | 2,850 | $0.10 | $0.10 | $0.01 | $0.01 |
| 38 | Mobilizations erosion control (628.1905) | EACH | 4 | $300.00 | $300.00 | $1,000.00 | $1,000.00 |
| 39 | Mobilizations emergency erosion control (628.1910) | EACH | 4 | $300.00 | $300.00 | $10.00 | $10.00 |
| 40 | Erosion mat class II type C (628.2027) | SY | 355 | $3.50 | $3.50 | $4.50 | $4.50 |
| 41 | Temporary ditch checks (628.7504) | LF | 50 | $15.00 | $15.00 | $8.00 | $8.00 |
| 42 | Fertilizer type B (629.0210) | CWT | 1 | $100.00 | $100.00 | $250.00 | $250.00 |
| 43 | Seeding mixture no. 20 (630.0120) | LB | 68 | $7.15 | $7.15 | $20.00 | $20.00 |
| 44 | Seeding temporary (630.0200) | LB | 40 | $4.10 | $4.10 | $3.00 | $3.00 |
| 45 | Seed water (630.0500) | MGAL | 34 | $25.00 | $25.00 | $1.00 | $1.00 |
| 46 | Posts wood 4X6-inch X 14-FT (634.0614) | EACH | 7 | $130.00 | $130.00 | $85.00 | $85.00 |
| 47 | Signs type II reflective H (637.2210) | SF | 6 | $35.00 | $35.00 | $17.00 | $17.00 |
| 48 | Signs type II reflective F (637.2230) | SF | 23.12 | $30.00 | $30.00 | $22.00 | $22.00 |
| 49 | Removing signs type II (638.2602) | EACH | 8 | $15.00 | $15.00 | $16.00 | $16.00 |
| 50 | Removing small sign supports (638.3000) | EACH | 7 | $15.00 | $15.00 | $15.00 | $15.00 |
| 51 | Field office type B (642.5001) | EACH | 1 | $3,300.00 | $5,000.00 | $4,500.00 | $9,500.00 |
| 52 | Traffic control barricades type III (643.0420) | DAY | 2,888 | $0.40 | $0.40 | $0.40 | $0.77 |
| 53 | Traffic control warning lights type A (643.0705) | DAY | 4,725 | $0.10 | $0.10 | $0.10 | $0.16 |
| 54 | Traffic control signs (643.0900) | DAY | 14,438 | $0.40 | $0.40 | $0.40 | $0.61 |
| 55 | Traffic control covering signs type II (643.0920) | EACH | 5 | $35.00 | $35.00 | $35.00 | $74.06 |
| 56 | Traffic control (643.5000) | EACH | 1 | $2,336.00 | $2,336.00 | $2,336.00 | $4,595.00 |
| 57 | Geotextile type DF schedule A (645.0111) | SY | 70 | $8.00 | $8.00 | $5.00 | $5.00 |
| 58 | Marking line epoxy 4-inch (646.1020) | LF | 2,050 | $2.90 | $2.65 | $2.90 | $2.90 |
| 59 | Construction staking subgrade (650.4500) | LF | 491 | $0.01 | $0.01 | $0.01 | $0.01 |
| 60 | Construction staking base (650.5000) | LF | 491 | $0.50 | $0.01 | $0.50 | $0.01 |
| 61 | Construction staking structure layout (structure) 01. B-57-0018 (650.6501) | EACH | 1 | $2,000.00 | $1,929.00 | $2,000.00 | $1,929.00 |
| 62 | Construction staking supplemental control (project) 01. 8394-00-73 (650.9911) | EACH | 1 | $750.00 | $500.00 | $750.00 | $500.00 |
| 63 | Construction staking slope stakes (650.9920) | LF | 491 | $1.00 | $0.98 | $1.00 | $0.98 |
| 64 | Sawing asphalt (690.0150) | LF | 274 | $1.79 | $2.25 | $2.25 | $2.25 |
| 65 | Incentive strength concrete structures (715.0502) | DOL | 2,123 | $1.00 | $1.00 | $1.00 | $1.00 |
| 66 | Installing and maintaining bird deterrent system (station) 01. 98+13.76 (999.2000.S) | EACH | 1 | $1.00 | $0.01 | $0.01 | $16,000 |
| 67 | On-the-job training apprentice at $5.00/HR (ASP.1T0A) | HRS | 300 | $5.00 | $5.00 | $5.00 | $5.00 |
| 68 | On-the-job training graduate at $5.00/HR (ASP.1T0G) | HRS | 300 | $5.00 | $5.00 | $5.00 | $5.00 |
| 69 | Special 01. foam void filling B-57- 0018 (SPV.0060) | EACH | 1 | $24,665 | $15,000 | $10,000 | $35,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.
Every contract let that day: WisDOT letting of February 10, 2026. Compiled by Mirage Metrics.