WisDOT contract 20260210043 bid tabulation

Amery - CTH I; Apple River Bridge B-48-0062 (CTH H, Polk County Amery - CTH I). Let by Wisconsin DOT on February 10, 2026, Polk. 4 bids received; low bid $790,773 by Larson Construction Co., Inc..

Owner
Wisconsin DOT
Letting
10 FEB 2026
Pay items
75
Data through
10 NOV 2026

3 of the 4 bids matched their published totals to within a dollar and are shown; the others are left out.

Bidders

RankBidderTotal bidAgainst the low bid
1Larson Construction Co., Inc.$790,773Low
2Sheet Piling Services LLC$930,441+18%
4Lunda Construction Company$1,008,500+28%
WisDOT contract 20260210043: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Larson Construction Co., Inc.2. Sheet Piling Services LLC3. Lunda Construction Company
1Clearing (201.0105)STA1$1.00$1.00$1.00
2Grubbing (201.0205)STA1$1.00$1.00$1.00
3Removing structure over waterway minimal debris (structure) 01. P-48- 0910 (203.0260)EACH1$33,900$100,000$120,000
4Removing asphaltic surface butt joints (204.0115)SY54$20.00$20.00$20.00
5Removing asphaltic surface milling (204.0120)SY530$20.00$20.00$20.00
6Excavation common (205.0100)CY753$13.80$13.80$13.80
7Excavation, hauling, and disposal of potential creosote contaminated soil (205.0508.S)TON112$68.50$75.00$30.00
8Excavation for structures bridges (structure) 01. B-48-0062 (206.1001)EACH1$34,600$62,000$25,000
9Cofferdams (structure) 01. B-48- 0062 (206.5001)EACH1$37,500$25,000$25,000
10Backfill structure type A (210.1500)TON310$20.25$20.25$20.25
11Finishing roadway (project) 01. 8862-00-70 (213.0100)EACH1$500.00$500.00$500.00
12Base aggregate dense 3/4-inch (305.0110)TON270$26.85$26.85$26.85
13Base aggregate dense 1 1/4-inch (305.0120)TON825$21.60$21.60$21.60
14Tack coat (455.0605)GAL110$7.50$7.50$7.50
15Asphaltic surface (465.0105)TON300$127.50$127.50$127.50
16Concrete masonry bridges (502.0100)CY232$779.00$1,200.00$850.00
17Protective surface treatment (502.3200)SY260$4.00$2.50$5.00
18Pigmented surface sealer (502.3210)SY64$8.00$2.50$20.00
19Underwater substructure inspection (structure) 01. B-48-0062 (502.9000.S)EACH1$3,500.00$5,200.00$5,200.00
20Bar steel reinforcement HS structures (505.0400)LB8,360$1.65$1.20$1.50
21Bar steel reinforcement HS coated structures (505.0600)LB32,090$1.65$1.50$1.50
22Rubberized membrane waterproofing (516.0500)SY14$60.00$20.00$25.00
23Piling cip concrete 10 3/4 X 0.25- inch (550.2104)LF1,990$61.00$55.00$35.00
24Riprap heavy (606.0300)CY125$82.00$55.00$53.00
25Pipe underdrain wrapped 6-inch (612.0406)LF160$8.00$8.00$8.00
26Anchor assemblies for steel plate beam guard (614.0150)EACH4$250.00$250.00$200.00
27Steel thrie beam structure approach (614.0200)LF21$95.00$95.00$95.00
28Steel plate beam guard class A (614.0305)LF25$25.35$25.35$25.35
29Steel plate beam guard short radius (614.0345)LF50$30.80$30.80$30.80
30Steel plate beam guard short radius terminal (614.0390)EACH1$2,240.00$2,240.00$2,240.00
31MGS guardrail 3 (614.2300)LF225$24.50$24.50$24.50
32MGS thrie beam transition (614.2500)LF120$94.00$94.00$94.00
33MGS guardrail terminal eat (614.2610)EACH3$3,750.00$3,750.00$3,750.00
34Maintenance and repair of haul roads (project) 01. 8862-00-70 (618.0100)EACH1$750.00$0.01$0.01
35Mobilization (619.1000)EACH1$85,000$83,355$298,812
36Water (624.0100)MGAL46$1.00$1.00$1.00
37Topsoil (625.0100)SY1,595$4.00$4.00$4.00
38Mulching (627.0200)SY1,230$0.60$0.60$0.60
39Silt fence (628.1504)LF1,355$2.00$2.00$2.00
40Silt fence maintenance (628.1520)LF2,710$0.01$0.01$0.01
41Mobilizations erosion control (628.1905)EACH4$500.00$500.00$500.00
42Mobilizations emergency erosion control (628.1910)EACH4$10.00$10.00$10.00
43Erosion mat class II type C (628.2027)SY1,115$4.00$4.00$4.00
44Turbidity barriers (628.6005)SY220$47.00$47.00$47.00
45Temporary ditch checks (628.7504)LF50$8.00$8.00$8.00
46Fertilizer type B (629.0210)CWT1.60$150.00$150.00$150.00
47Seeding mixture no. 20 (630.0120)LB106$12.00$12.00$12.00
48Seeding temporary (630.0200)LB64$10.00$10.00$10.00
49Seed water (630.0500)MGAL53$1.00$1.00$1.00
50Posts wood 4X6-inch X 14-FT (634.0614)EACH4$90.00$90.00$90.00
51Signs type II reflective F (637.2230)SF12$25.00$25.00$25.00
52Moving signs type II (638.2102)EACH5$80.00$80.00$80.00
53Removing signs type II (638.2602)EACH4$15.00$15.00$15.00
54Removing small sign supports (638.3000)EACH4$15.00$15.00$15.00
55Moving small sign supports (638.4000)EACH4$70.00$70.00$70.00
56Field office type B (642.5001)EACH1$4,000.00$3,000.00$3,500.00
57Traffic control barricades type III (643.0420)DAY2,613$0.45$0.45$0.45
58Traffic control warning lights type A (643.0705)DAY4,275$0.10$0.10$0.10
59Traffic control signs (643.0900)DAY11,756$0.50$0.50$0.50
60Traffic control (643.5000)EACH1$4,012.00$4,012.00$4,012.00
61Geotextile type DF schedule A (645.0111)SY110$5.00$5.00$5.00
62Geotextile type HR (645.0120)SY275$3.25$3.00$5.00
63Marking line epoxy 4-inch (646.1020)LF1,005$5.50$5.45$5.50
64Construction staking subgrade (650.4500)LF465$0.01$0.01$0.01
65Construction staking base (650.5000)LF465$0.01$0.01$1.00
66Construction staking structure layout (structure) 01. B-48-0062 (650.6501)EACH1$2,685.00$2,685.00$3,000.00
67Construction staking supplemental control (project) 01. 8862-00-70 (650.9911)EACH1$500.00$500.00$1,000.00
68Construction staking slope stakes (650.9920)LF465$0.98$0.98$1.00
69Sawing asphalt (690.0150)LF486$2.25$2.25$2.25
70Incentive strength concrete structures (715.0502)DOL1,392$1.00$1.00$1.00
71Installing and maintaining bird deterrent system (station) 01. 10+00 (999.2000.S)EACH1$2,900.00$0.01$0.01
72On-the-job training apprentice at $5.00/HR (ASP.1T0A)HRS300$5.00$5.00$5.00
73On-the-job training graduate at $5.00/HR (ASP.1T0G)HRS300$5.00$5.00$5.00
74Special 01. removing existing timber piling (SPV.0060)EACH10$1,000.00$100.00$50.00
75Special 01. select crushed material for travel corridor (SPV.0195)TON14$94.00$35.00$25.00
WisDOT contract 20260210043: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.

Every contract let that day: WisDOT letting of February 10, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy