WisDOT contract 20260310036 bid tabulation
T Ackley, Range Line Road; Black Brook Bridge, B-34-0066 (LOC STR, Langlade County T Ackley, Range Line Road). Let by Wisconsin DOT on March 10, 2026, Langlade. 5 bids received.
- Owner
- Wisconsin DOT
- Letting
- 10 MAR 2026
- Pay items
- 52
- Data through
- 10 NOV 2026
4 of the 5 bids matched their published totals to within a dollar and are shown; the others are left out.
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 2 | Larson Construction Co., Inc. | $433,903 | +11% |
| 3 | Janke General Contractors, Inc. | $449,401 | +15% |
| 4 | Sheet Piling Services LLC | $487,185 | +24% |
| 5 | Lunda Construction Company | $564,463 | +44% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Larson Construction Co., Inc. | 2. Janke General Contractors, Inc. | 3. Sheet Piling Services LLC | 4. Lunda Construction Company |
|---|---|---|---|---|---|---|---|
| 1 | Removing structure (structure) 01. P-34-917 (203.0220) | EACH | 1 | $36,300 | $55,000 | $90,000 | $175,598 |
| 2 | Excavation common (205.0100) | CY | 110 | $29.09 | $36.00 | $29.09 | $29.09 |
| 3 | Excavation for structures bridges (structure) 01. B-34-66 (206.1001) | EACH | 1 | $36,500 | $55,000 | $75,000 | $34,074 |
| 4 | Backfill structure type A (210.1500) | TON | 230 | $32.60 | $50.00 | $48.00 | $32.60 |
| 5 | Finishing roadway (project) 01. 9833-03-72 (213.0100) | EACH | 1 | $1,000.00 | $100.00 | $1,000.00 | $1,000.00 |
| 6 | Base aggregate dense 3/4-inch (305.0110) | TON | 20 | $42.50 | $53.00 | $42.50 | $42.50 |
| 7 | Base aggregate dense 1 1/4-inch (305.0120) | TON | 170 | $27.23 | $36.00 | $27.23 | $27.23 |
| 8 | Tack coat (455.0605) | GAL | 20 | $19.00 | $19.00 | $19.00 | $19.00 |
| 9 | Asphaltic surface (465.0105) | TON | 70 | $167.42 | $167.42 | $167.42 | $167.42 |
| 10 | Concrete masonry bridges (502.0100) | CY | 140 | $789.00 | $765.00 | $825.00 | $750.00 |
| 11 | Protective surface treatment (502.3200) | SY | 177 | $4.00 | $5.00 | $4.00 | $3.00 |
| 12 | Bar steel reinforcement HS structures (505.0400) | LB | 3,260 | $1.75 | $3.35 | $1.80 | $1.08 |
| 13 | Bar steel reinforcement HS coated structures (505.0600) | LB | 18,910 | $1.75 | $1.70 | $1.50 | $1.18 |
| 14 | Railing tubular type M (513.4061) | LF | 131 | $379.00 | $420.00 | $315.00 | $625.00 |
| 15 | Rubberized membrane waterproofing (516.0500) | SY | 18 | $60.00 | $50.00 | $20.00 | $25.00 |
| 16 | Piling steel HP 10-inch X 42 LB (550.1100) | LF | 280 | $78.20 | $71.00 | $62.00 | $53.00 |
| 17 | Riprap heavy (606.0300) | CY | 105 | $114.66 | $140.00 | $102.00 | $114.66 |
| 18 | Pipe underdrain wrapped 6-inch (612.0406) | LF | 140 | $7.20 | $10.00 | $10.00 | $7.20 |
| 19 | Maintenance and repair of haul roads (project) 01. 9833-03-72 (618.0100) | EACH | 1 | $1,000.00 | $100.00 | $0.01 | $1,500.00 |
| 20 | Mobilization (619.1000) | EACH | 1 | $65,183 | $40,000 | $50,723 | $54,581 |
| 21 | Water (624.0100) | MGAL | 6 | $50.00 | $25.00 | $50.00 | $50.00 |
| 22 | Topsoil (625.0100) | SY | 145 | $8.90 | $8.00 | $8.90 | $8.90 |
| 23 | Mulching (627.0200) | SY | 210 | $1.50 | $3.00 | $1.50 | $1.50 |
| 24 | Silt fence (628.1504) | LF | 245 | $4.25 | $3.00 | $4.25 | $4.25 |
| 25 | Silt fence maintenance (628.1520) | LF | 490 | $0.10 | $0.01 | $0.10 | $0.10 |
| 26 | Mobilizations erosion control (628.1905) | EACH | 4 | $200.00 | $50.00 | $200.00 | $200.00 |
| 27 | Mobilizations emergency erosion control (628.1910) | EACH | 4 | $200.00 | $50.00 | $200.00 | $200.00 |
| 28 | Erosion mat class II type C (628.2027) | SY | 50 | $5.00 | $7.00 | $5.00 | $5.00 |
| 29 | Turbidity barriers (628.6005) | SY | 175 | $52.19 | $25.00 | $0.01 | $52.19 |
| 30 | Temporary ditch checks (628.7504) | LF | 50 | $15.00 | $8.00 | $15.00 | $15.00 |
| 31 | Fertilizer type B (629.0210) | CWT | 0.30 | $100.00 | $275.00 | $100.00 | $100.00 |
| 32 | Seeding mixture no. 20 (630.0120) | LB | 11 | $7.15 | $15.00 | $7.15 | $7.15 |
| 33 | Seeding temporary (630.0200) | LB | 8 | $10.00 | $7.00 | $10.00 | $10.00 |
| 34 | Seed water (630.0500) | MGAL | 5 | $50.00 | $25.00 | $50.00 | $50.00 |
| 35 | Posts wood 4X6-inch X 14-FT (634.0614) | EACH | 4 | $140.00 | $160.00 | $140.00 | $140.00 |
| 36 | Signs type II reflective F (637.2230) | SF | 12 | $30.00 | $30.00 | $30.00 | $30.00 |
| 37 | Removing signs type II (638.2602) | EACH | 6 | $20.00 | $50.00 | $20.00 | $20.00 |
| 38 | Removing small sign supports (638.3000) | EACH | 6 | $20.00 | $50.00 | $20.00 | $20.00 |
| 39 | Field office type B (642.5001) | EACH | 1 | $4,250.00 | $2,500.00 | $1,000.00 | $2,000.00 |
| 40 | Traffic control barricades type III (643.0420) | DAY | 1,450 | $0.40 | $0.40 | $0.40 | $0.40 |
| 41 | Traffic control warning lights type A (643.0705) | DAY | 2,255 | $0.10 | $0.10 | $0.10 | $0.10 |
| 42 | Traffic control signs (643.0900) | DAY | 965 | $0.40 | $0.40 | $0.40 | $0.40 |
| 43 | Traffic control (643.5000) | EACH | 1 | $2,000.00 | $2,000.00 | $2,000.00 | $2,000.00 |
| 44 | Geotextile type DF schedule A (645.0111) | SY | 50 | $8.50 | $4.00 | $5.00 | $8.50 |
| 45 | Geotextile type HR (645.0120) | SY | 210 | $7.10 | $5.00 | $5.00 | $7.10 |
| 46 | Construction staking subgrade (650.4500) | LF | 100 | $0.01 | $0.01 | $0.01 | $0.01 |
| 47 | Construction staking base (650.5000) | LF | 100 | $0.01 | $1.00 | $1.00 | $1.00 |
| 48 | Construction staking structure layout (structure) 01. B-34-66 (650.6501) | EACH | 1 | $2,200.00 | $2,200.00 | $2,200.00 | $2,200.00 |
| 49 | Construction staking supplemental control (project) 01. 9833-03-72 (650.9911) | EACH | 1 | $764.00 | $764.00 | $764.00 | $764.00 |
| 50 | Construction staking slope stakes (650.9920) | LF | 100 | $3.00 | $3.00 | $3.00 | $3.00 |
| 51 | Sawing asphalt (690.0150) | LF | 43 | $5.00 | $3.00 | $5.00 | $5.00 |
| 52 | Incentive strength concrete structures (715.0502) | DOL | 840 | $1.00 | $1.00 | $1.00 | $1.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.
Every contract let that day: WisDOT letting of March 10, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.