WisDOT contract 20260414025 bid tabulation
T Arcadia, Middle Road; Myers Valley Creek Bridge B-61-0294 (LOC STR, Trempealeau County T Arcadia, Middle Road). Let by Wisconsin DOT on April 14, 2026, Trempealeau. 4 bids received; low bid $447,891 by Larson Construction Co., Inc..
- Owner
- Wisconsin DOT
- Letting
- 14 APR 2026
- Pay items
- 53
- Data through
- 10 NOV 2026
3 of the 4 bids matched their published totals to within a dollar and are shown; the others are left out.
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Larson Construction Co., Inc. | $447,891 | Low |
| 3 | Lunda Construction Company | $499,760 | +12% |
| 4 | Sheet Piling Services LLC | $529,602 | +18% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Larson Construction Co., Inc. | 2. Lunda Construction Company | 3. Sheet Piling Services LLC |
|---|---|---|---|---|---|---|
| 1 | Removing structure over waterway remove debris (structure) 01. P-61- 0195 (203.0250) | EACH | 1 | $39,186 | $100,000 | $110,000 |
| 2 | Excavation common (205.0100) | CY | 120 | $20.00 | $20.00 | $20.00 |
| 3 | Excavation, hauling, and disposal of creosote contaminated soil (205.0506.S) | TON | 55 | $115.00 | $110.00 | $110.00 |
| 4 | Excavation for structures bridges (structure) 01. B-61-0294 (206.1001) | EACH | 1 | $18,500 | $27,500 | $62,500 |
| 5 | Backfill structure type A (210.1500) | TON | 300 | $20.00 | $20.00 | $20.00 |
| 6 | Finishing roadway (project) 01. 7276-00-76 (213.0100) | EACH | 1 | $500.00 | $500.00 | $500.00 |
| 7 | Base aggregate dense 3/4-inch (305.0110) | TON | 20 | $45.00 | $45.00 | $45.00 |
| 8 | Base aggregate dense 1 1/4-inch (305.0120) | TON | 210 | $28.00 | $28.00 | $28.00 |
| 9 | Tack coat (455.0605) | GAL | 11 | $4.25 | $4.25 | $4.25 |
| 10 | Asphaltic surface (465.0105) | TON | 55 | $251.68 | $251.68 | $251.68 |
| 11 | Concrete masonry bridges (502.0100) | CY | 129 | $798.40 | $800.00 | $925.00 |
| 12 | Protective surface treatment (502.3200) | SY | 178 | $4.00 | $5.00 | $2.50 |
| 13 | Bar steel reinforcement HS structures (505.0400) | LB | 4,180 | $1.65 | $1.38 | $1.75 |
| 14 | Bar steel reinforcement HS coated structures (505.0600) | LB | 19,180 | $1.65 | $1.38 | $1.85 |
| 15 | Railing tubular type M (513.4061) | LF | 90 | $352.00 | $350.00 | $325.00 |
| 16 | Rubberized membrane waterproofing (516.0500) | SY | 12 | $65.00 | $20.00 | $18.00 |
| 17 | Piling cip concrete 10 3/4 X 0.25- inch (550.2104) | LF | 1,190 | $65.00 | $50.00 | $35.00 |
| 18 | Riprap heavy (606.0300) | CY | 190 | $70.00 | $70.00 | $70.00 |
| 19 | Pipe underdrain wrapped 6-inch (612.0406) | LF | 140 | $8.00 | $8.00 | $8.00 |
| 20 | Maintenance and repair of haul roads (project) 01. 7276-00-76 (618.0100) | EACH | 1 | $1,000.00 | $0.01 | $0.01 |
| 21 | Mobilization (619.1000) | EACH | 1 | $57,707 | $66,874 | $47,231 |
| 22 | Water (624.0100) | MGAL | 4 | $25.00 | $25.00 | $25.00 |
| 23 | Topsoil (625.0100) | SY | 360 | $5.00 | $5.00 | $5.00 |
| 24 | Silt fence (628.1504) | LF | 300 | $2.00 | $2.00 | $2.00 |
| 25 | Silt fence maintenance (628.1520) | LF | 600 | $0.10 | $0.10 | $0.10 |
| 26 | Mobilizations erosion control (628.1905) | EACH | 2 | $150.00 | $150.00 | $150.00 |
| 27 | Mobilizations emergency erosion control (628.1910) | EACH | 2 | $150.00 | $150.00 | $150.00 |
| 28 | Erosion mat urban class I type B (628.2008) | SY | 360 | $3.00 | $3.00 | $3.00 |
| 29 | Turbidity barriers (628.6005) | SY | 210 | $40.00 | $40.00 | $40.00 |
| 30 | Fertilizer type B (629.0210) | CWT | 0.50 | $120.00 | $120.00 | $120.00 |
| 31 | Seeding mixture no. 20 (630.0120) | LB | 15 | $8.00 | $8.00 | $8.00 |
| 32 | Seeding mixture no. 60 (630.0160) | LB | 1 | $20.00 | $20.00 | $20.00 |
| 33 | Seeding temporary (630.0200) | LB | 10 | $8.00 | $8.00 | $8.00 |
| 34 | Seed water (630.0500) | MGAL | 15 | $0.01 | $0.01 | $0.01 |
| 35 | Posts wood 4X6-inch X 14-FT (634.0614) | EACH | 4 | $110.00 | $110.00 | $110.00 |
| 36 | Signs type II reflective F (637.2230) | SF | 12 | $32.00 | $32.00 | $32.00 |
| 37 | Removing signs type II (638.2602) | EACH | 10 | $25.00 | $25.00 | $25.00 |
| 38 | Removing small sign supports (638.3000) | EACH | 6 | $25.00 | $25.00 | $25.00 |
| 39 | Field office type B (642.5001) | EACH | 1 | $3,800.00 | $3,000.00 | $2,000.00 |
| 40 | Traffic control barricades type III (643.0420) | DAY | 1,360 | $0.45 | $0.45 | $0.45 |
| 41 | Traffic control warning lights type A (643.0705) | DAY | 2,720 | $0.25 | $0.25 | $0.25 |
| 42 | Traffic control signs (643.0900) | DAY | 1,088 | $0.45 | $0.45 | $0.45 |
| 43 | Traffic control (643.5000) | EACH | 1 | $3,900.00 | $3,900.00 | $3,900.00 |
| 44 | Geotextile type DF schedule A (645.0111) | SY | 88 | $5.00 | $2.00 | $3.00 |
| 45 | Geotextile type HR (645.0120) | SY | 320 | $3.00 | $3.00 | $3.00 |
| 46 | Construction staking subgrade (650.4500) | LF | 100 | $0.01 | $0.01 | $0.01 |
| 47 | Construction staking base (650.5000) | LF | 100 | $0.01 | $2.00 | $0.01 |
| 48 | Construction staking structure layout (structure) 01. B-61-0294 (650.6501) | EACH | 1 | $1,659.00 | $2,250.00 | $1,659.00 |
| 49 | Construction staking supplemental control (project) 01. 7276-00-76 (650.9911) | EACH | 1 | $369.00 | $250.00 | $369.00 |
| 50 | Construction staking slope stakes (650.9920) | LF | 100 | $1.50 | $2.00 | $1.50 |
| 51 | Sawing asphalt (690.0150) | LF | 36 | $4.00 | $4.00 | $4.00 |
| 52 | Incentive strength concrete structures (715.0502) | DOL | 774 | $1.00 | $1.00 | $1.00 |
| 53 | Maintaining bird deterrent system (station) 01. sta. 10+75 (999.2005.S) | EACH | 1 | $1,000.00 | $0.01 | $0.01 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.
Every contract let that day: WisDOT letting of April 14, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.