WisDOT contract 20261110024 bid tabulation

STH 66 - CTH C; Bear Creek Bridge, B-49-0203 (CTH II, Portage County STH 66 - CTH C). Let by Wisconsin DOT on November 10, 2026, Portage. 6 bids received; low bid $717,328 by Larson Construction Co., Inc..

Owner
Wisconsin DOT
Letting
10 NOV 2026
Pay items
61
Data through
10 NOV 2026

5 of the 6 bids matched their published totals to within a dollar and are shown; the others are left out.

Bidders

RankBidderTotal bidAgainst the low bid
1Larson Construction Co., Inc.$717,328Low
2Sheet Piling Services LLC$749,688+5.0%
3Radtke Contractors Inc.$772,885+8.0%
5Lunda Construction Company$900,639+26%
6Janke General Contractors, Inc.$988,756+38%
WisDOT contract 20261110024: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Larson Construction Co., Inc.2. Sheet Piling Services LLC3. Radtke Contractors Inc.4. Lunda Construction Company5. Janke General Contractors, Inc.
1Removing structure (structure) 01. P-49-0055 (203.0220)EACH1$10,500$3,500.00$30,108$163,500$9,000.00
2Removing structure (structure) 01. V-49-0139 (203.0220)EACH1$2,500.00$2,500.00$30,108$2,500.00$8,000.00
3Removing guardrail (204.0165)LF350$2.50$2.50$5.00$2.50$3.20
4Excavation common (205.0100)CY1,720$19.50$19.50$19.50$19.50$35.00
5Excavation for structures bridges (structure) 01. B-49-0203 (206.1001)EACH1$10,500$7,500.00$32,122$7,500.00$7,350.00
6Excavation for structures culverts (structure) 01. V-49-0139 (206.2001)EACH1$6,500.00$3,500.00$25,387$3,500.00$12,600
7Cofferdams (structure) 01. B-49- 0203 (206.5001)EACH1$58,400$55,000$46,486$100,000$181,285
8Cofferdams (structure) 01. V-49- 0139 (206.5001)EACH1$24,000$45,000$20,391$15,000$21,250
9Backfill granular grade 2 (209.2500)TON720$20.50$20.50$20.50$20.50$31.90
10Backfill structure type A (210.1500)TON382$22.25$22.25$22.25$22.25$28.50
11Finishing roadway (project) 01. 6792-00-70 (213.0100)EACH1$1,000.00$1,000.00$1,000.00$1,000.00$198.00
12Base aggregate dense 3/4-inch (305.0110)TON71$30.00$30.00$30.00$30.00$64.50
13Base aggregate dense 1 1/4-inch (305.0120)TON1,390$24.75$24.75$24.75$24.75$32.00
14Select crushed material (312.0110)TON1,410$32.50$32.50$32.50$32.50$36.85
15Tack coat (455.0605)GAL87$9.00$9.00$9.00$9.00$9.00
16Asphaltic surface (465.0105)TON320$136.80$136.80$136.80$136.80$136.80
17Concrete masonry bridges (502.0100)CY154$759.00$925.00$716.68$750.00$810.00
18Protective surface treatment (502.3200)SY161$4.00$5.00$4.26$2.00$5.00
19Bar steel reinforcement HS structures (505.0400)LB4,080$1.70$2.00$1.52$1.20$3.39
20Bar steel reinforcement HS coated structures (505.0600)LB19,562$1.70$2.50$1.49$1.20$2.10
21Railing tubular type M (513.4061)LF132$510.00$400.00$369.20$375.00$277.00
22Rubberized membrane waterproofing (516.0500)SY18$61.00$25.00$64.32$25.00$32.00
23Pre-boring rock or consolidated materials (550.0020)LF160$235.00$215.00$147.19$350.00$530.00
24Piling steel HP 10-inch X 42 LB (550.1100)LF200$86.00$60.00$50.39$62.00$103.00
25Riprap heavy (606.0300)CY187$65.00$65.00$65.00$65.00$91.00
26Pipe underdrain wrapped 6-inch (612.0406)LF180$6.50$6.50$6.50$6.50$16.00
27Maintenance and repair of haul roads (project) 01. 6792-00-70 (618.0100)EACH1$500.00$0.01$250.00$500.00$198.00
28Mobilization (619.1000)EACH1$68,500$76,064$102,648$88,639$90,000
29Water (624.0100)MGAL30$40.00$40.00$40.00$40.00$12.00
30Salvaged topsoil (625.0500)SY1,123$3.75$3.75$3.75$3.75$8.00
31Silt fence (628.1504)LF1,075$2.75$2.75$2.75$2.75$2.70
32Silt fence maintenance (628.1520)LF1,075$0.95$0.95$0.95$0.95$0.03
33Mobilizations erosion control (628.1905)EACH4$100.00$100.00$100.00$100.00$298.00
34Mobilizations emergency erosion control (628.1910)EACH4$175.00$175.00$175.00$175.00$298.00
35Erosion mat class II type C (628.2027)SY2,010$2.50$2.50$2.50$2.50$6.45
36Turbidity barriers (628.6005)SY340$36.50$36.50$36.50$36.50$37.00
37Seeding mixture no. 20 (630.0120)LB91$5.50$5.50$5.50$5.50$13.50
38Seeding temporary (630.0200)LB55$4.50$4.50$4.50$4.50$8.10
39Seed water (630.0500)MGAL32$25.00$25.00$25.00$25.00$7.50
40Posts wood 4X6-inch X 12-FT (634.0612)EACH4$125.00$125.00$125.00$125.00$140.00
41Signs type II reflective F (637.2230)SF12$38.50$38.50$38.50$38.50$21.21
42Removing signs type II (638.2602)EACH4$25.00$25.00$25.00$25.00$37.30
43Removing small sign supports (638.3000)EACH4$50.00$50.00$50.00$50.00$37.30
44Field office type B (642.5001)EACH1$4,900.00$1,500.00$2,629.04$3,500.00$5,535.00
45Traffic control barricades type III (643.0420)DAY2,124$0.45$0.45$0.45$0.45$0.45
46Traffic control warning lights type A (643.0705)DAY3,304$0.20$0.20$0.20$0.20$0.20
47Traffic control signs (643.0900)DAY1,652$0.45$0.45$0.45$0.45$0.45
48Traffic control (643.5000)EACH1$1,700.00$1,700.00$1,700.00$1,700.00$1,700.00
49Geotextile type DF schedule A (645.0111)SY58$5.50$5.50$5.50$5.50$3.56
50Geotextile type HR (645.0120)SY306$6.25$6.25$6.25$6.25$4.72
51Marking line epoxy 6-inch (646.2020)LF150$5.00$28.00$28.00$28.00$29.65
52Construction staking subgrade (650.4500)LF531$0.01$3.00$0.01$0.01$0.01
53Construction staking base (650.5000)LF531$2.00$3.00$1.00$1.00$1.00
54Construction staking structure layout (structure) 01. B-49-0203 (650.6501)EACH1$3,000.00$3,000.00$3,200.00$3,200.00$3,200.00
55Construction staking supplemental control (project) 01. 6792-00-70 (650.9911)EACH1$1,000.00$1,200.00$750.00$750.00$750.00
56Construction staking slope stakes (650.9920)LF531$2.00$3.50$2.00$2.00$2.00
57Sawing asphalt (690.0150)LF53$6.50$6.50$6.50$6.50$10.00
58Incentive strength concrete structures (715.0502)DOL924$1.00$1.00$1.00$1.00$1.00
59Installing and maintaining bird deterrent system (station) 01. sta 10+00 (999.2000.S)EACH1$1,500.00$0.01$500.00$2,000.00$4,800.00
60On-the-job training apprentice at $5.00/HR (ASP.1T0A)HRS300$5.00$5.00$5.00$5.00$5.00
61On-the-job training graduate at $5.00/HR (ASP.1T0G)HRS600$5.00$5.00$5.00$5.00$5.00
WisDOT contract 20261110024: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.

Every contract let that day: WisDOT letting of November 10, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy