Marking line grooved wet ref contrast epoxy 4-inch, WisDOT 646.1545
Low bidders on WisDOT contracts carried a median of $3.00 per LF for this item, over the 24 months to 10 NOV 2026, across 1 low bids. Half of all 2 bids fell between $3.12 and $3.38.
- Owner
- Wisconsin DOT
- Item
- 646.1545
- Unit
- LF
- Data through
- 10 NOV 2026
WisDOT prints this item as “Marking Line Grooved Wet Ref Contrast Epoxy 4-Inch”.
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2022 | 20 | 19 | $3.50 | 52 | $4.00 |
| 2023 | 21 | 20 | $3.20 | 74 | $3.08 |
| 2024 | 2 | 2 | $6.15 | 7 | $7.00 |
| 2025 | 1 | 1 | $3.00 | 2 | $3.25 |
Bid prices as published, not adjusted for inflation.
By county
| County | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Milwaukee | 12 | $5.65 | 44 | $5.12 |
| Waukesha | 6 | $3.00 | 24 | $3.00 |
| Kenosha | 4 | $3.38 | 18 | $3.50 |
| Racine | 3 | $2.50 | 9 | $2.50 |
| Walworth | 3 | $4.00 | 5 | $4.00 |
Countys with at least three low bids, over all lettings.
By quantity
| Quantity (LF) | Low bids | Low-bid median |
|---|---|---|
| 10 to 784 | 10 | $9.50 |
| 826 to 2,625 | 11 | $4.24 |
| 2,898 to 8,440 | 10 | $3.10 |
| 9,745 to 68,549 | 11 | $2.50 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Who is lowest on this line
| Bidder | Lines bid | Lowest on the line |
|---|---|---|
| Zignego Company, Inc. | 17 | 13 (76%) |
| Lalonde Contractors Incorporated | 13 | 10 (77%) |
| Zenith Tech., Inc. - Waukesha | 13 | 8 (62%) |
| Vinton Construction Company | 8 | 6 (75%) |
| Michels Road & Stone, Inc. | 8 | 6 (75%) |
| Payne and Dolan, Inc | 8 | 5 (63%) |
The lowest unit price on each line, whoever won the contract, over all lettings in the data, for firms with five lines or more.
Latest contracts with this item
| Let | Contract | County | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 08 APR 2025 | 20250408030 | Waukesha | 425 | $3.00 | $3.25 | 2 | Musson Bros., Inc. | WisDOT |
| 08 OCT 2024 | 20241008006 | Milwaukee | 570 | $5.30 | $7.65 | 2 | Zignego Company, Inc. | WisDOT |
| 08 OCT 2024 | 20241008009 | Milwaukee | 1,306 | $7.00 | $7.00 | 5 | A.W. Oakes & Son, Inc. | WisDOT |
| 12 DEC 2023 | 20231212016 | Milwaukee | 200 | $9.00 | $9.50 | 2 | Lunda Construction Company | WisDOT |
| 14 NOV 2023 | 20231114047 | Waukesha | 165 | $10.00 | $10.00 | 8 | Michels Road & Stone, Inc. | WisDOT |
| 12 SEP 2023 | 20230912012 | Oneida | 2,124 | $4.50 | $4.50 | 2 | Northeast Asphalt, Inc | WisDOT |
| 08 AUG 2023 | 20230808007 | Milwaukee | 6,770 | $2.75 | $2.65 | 8 | A.W. Oakes & Son, Inc. | WisDOT |
| 11 JUL 2023 | 20230711002 | Ozaukee | 68,549 | $2.00 | $2.00 | 5 | Zignego Company, Inc. | WisDOT |
| 11 JUL 2023 | 20230711010 | Milwaukee | 1,246 | n/a | $7.00 | 3 | WisDOT | |
| 09 MAY 2023 | 20230509004 | Waukesha | 952 | $3.00 | $2.92 | 4 | Vinton Construction Company | WisDOT |
| 09 MAY 2023 | 20230509006 | Kenosha | 1,778 | $3.50 | $3.50 | 6 | A.W. Oakes & Son, Inc. | WisDOT |
| 09 MAY 2023 | 20230509010 | Waukesha | 38,802 | $3.90 | $3.85 | 2 | Stark Pavement Corporation | WisDOT |
| 09 MAY 2023 | 20230509011 | Waukesha | 553 | $2.00 | $2.00 | 3 | Rock Road Companies, Inc. | WisDOT |
| 09 MAY 2023 | 20230509013 | Racine | 50,223 | $2.50 | $2.50 | 6 | Payne and Dolan, Inc | WisDOT |
| 09 MAY 2023 | 20230509029 | Racine | 1,465 | $3.15 | $3.15 | 2 | Stark Pavement Corporation | WisDOT |
Filter this item by your own quantity, county and period, or check your price against it, in the WisDOT explorer.
How these prices were read
WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are WisDOT's own: this item is compared with WisDOT contracts only.
- Prices are bid prices, not paid prices. Use them as a reference range, never as a quote.
- The data runs to the WisDOT letting of 10 NOV 2026 and was rebuilt on 26 NOV 2026.
Your own bid history, read the same way