I-80 Mississippi River Bridge Replacement
- Location
- LeClaire / Rapids City, IA / IL, United States. Location shown at city level. See it on the map
- Stage
- Development, as of October 14, 2026 (Illinois Department of Transportation and Iowa Department of Transportation, p. 1).
- Status
- Research record, not reviewed: compiled from the sources below, and each fact checked against them on 24 Nov 2026; an editor has not yet reviewed it.
- Research as of
Owners, scope and amount
Every figure the record holds, each a different object: a project cost, a financed scope, a grant or a contract value are never added together, and an older estimate stays as history.
| Amount | What it is | Scope | As of | Source |
|---|---|---|---|---|
| US$442 M | Capital estimate | Whole project | 2025 | Illinois Department of Transportation, p. 2'I-80: $441.5 million to replace the bridge over the Mississippi River. Illinois is leading the project, with Iowa sharing equally in the cost.' |
| US$481 M | Capital estimate | One package | 2 Dec 2025 | Bi-State Regional Commission (Quad Cities MPO), p. 1Quad Cities TIP line IL-28-11, 'I-80 Mississippi River, IL 84 & RR Bridge Replacement', total estimated cost; construction engineering is a separate line |
| US$40 M | Capital estimate | One package | 2 Dec 2025 | Bi-State Regional Commission (Quad Cities MPO), p. 1Quad Cities TIP line IL-28-12, construction engineering for the bridge replacement |
Contracts and teams
Contracts and teams: No construction contract awarded yet Illinois Department of Transportation and Iowa Department of Transportation, p. 1. The project entered final design, which is to 'prepare construction plans'; the October 2026 newsletter gives 'Construction Begins EARLY 2028'.
Milestones
| Date | Milestone | Scope | Source |
|---|---|---|---|
| April 2020 | public meeting | Whole project | Illinois Department of Transportation and Iowa Department of Transportation, p. 1 |
| November 2023 | preferred alternative | Whole project | Illinois Department of Transportation, District 2, p. 23 |
| October 2024 | public hearing | Whole project | Illinois Department of Transportation and Iowa Department of Transportation, p. 1 |
| April 10, 2025 | approval | Whole project | Illinois Department of Transportation, District 2, with the Iowa Department of Transportation and FHWA, p. 15 |
| October 14, 2026 | public meeting | Whole project | Illinois Department of Transportation and Iowa Department of Transportation, p. 1 |
| 2028 | planned construction start | Whole project | Illinois Department of Transportation and Iowa Department of Transportation, p. 1 |
| 2030 | planned construction | One package | Illinois Department of Transportation and Iowa Department of Transportation, p. 1 |
About the project
Replacement of the 1967 Interstate 80 bridge over the Mississippi River between LeClaire, Iowa and Rapids City, Illinois by two bridges, one for each direction, each with two through lanes and an auxiliary lane. The new eastbound bridge is built about 20 feet west of the existing bridge, which is then demolished so that the westbound bridge, with a multi-use path, can be built on its alignment; the US 67 and IL 84 interchanges are rebuilt and the I-80/I-88 interchange is expanded. The Illinois Department of Transportation leads the project, with Iowa sharing the cost equally, and lists $441.5 million to replace the bridge in its FY 2026 to 2031 program. The project is in final design, with construction planned to begin in early 2028.
Sources
- I-80 Mississippi River Bridge: Project Overview, Illinois Department of Transportation with the Iowa Department of Transportation (project website). 'The plan will replace the existing bridge with two new structures, one for each direction of travel.' 'A new bridge will first be built immediately west of the existing bridge. Traffic will then shift to the new structure while the existing bridge is removed and replaced.' 'The Final Design phase is expected to result in construction-ready plans, with construction to begin in 2028.'. Consulted 24 Nov 2026.
- I-80 Mississippi River Bridge (home page), Illinois Department of Transportation with the Iowa Department of Transportation (project website). 'The Illinois Department of Transportation is conducting this study in conjunction with the Iowa Department of Transportation'. Consulted 24 Nov 2026.
- A New I-80 Crossing Is Taking Shape: From Vision to Final Design (newsletter, Phase 2 public meeting), Illinois Department of Transportation and Iowa Department of Transportation, 14 Oct 2026. 'After more than five years of planning, engineering, environmental review and public input, the I-80 Mississippi River Bridge project has entered the final design phase.' Timeline: 'Public Meeting APR 2020', 'Public Hearing OCT 2024', 'Final Design Phase Begins 2025', 'Public Meeting OCT 14, 2026', 'Construction Begins EARLY 2028'.. Consulted 24 Nov 2026.
- Exhibit boards, Phase 2 public meeting, Illinois Department of Transportation and Iowa Department of Transportation, 14 Oct 2026. Board text: 'PLANNED RELOCATION' 'JUNE' 'to' 'OCTOBER' '2027' 'Mussels will be relocated before construction begins'; 'Construction of River Bridge and approach roadway areas expected to begin in 2028'; 'Two lanes in each direction are expected to remain open on I-80 during most construction'. Consulted 24 Nov 2026.
- Contract scope: anticipated work areas (Phase 2 public meeting), Illinois Department of Transportation and Iowa Department of Transportation, 14 Oct 2026. 'EB Mississippi River Bridge (MRB) Summary of Work: New Companion Bridge Anticipated Construction: 2028-2029' 'WB Mississippi River Bridge (MRB) Summary of Work: I-80 MRB removal & replacement bridge. Anticipated Construction: 2030-2031' 'flyover ramp w/5 new bridges ... Anticipated Construction: 2031-2032'. Consulted 24 Nov 2026.
- Section diagram (rendering with dimensioned cross sections of the two bridges), Illinois Department of Transportation and Iowa Department of Transportation, 14 Oct 2026. Labels on the image: '15'0" MUP', '6'0" Shldr.', '12'0" Lane' (three), '12'0" Shldr.' on one bridge; '12'0" Shldr.', '12'0" Lane' (three), '6'0" Shldr.' on the other. Consulted 24 Nov 2026.
- Roll plot map (plan of the selected alternative), Illinois Department of Transportation and Iowa Department of Transportation, 14 Oct 2026. Ramp labels on the plan: 'I-80 WESTBOUND EXIT RAMP (RAMP C)', 'I-80 EASTBOUND ENTRANCE RAMP (RAMP B)' at 'US ROUTE 67 (S CODY RD)'; 'I-80 WESTBOUND ENTRANCE RAMP (RAMP H)', 'I-80 EASTBOUND EXIT RAMP (RAMP E)' at 'ILLINOIS ROUTE 84'. Consulted 24 Nov 2026.
- Environmental Document, Federal Approved Categorical Exclusion, I-80 over Mississippi River (with appendices: Purpose and Need, biological assessments, agency meeting minutes), Illinois Department of Transportation, District 2, with the Iowa Department of Transportation and FHWA, Apr 2025. 'The new bridge for the eastbound traffic would be constructed approximately 20 feet west of the existing bridge, which would be demolished following the completion of the new bridge.' (p. 11 of 68); 'a 14-foot multi-use path for pedestrian and bicycle traffic was added to the project on the east side of the westbound bridge' (p. 14 of 68); FHWA signature 'Date: 2025.04.10'; 'The existing navigation span is 370 feet while the US Coast Guard (USCG) requires a minimum 420-foot-wide navigation span for new structures.' (Purpose and Need). Consulted 24 Nov 2026.
- Preferred Alternative Technical Memorandum, I-80 over Mississippi River (November 2023, revised April 2025), Illinois Department of Transportation, District 2, Nov 2023. 'As a result, Alternative 5 is recommended as the Preferred Alternative for the I-80 MRB.' 'both alternatives were combined to create a single Preferred Alternative for the entire project called Preferred Alternative 5B.'. Consulted 24 Nov 2026.
- FY 2026-2031 Multi-Year Program for Roads and Bridges, District 2 fact sheet, Illinois Department of Transportation. 'I-80: $441.5 million to replace the bridge over the Mississippi River. Illinois is leading the project, with Iowa sharing equally in the cost.'. Consulted 24 Nov 2026.
- December 2, 2025 Transportation Policy Committee, FFY2026-2029 Transportation Improvement Program amendments, Bi-State Regional Commission (Quad Cities MPO), 2 Dec 2025. 'IL-28-11 2028 I-80 Mississippi River, IL 84 & RR Bridge Replacement MAINT $481,000,000 $216,450,000 NHPP $24,050,000 STA New Project. Amendment Approved 12/2025'. Consulted 24 Nov 2026.