IAH Terminal Redevelopment Program

Location
Houston, TX, United States. Location shown at city level. See it on the map
Stage
Opened, as of November 2026 (Houston Airports).
Status
Research record, not reviewed: compiled from the sources below, and each fact checked against them on 19 Nov 2026; an editor has not yet reviewed it.
Research as of

Owners, scope and amount

FieldValueSource
Owner or sponsorHouston Airports (City of Houston)
CategoryAirports
AmountUS$1.458 billion (US dollars), as of October 2024Houston Airports
What the amount coversProgramme value.
Threshold evidenceA cited project-scope figure meets the threshold
Sourced facts in the research record

Every figure the record holds, each a different object: a project cost, a financed scope, a grant or a contract value are never added together, and an older estimate stays as history.

AmountWhat it isScopeAs ofSource
US$1.46 bnProgramme valueProgrammeOct 2024Houston Airports
Financial records, each with its kind and scope

Contracts and teams

Contracts and teams: Not found in the sources consulted.

Milestones

DateMilestoneScopeSource
November 2019construction startWhole projectHouston Airports
October 22, 2024openingWhole projectHouston Airports
February 24, 2025openingWhole projectHouston Airports
Dated milestones, at the precision of their source

About the project

$1.458 billion programme modernizing international facilities at George Bush Intercontinental Airport. The 160,000 sq ft Terminal D-West Pier with six gates (D1 to D6), construction of which began in November 2019 with the demolition of the old Terminal C-North, opened on October 22, 2024. The new Terminal E Ticketing Lobby opened on February 24, 2025, which the airport's review of 2025 calls the opening of the first phase of the International Central Processor (ICP), 'the largest modernization project in the airport's history'; the lobby was to evolve later in 2025 into the ICP, replacing the Terminal E and Terminal D ticketing lobbies, with TSA screening expanded to 17 lanes. The October 2024 release scheduled the ICP in two phases, winter 2025 and summer 2025 (United's Terminal E operations first, the international airlines second).