- Under construction, as of November 2026 (Texas Department of Transportation).
- Status
- Research record, not reviewed: compiled from the sources below, and each fact checked against them on 19 Nov 2026; an editor has not yet reviewed it.
- Research as of
Owners, scope and amount
| Field | Value | Source |
|---|---|---|
| Owner or sponsor | Texas Department of Transportation | |
| Category | Highways | |
| Amount | Not collected yet | |
| Threshold evidence | A comparable project-wide cost is still needed |
Every figure the record holds, each a different object: a project cost, a financed scope, a grant or a contract value are never added together, and an older estimate stays as history.
| Amount | What it is | Scope | As of | Source |
|---|---|---|---|---|
| US$2.14 bn | Capital estimate, approx. | One package | Jul 2026 | Texas Department of TransportationIn July 2026 the Texas Transportation Commission authorized TxDOT to issue a request for qualifications for NHHIP Segment 3C-2, an 'approximately $2.14 billion design-build project' around the I-10 and I-69 interchange. No contract is awarded. It is not the whole I-45 programme. |
Contracts and teams
Contracts and teams: Not found in the sources consulted.
About the project
In July 2026 the Texas Transportation Commission authorized TxDOT to issue a request for qualifications for NHHIP Segment 3C-2, an approximately US$2.14bn design-build project around the I-10 and I-69 interchange. It is not the whole I-45 programme.
Scope notes
- In July 2026 the Texas Transportation Commission authorized TxDOT to issue a request for qualifications for NHHIP Segment 3C-2, an 'approximately $2.14 billion design-build project' around the I-10 and I-69 interchange. No contract is awarded. It is not the whole I-45 programme. Texas Department of Transportation
Sources
- I-45 North Houston Highway Improvement Project – official project evidence, Texas Department of Transportation, Jul 2026. The July 2026 release describes an approximately US$2.14bn design-build package around the I-10 and I-69 interchange. It is not the whole I-45 programme.. Consulted 9 Nov 2026.
- NHHIP: Segment 3, Texas Department of Transportation. 'Segment 3B-1 is the drainage improvement project along St. Emanuel Street in East Downtown. Construction began in October 2024.'; 'Segment 3B-2 is the project to rebuild the I-69 mainlanes from State Highway (SH) 288 to I-45, including the I-69/SH 288 interchange. Construction begin in January 2025.'. Consulted 19 Nov 2026.