Kapalama Container Terminal
- Location
- Honolulu, HI, United States. Location shown at city level. See it on the map
- Stage
- Under construction, as of March 2025 (Hawaii Department of Transportation).
- Status
- Research record, not reviewed: compiled from the sources below, and each fact checked against them on 19 Nov 2026; an editor has not yet reviewed it.
- Research as of
Owners, scope and amount
| Field | Value | Source |
|---|---|---|
| Owner or sponsor | Hawaii Department of Transportation, Harbors Division | |
| Category | Ports | |
| Amount | US$500 million (US dollars), as of March 2021 | Hawaii Department of Transportation |
| What the amount covers | Project value, approx. | |
| Threshold evidence | A cited project-scope figure meets the threshold |
Every figure the record holds, each a different object: a project cost, a financed scope, a grant or a contract value are never added together, and an older estimate stays as history.
| Amount | What it is | Scope | As of | Source |
|---|---|---|---|---|
| US$500 M | Project value, approx. | Whole project | Mar 2021 | Hawaii Department of Transportation, Harbors Division |
| US$174 M | Project value | One phase | Mar 2021 | Hawaii Department of Transportation, Harbors Division |
| US$350 M | Contract value | One package | Oct 2020 | Hawaii Department of Transportation, Harbors Division |
Contracts and teams
| Company | Role | Package | Source |
|---|---|---|---|
| Kiewit Infrastructure West | Phase 2 contractor | Phase 2 waterside construction, Piers 40-43 | Hawaii Department of Transportation, Harbors Division |
Milestones
| Date | Milestone | Scope | Source |
|---|---|---|---|
| January 2018 | construction start | Whole project | Hawaii Department of Transportation, Harbors Division |
| October 21, 2020 | award | Whole project | Hawaii Department of Transportation, Harbors Division |
| March 1, 2021 | Groundbreaking | Whole project | Hawaii Department of Transportation, Harbors Division |
About the project
New container terminal on the former Kapalama Military Reservation in Honolulu Harbor, which HDOT calls the largest capital improvement project in Hawaii harbors history and an approximately half-billion-dollar project that will increase cargo capacity by 40 percent. Phase 1 (a 65.9-acre container yard, $174 million) was completed in 2020; Phase 2, a $350 million contract awarded to Kiewit Infrastructure West in October 2020 (stated as $352.5 million in the 2021 release), builds the waterside works at Piers 40 to 43: 18.5 acres of new fast land, 1,860 linear feet of berthing for two container ships, up to six gantry cranes, dredging along the waterfront and up to the federal channel, and widening of the water basin between Piers 40 and 41. The 2021 release expected Phase 2 to be complete in early 2024; in March 2025 HDOT's Land Matters agenda carried a request to authorize a construction right-of-entry for Kiewit to transport and process material dredged from the terminal at Piers 42 and 43.
Sources
- Major milestone in commercial harbors modernization: Dedication of Kapalama Container Terminal Phase 1 & groundbreaking of Phase 2, Hawaii Department of Transportation, Harbors Division, 2 Mar 2021. Body: 'this approximately half billion-dollar project will increase cargo capacity by 40-percent'; Phase 1 'cost of $174 million'; 'Phase 2 was awarded in late 2020 for $352.5 million'; 65.9-acre and 18.5-acre yards; '1863 linear feet'; dredging and widening of Piers 40 and 41; ceremony Monday, March 1, 2021. Consulted 12 Nov 2026.
- HDOT Harbors Division announces award for critical improvements project, Hawaii Department of Transportation, Harbors Division, 21 Oct 2020. Body: 'The awarded contract of $350 million features the waterside construction at Piers 40-43'; '1,860 linear feet of new berthing space for two container ships to dock simultaneously and up to six gantry cranes'; 'widening of the water basin between Piers 40 and 41'; 'the largest capital improvement project in Hawaii harbors history'; start spring 2021, completion winter 2023. Consulted 12 Nov 2026.
- Kapalama Container Terminal Project Ahead of Schedule and on Budget as it Enters Phase 2, Hawaii Department of Transportation, Harbors Division, 19 Dec 2019. Body: 'Phase 1 began January 2018 ... at a cost of $163 million'; Phase 2 estimated $200-300 million; 84 acres of new container space. Consulted 12 Nov 2026.
- Agenda for meeting on Hawaii Department of Transportation land matters, March 27, 2025, Hawaii Department of Transportation, 27 Mar 2025. Item 5 (PDF, read locally with pymupdf after WebFetch downloaded it): 'REQUEST FOR AUTHORIZATION TO ISSUE A CONSTRUCTION RIGHT-OF-ENTRY (CROE) TO KIEWIT INFRASTRUCTURE WEST CO., FOR TRANSPORT AND PROCESSING/DRYING MATERIALS DREDGED FROM KAPALAMA CONTAINER TERMINAL (KCT) AT PIERS 42 AND 43, SITUATED AT KALAELOA BARBERS POINT HARBOR'; meeting Thursday, March 27, 2025. Consulted 12 Nov 2026.