Research record, not reviewed
Sabine-Neches Waterway Channel Improvement Project
- Location
- Port Arthur / Beaumont, TX, United States. Location shown at city level. See it on the map
- Stage
- Under construction, as of April 2026 (Sabine-Neches Navigation District).
- Status
- Research record, not reviewed: compiled from the sources below, and each fact checked against them on 19 Nov 2026; an editor has not yet reviewed it.
- Research as of
Owners, scope and amount
| Field | Value | Source |
|---|---|---|
| Owner or sponsor | U.S. Army Corps of Engineers with the Sabine-Neches Navigation District (non-federal sponsor) | |
| Category | Ports | |
| Amount | US$1.4 billion (US dollars), as of November 2026 | Sabine-Neches Navigation District |
| What the amount covers | Capital estimate, approx. | |
| Threshold evidence | A cited project-scope figure meets the threshold |
Every figure the record holds, each a different object: a project cost, a financed scope, a grant or a contract value are never added together, and an older estimate stays as history.
| Amount | What it is | Scope | As of | Source |
|---|---|---|---|---|
| US$1.4 bn | Capital estimate, approx. | Whole project | Nov 2026 | Sabine-Neches Navigation District |
| US$239 M | Contract value | One package | Apr 2026 | Sabine-Neches Navigation District |
Contracts and teams
| Company | Role | Package | Source |
|---|---|---|---|
| Callan Marine, Ltd. | dredging contractor | $239 million dredging contract (Taylor Bayou intersection to Port Arthur and Beaumont, two anchorage basins) | Sabine-Neches Navigation District |
Milestones
| Date | Milestone | Scope | Source |
|---|---|---|---|
| 2019 | construction start | Whole project | Sabine-Neches Navigation District |
| April 14, 2026 | award | Whole project | Sabine-Neches Navigation District |
| April 15, 2028 | planned completion | One package | Sabine-Neches Navigation District |
About the project
Deepening of the 57-mile Sabine-Neches Waterway from 40 to 48 feet, a federally authorized project that USACE estimates at $1.4 billion, 60 percent federal and 40 percent non-federal; construction began in 2019. On April 14, 2026 the Navigation District signed a $239 million dredging contract with Callan Marine, Ltd. (about 20 million cubic yards, two additional anchorage basins, 44 feet of usable draft from the Taylor Bayou intersection to the Ports of Port Arthur and Beaumont, dredging from early June 2026 to April 15, 2028), under a memorandum of understanding signed with USACE on April 1, 2026, positioning the project for completion eight years ahead of USACE's most recent schedule before the District assumes responsibility for all remaining construction.
Sources
- Deepening Project, Sabine-Neches Navigation District. Project page: 'USACE estimates that it will take $1.4 billion to deepen the Sabine-Neches Waterway'; 'federal funds will account for 60 percent of the cost'; 'Construction on the latest deepening project began in 2019'; 40 feet to 48 feet; fifty-seven miles. Consulted 12 Nov 2026.
- Sabine-Neches Navigation District Signs $239 Million Dredging Contract with Callan Marine to Accelerate Sabine-Neches Waterway Deepening by Eight Years, Sabine-Neches Navigation District, 14 Apr 2026. Press release (PDF, text layer): '$239 million dredging contract with Callan Marine, Ltd.'; 'approximately 20 million cubic yards'; 'two critically needed additional anchorage basins'; '44 feet of usable draft from the Taylor Bayou intersection'; 'begin in early June 2026 and must be completed by April 15, 2028'; 'from 40 feet to 48 feet'; MOU of April 1; 'prior to SNND assuming responsibility for all remaining construction'. PDF text read locally (pymupdf) after WebFetch downloaded it.. Consulted 12 Nov 2026.