MSD Project Clear Solids Management Upgrades

Location
St. Louis area, MO, United States. Location shown at city level. See it on the map
Stage
Stage not confirmed: Not collected yet.
Status
Research record, not reviewed: compiled from the sources below, and each fact checked against them on 19 Nov 2026; an editor has not yet reviewed it.
Research as of

Owners, scope and amount

FieldValueSource
Owner or sponsorMetropolitan St. Louis Sewer District
CategoryWater
AmountUS$898 million (US dollars), as of September 20, 2023U.S. Environmental Protection Agency
What the amount coversCost of the WIFIA-financed scope: Cost for the scope covered in this EPA fact sheet. It can be a phase or tranche and is not automatically the latest programme-wide cost.
Threshold evidenceOnly a financed-scope figure meets the threshold; to reconcile
Sourced facts in the research record

Water projects are counted apart and left out of totals while their place in the atlas is decided.

Every figure the record holds, each a different object: a project cost, a financed scope, a grant or a contract value are never added together, and an older estimate stays as history.

AmountWhat it isScopeAs ofSource
US$898 MCost of the WIFIA-financed scopeScope financed by WIFIA20 Sep 2023U.S. Environmental Protection AgencyCost for the scope covered in this EPA fact sheet. It can be a phase or tranche and is not automatically the latest programme-wide cost.
Financial records, each with its kind and scope

Contracts and teams

Contracts and teams: Not found in the sources consulted.

Milestones

DateMilestoneScopeSource
September 20, 2023Financing closedScope financed by WIFIAU.S. Environmental Protection Agency
Dated milestones, at the precision of their source

About the project

EPA identifies new biosolids processing and dewatering infrastructure.

Scope notes

Sources

See it on the map. How the atlas qualifies a record.