Haul truck fleet sizing calculator
How many trucks does a shift need to move its tonnes? Enter the target, the payload, the cycle at the face and the three time factors your fleet records. Each loss is counted once: the queue at the loader sits in the cycle, never in a factor. Add the number of loaders to see whether the loader or the trucks set the pace.
Send one shift of dispatch or GPS data.
Our agents send you back what they read from it: trips, loading, queuing and cycle times per truck. A note on the fleet and the system it reports to is enough to start, with no file.
See fleet and haulage intelligence
Prefer to talk it through? Book a call
How to use it
- Enter the tonnes the shift must deliver to the crusher or the dump, the scheduled shift length and the rated payload of the truck class, with a fill factor if the trucks carry less than rated.
- Break the cycle into its legs: spot, queue, loading, haul loaded, dump, return empty. Take measured averages from the fleet management system over several shifts, not one good cycle.
- Enter the three time factors as your systems report them, after checking which losses each one already removes (next section). A loss counted in the cycle must not be removed again by a factor.
- To check the loader, enter the number of loaders and, if you have it, their own working share of the shift.
- Read the trucks required, the loader check and the scenario rows. Change one input at a time to see what moves the count.
Where each minute is counted
- Shift length
- The scheduled hours of the shift. What falls outside it is already out of the calculation. Includes: time the truck is not scheduled (no work planned, holidays, shutdowns).
- Physical availability
- Available hours divided by scheduled hours. It removes downtime. Includes: breakdowns and repairs, planned maintenance and services.
- Use of availability
- Operating hours divided by available hours. It removes standby, the time the truck is available but not operated. Includes: shift change, meal and coffee breaks, safety and crew meetings, no operator, site-wide weather stoppage, loader out of digging, no face to work.
- Operating efficiency
- Working hours divided by operating hours. It removes operating delays, the stops of a truck that is manned and running. Includes: refuelling and lubrication, blasting clearance, operator change during the shift, loader moving or down while the truck waits for it, stops for road or pit cleanup, crusher or dump closed.
- Cycle
- Minutes from one load to the next, waits included. The working hours are divided by it. Includes: spot at the loader, queue at the loader while it loads another truck, loading, haul loaded, dump, queue at the dump or crusher, return empty.
The allocation follows the time categories of the Global Mining Guidelines Group, which files waiting at the loading unit and travelling empty under working time, shift change and breaks under standby, and refuelling and blasting under operating delay. The three factors multiply to working hours over scheduled hours, so each hour is removed once. Systems name these ratios differently: some call the first one mechanical availability, some report one combined utilisation. What matters is the denominator of each figure and the losses it already removes. If your utilisation already deducts the queue, enter the queue as 0.
Measured inputs: the cycle legs, the three factors and the loader's working share, read from the fleet management and maintenance systems. Planning inputs: the target, the payload, the fill factor and the scenario rows, which show what a longer or shorter haul would do.
The formula
cycle = spot + queue + loading + haul + dump + return
working hours = shift hours × physical availability × use of availability × operating efficiency
trips per truck = working hours × 60 / cycle
tonnes per truck = trips × payload × fill factor
trucks required = ceiling(target / tonnes per truck)
Trucks come whole, so the result is rounded up and the calculator shows the capacity the rounding leaves, and the cycle at which one truck fewer would still make the target. The 1979 paper on Palabora's truck requirements below uses the same cycle-time method, and notes that the allowance for waiting and delays goes either into the cycle or into a final efficiency factor: once.
Sources
- Global Mining Guidelines Group, A Standardized Time Classification Framework for Mobile Equipment in Surface Mining (2020). Time categories, which loss belongs where, and the availability, use of availability and operating efficiency ratios.
- Plaistowe and Algeo, The determination of haulage-truck requirements for an open-pit operation, SAIMM Journal (1979). The cycle-time method for truck requirements, and the efficiency allowance counted once.
The loader check
loader minutes per truck = spot + loading
loads per shift = loaders × loader working hours × 60 / loader minutes per truck
trucks that keep the loaders busy = loads per shift / (truck working hours × 60 / cycle without queue)
match factor = trucks in the fleet / trucks that keep the loaders busy
production = smaller of truck capacity and loader capacity
When trucks and loaders work the same hours, the match factor reduces to the familiar trucks × loading time / (loaders × truck cycle). Below 1 the loader waits for trucks; above 1 trucks wait for the loader, and a truck added past that point adds queue, not tonnes.
The cycle used here leaves the queue out, because the queue is what an over-trucked loader produces. Counting the spot as loader time assumes the trucks are loaded from one side; with double-sided loading the spot overlaps the previous truck's loading, and the check is conservative.
A worked example
A quarry must move 12,000 t per 12-hour shift with 90 t trucks and one loader. Cycle: 0.5 min spot, 1.5 min queue, 3 min loading, 9 min haul, 1 min dump, 6.5 min return, so 21.5 minutes. Physical availability 85%, use of availability 85%, operating efficiency 90%: 12 × 0.85 × 0.85 × 0.90 = 7.803 working hours, so 21.78 trips and 1,960 t per truck and shift. 12,000 / 1,960 = 6.12, so 7 trucks, with 13,719 t of capacity and 14% in hand. The loader works 75% of the shift, 9 hours: at 3.5 minutes per truck it can load 154 trucks, 13,860 t, so it covers the target, and it can keep 6.6 trucks busy (154.3 loads / 23.4 trips per truck without queue). With 7 trucks the match factor is 1.06: part of the seventh truck's time goes into the queue the cycle already counts. With haul and return 20% longer the cycle reaches 24.6 minutes and the fleet 8 trucks. Had the 1.5-minute queue also been deducted from the operating efficiency, the unrounded count would have risen from 6.12 to 6.58 (× 21.5 / 20) for a loss already paid for.
What an average cannot show
- It works on averages. Trucks bunch on the ramp and arrive at the loader in groups, so even a fleet with a match factor below 1 queues at times, and the queue grows quickly as the match factor nears 1. The average queue you measure carries that effect for today's fleet; it will not stay the same if you add or remove trucks.
- Shift change, the first load of the shift and the last trips that cannot finish before the end are averaged into the use of availability. Production within the shift is not flat, and a target per hour can be missed at the start and end of each shift even when the shift total is met.
- One average cycle stands for one circuit. Several faces or dumps at different distances, mixed truck classes or a crusher with its own capacity need one calculation per circuit, or a weighted cycle.
- Payload is in tonnes: if you plan in loose cubic metres, convert with the loose density of the material.
- This is a planning estimate, not a fleet simulation. Before buying or parking trucks, replay the fleet management history or run a discrete-event simulation that models arrivals, queues and dispatch.
FAQ
Divide the tonnes the shift must move by what one truck delivers in that shift: its trips (working hours × 60 / cycle time) times its payload. Working hours are the scheduled shift hours multiplied by physical availability, use of availability and operating efficiency. Round the result up to whole trucks.
In one of them, never both. This calculator keeps it in the cycle, where the fleet management system measures it, and expects the time factors not to deduct it. If your utilisation figure already removes waiting at the loader, enter the queue as 0. Counting a 2-minute queue twice in a 22-minute cycle adds 10% to the truck count.
Physical availability is available hours over scheduled hours: it removes breakdowns and maintenance. Use of availability is operating hours over available hours: it removes standby such as shift change, breaks and no operator. Operating efficiency is working hours over operating hours: it removes delays of a running truck such as refuelling and blasting. Their product is the working share of the shift.
The number of trucks divided by the number that keeps the loaders exactly busy, which with equal working hours is trucks × loading time / (loaders × truck cycle). Below 1 the loader waits; above 1 trucks queue. Fill in the loader check to get it for your fleet.
There is no typical value: it depends on haul distance, grade, rolling resistance, loader size and traffic on the ramp. Measure it from the fleet management system over several shifts and use the average with its spread, not a single good cycle.
Yes: the arithmetic is the same for any load, haul and dump cycle, whether the trucks are rigid haulers in a pit, articulated trucks on an earthworks site or road trucks at a quarry. What changes is the cycle and the realistic time factors.
The factors in this formula are read off records, not guessed.