Free templates / Construction

Submittal Log Template (Excel)

A free Excel submittal log for contractors: review periods by document type, counted in calendar or working days with your holidays, every resubmission kept as its own revision, and the latest date each submittal can go out, counted back from the date the item is needed on site and the supplier's lead time. Late and at-risk items are flagged.

Download the Excel template

Free, no sign-up. Opens in Excel, Google Sheets and LibreOffice.

Mirage does this work from your own documents. See RFI and submittal automation

Who uses it, and when

Project engineers and project managers at general contractors keep the submittal log from the start of procurement to closeout. Subcontractors and suppliers produce the submittals; the architect and engineers review them; the superintendent needs the log to know which materials can be ordered and installed.

The log matters most on jobs with long-lead items (switchgear, curtain wall, elevators, structural steel), where a submittal that goes out late, or comes back for resubmission, pushes the delivery back by the same time or more. Its job is to make that visible while there is still time to act.

What is in the file

Submittal log
The settings (how review periods and lead times are counted, a default review period, the status date), then one row per submittal: number, specification section, description, type, who provides it, reviewer, date required on site, supplier lead time, void and notes. Computed: the review period used, approval needed by, submit by, number of cycles, current revision, last submitted, review due, last returned, status, days in review, projected approval, float and a flag.
Revisions
One row per submission cycle: submittal number (picked from the log), revision, date submitted, date returned, reviewer action, reviewer and notes. Computed: the review period, the review due date, days in review and a check (review overdue, returned after the due date, revision number used twice, number not in the log).
Review periods
Document types as labels you edit (shop drawings, product data, samples, mix design, calculations, test report, certificate, warranty, O&M manual, other), each with the review period your contract gives it. The Type list on the log comes from here.
Holidays
Up to 100 public holidays or site shutdowns, skipped when a count is set to working days.
Instructions
How to fill it, step by step, and the limits.

Column by column

Submittal no.
Your number, often prefixed by the specification section. A resubmittal keeps its number: the new cycle is a row on the Revisions sheet.
Spec section
The section that requires the submittal, from its 'Submittals' article (part 1 of each section in a MasterFormat specification).
Type
Picked from the Review periods sheet, which sets the review period. A type with no period there uses the default at the top of the log.
From and reviewer
The subcontractor or supplier who prepares it, and who reviews it.
Required on site
The date the material or equipment must be on site, from the schedule.
Lead time (days)
Fabrication and delivery time after approval, as the supplier quotes it, counted in calendar or working days per the setting at the top.
Approval needed by
Computed: required on site minus lead time.
Submit by (latest)
Computed: approval needed by minus the review period. The latest date the submittal, or its resubmission, can go out without delaying the work.
Cycles and current revision
Computed from the Revisions sheet: how many times the submittal went out, and the highest revision number.
Last submitted, review due, last returned
Computed from the latest revision's row. The review due date is the date submitted plus the review period, in calendar or working days.
Status
Computed: Not submitted, In review, the reviewer's action on the latest revision (Approved, Approved as noted, Reviewed for information, Revise and resubmit, Rejected), or Void.
Days in review
Computed for the latest cycle, up to the return date or, while it is out, the status date.
Projected approval and float
Computed. Projected approval is the return date once approved, the review due date while in review, and otherwise the status date plus a full review period, as if the submittal went out that day. Float is approval needed by minus projected approval, in calendar days: negative means the item will reach site late.
Flag
Computed. Late: not submitted by the submit-by date, review overdue, resubmission after the submit-by date, or approval projected after the needed date. It also names what is missing: no required-on-site date, no review period for the type, the same revision number entered twice.

How to use it

  1. At the top of the log, choose how review periods and lead times are counted (calendar or working days), set a default review period and, if you count working days, list the project's holidays on the Holidays sheet.
  2. On the Review periods sheet, enter the period your contract gives for each document type. Rename or add types as your specification names them.
  3. Go through the specification section by section and list every submittal it requires, before the first one is due, with the date needed on site and the supplier's lead time.
  4. Each time a submittal goes out, add a row on the Revisions sheet: its number, the revision (0 for the first, then 1, 2...) and the date submitted. When it comes back, enter the date returned and the reviewer's action.
  5. Leave the status date empty to work on today, or set it to see the log as of a meeting date. Review the flags and the float every week, in the meeting where the design team is present.

Limits

  • Working days skip Saturdays, Sundays and the Holidays sheet. Another working week, such as a six-day week, is not handled.
  • One review period per document type. A submittal reviewed on a different period than its type needs a type of its own on the Review periods sheet; no formula needs editing.
  • The float of an item not yet submitted, or sent back for resubmission, assumes it goes out on the status date and takes the full review period. It is a projection, not a schedule.
  • The submit-by date is when the submittal must go out; the time the supplier needs to prepare it comes before that date.
  • The log tracks dates; it does not check the content of a submittal against the specification. That review is the design team's.
  • 300 submittals, 500 revision rows, 20 document types and 100 holidays.

A worked example

An invented example, with the log set to count review periods in working days and lead times in calendar days, a status date of 16 October 2026, shop drawings reviewed in 10 working days and product data in 7.

Structural steel shop drawings are needed on site on 15 December; the fabricator quotes 42 days after approval, so approval is needed by 3 November and the submittal must go out by 20 October. Revision 0 went out on 14 September, was due back on 28 September and came back on 29 September marked Revise and resubmit: the Revisions sheet flags it as returned after the due date. Revision 1 went out on 5 October, is due back on 19 October and has spent 9 working days in review. Projected approval 19 October, float 15 days, no flag.

Tile samples have no period on the Review periods sheet, so the default of 10 working days applies. Needed on site on 30 October with 14 days of lead time, approval is needed by 16 October and the samples had to go out by 2 October. Nothing has been sent: the row turns red, 'Late: not submitted by the submit-by date', with a float of minus 14 days.

HVAC product data is needed on site on 31 December with 30 days of lead time: approval needed by 1 December. With Thanksgiving, 26 November, on the Holidays sheet, the 7 working days of review put the submit-by date at 19 November instead of 20. Sent on 20 November, its review is due on 2 December: one day after approval is needed, so the row turns red, 'Late: approval projected after the needed date', with a float of minus 1.

Switch the review count to calendar days and the steel's revision 1 is due back on 15 October: on 16 October it shows 'Late: review overdue'.

Mistakes to avoid

  • Building the log as submittals arrive instead of from the specification. The ones nobody thought of are the ones that end up late.
  • Ignoring lead time. A submittal sent 'on time' against the review period can still be too late for fabrication.
  • Overwriting the first submission's dates when it comes back for resubmission. Add a revision row: the history shows where the time went, and who held it.
  • Mixing calendar and working days. The contract states which one the review period is in; set the switch to match it, and count the supplier's lead time the way the supplier quotes it.
  • Starting fabrication on an unapproved submittal to save time. If the reviewer marks it up, the cost is the contractor's.

Questions

  • A document or sample the contractor sends to the design team for review before fabrication or installation: shop drawings, product data, samples, mix designs, test reports, certificates. It shows how the contractor intends to meet the contract documents.

  • The list of every submittal the specification requires, with its dates, reviewer, status and revision. It tells the team which submittals are late to go out or late to come back, and which materials can be ordered.

  • The contract sets it, sometimes per type of submittal and in calendar or working days. The template takes a period per document type and the counting unit you choose, and uses a default period for any type you leave empty.

  • Set the review count, the lead time count, or both, to Working days and list the holidays on the Holidays sheet. The template then uses WORKDAY and NETWORKDAYS, which skip Saturdays, Sundays and those dates.

  • Add a row on the Revisions sheet with the same submittal number and the next revision number. The log reads the latest revision for its dates and status, and the earlier rows stay as the history.

  • The reviewer accepts the submittal with corrections marked on it; the contractor can proceed if it follows the notes, without resubmitting unless the notes say so. 'Revise and resubmit' means it cannot proceed until a new revision is approved.

Submittals listed from the specification

This log tracks the submittals you list. Mirage deploys AI agents that read the specification, list every required submittal with its section, and keep the log current as packages come and go, for your project engineers to review.