ALDOT contract 20250228012 bid tabulation
ROADWAY SAFETY IMPROVEMENTS (SAFETY WIDENING AND SCORING) ON CR-15 FROM THE JUNCTION OF SR-49 NORTHEAST OF REELTOWN TO THE JUNCTION OF SR-50. Let by Alabama DOT on February 28, 2025, Tallapoosa, 0401. 2 bids received; low bid $767,052 by Gary Ingram Grading & Paving, Inc..
- Owner
- Alabama DOT
- Letting
- 28 FEB 2025
- Pay items
- 10
- Data through
- 28 AUG 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Gary Ingram Grading & Paving, Inc. | $767,052 | Low |
| 2 | East Alabama Paving Company, Inc. | $903,745 | +18% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Gary Ingram Grading & Paving, Inc. | 2. East Alabama Paving Company, Inc. |
|---|---|---|---|---|---|
| 0010 | Tack coat (405A000) | GAL | 1,374 | $1.00 | $5.00 |
| 0020 | Superpave bituminous concrete wearing surface layer, leveling, 3/8" maximum aggregate size mix, esal range A/B (424A338) | TON | 200 | $129.85 | $151.52 |
| 0030 | Superpave bituminous concrete upper binder layer, patching, 1" maximum aggregate size mix, esal range A/B (424B640) | TON | 300 | $161.75 | $205.89 |
| 0040 | Superpave bituminous concrete lower binder layer, widening, 1" maximum aggregate size mix, esal range A/B (424B677) | TON | 5,094 | $104.65 | $130.05 |
| 0050 | Scoring bituminous pavement surface (428A001) | MI | 15 | $720.00 | $600.00 |
| 0060 | Aggregate surfacing (1" down, crusher run) (430B043) | TON | 1,794 | $53.25 | $8.16 |
| 0070 | Mobilization (600A000) | LS | 1 | $35,104 | $98,670 |
| 0080 | Construction fuel (maximum bid limited to $ 36,000.00) (698A000) | LS | 1 | $0.00 | $0.00 |
| 0090 | Construction signs (740B000) | SF | 522 | $5.52 | $10.00 |
| 0100 | Pilot car (740O000) | EACH | 1 | $13,780 | $14,800 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ALDOT's tabulation for this contract. ALDOT bid tabulation PDFs, one per letting, January 2022 to August 2026, with bidder names and totals from each letting's vendor ranking. Every bid matched its published total.
Every contract let that day: ALDOT letting of February 28, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.