ALDOT contract 20250328010 bid tabulation

PLANING, RESURFACING, GUARDRAIL INSTALLATION, AND STRIPE ON SR-10 (US-231) FROM THE INTERSECTION OF SR-15 (US-29) TO THE JUNCTION OF DIAMOND DRIVE IN TROY. Let by Alabama DOT on March 28, 2025, Pike, 0705. 2 bids received; low bid $2,833,185 by Apac-Alabama, Inc..

Owner
Alabama DOT
Letting
28 MAR 2025
Pay items
44
Data through
28 AUG 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Apac-Alabama, Inc.$2,833,185Low
2Wiregrass Construction Company, Inc.$3,825,998+35%
ALDOT contract 20250328010: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Apac-Alabama, Inc.2. Wiregrass Construction Company, Inc.
0010Removing guardrail (206D001)LF2,188$2.06$2.21
0020Removing guardrail end anchor (all type) (206E008)EACH10$206.00$275.77
0030Tack coat (405A000)GAL17,457$3.95$6.38
0040Planing existing pavement (approximately 1.10" thru 2.0" thick) (408A052)SY167,397$1.72$1.86
0050Material remixing device (410H000)EACH1$32,800$22,500
0060Superpave bituminous concrete wearing surface layer, 3/4" maximum aggregate size mix, esal range E (424A281)TON9,072$109.67$155.22
0070Superpave bituminous concrete wearing surface layer, widening, 3/4" maximum aggregate size mix, esal range C/D (424A370)TON4,720$137.01$172.39
0080Superpave bituminous concrete upper binder layer, patching, 1" maximum aggregate size mix, esal range E (424B285)TON200$208.77$202.48
0090Superpave bitmuinous concrete upper binder layer, leveling, 3/8" maximum aggregate size mix, esal range E (424B702)TON200$144.30$211.58
0095Scoring bituminous pavement surface (428A001)MI1$309.00$330.93
0100Aggregate surfacing (1" down, crusher run) (430B043)TON1,563$38.13$235.10
0110High density mineral bond (432A000)SY15,175$5.05$4.96
0120Mobilization (600A000)LS1$182,421$189,052
0130Steel beam guardrail, class A, type 2 (630A001)LF2,188$22.66$22.89
0140Guardrail end anchor, type 8 (MASH) (630C077)EACH5$1,699.50$1,527.78
0150Guardrail end anchor, type 20 series (MASH) (630C080)EACH5$3,399.00$3,033.50
0160Mowing (652C000)ACRE34$169.95$121.34
0170Wattle (665Q002)LF458$8.29$13.24
0180Construction fuel (maximum bid limited to $ 151,850.00) (698A000)LS1$0.00$0.00
0190Solid white, class 2, type A traffic stripe (5" wide) (701A227)MI12$3,939.75$4,219.32
0200Solid yellow, class 2, type A traffic stripe (5" wide) (701A230)MI10$3,939.75$4,219.32
0210Broken white, class 2, type A traffic stripe (5" wide) (701A239)MI7$2,379.30$2,548.14
0220Broken yellow, class 2, type A traffic stripe (5" wide) (701A244)MI1$2,379.30$2,548.14
0230Dotted, class 2, type A traffic stripe (5" wide) (701B207)LF13,215$1.55$1.65
0240Broken temporary traffic stripe (701C000)MI24$772.50$827.32
0250Solid temporary traffic stripe (701C001)MI64$787.95$843.86
0260Solid traffic stripe removed (paint) (701D007)MI2$206.00$220.62
0270Solid traffic stripe removed (plastic) (701D008)MI2$206.00$220.62
0280Broken traffic stripe removed (paint) (701D014)MI2$206.00$220.62
0290Broken traffic stripe removed (plastic) (701D015)MI2$206.00$220.62
0300Solid white, class 2, type A traffic stripe (5" wide) (rumble strip) (701G252)LF600$8.24$8.82
0310Traffic control markings, class 2, type A (703A002)SF8,944$4.12$4.41
0320Traffic control legends, class 2, type A (703B002)SF3,141$5.15$5.52
0330Temporary traffic control markings (703D001)SF11,739$1.03$1.10
0340Temporary traffic control legends (703E001)SF766$3.09$3.31
0350Pavement markers, class A-H, type 2-C (705A030)EACH1,874$5.41$5.79
0360Pavement markers, class A-H, type 1-B (705A032)EACH16$5.41$5.79
0370Pavement markers, class A-H, type 2-D (705A037)EACH137$5.41$5.79
0380Construction signs (740B000)SF1,755$6.70$7.17
0390Special construction signs (740C000)SF41$8.24$8.82
0400Channelizing drums (740D000)EACH100$25.75$27.58
0410Cones (36 inches high) (740E000)EACH450$16.00$38.55
0420Portable sequential arrow and chevron sign unit (741C010)EACH5$1,622.25$1,737.37
0430Portable changeable message sign, type 2 (742A001)EACH4$2,729.50$2,923.19
ALDOT contract 20250328010: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from ALDOT's tabulation for this contract. ALDOT bid tabulation PDFs, one per letting, January 2022 to August 2026, with bidder names and totals from each letting's vendor ranking. Every bid matched its published total.

Every contract let that day: ALDOT letting of March 28, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy