ARDOT contract A00073 bid tabulation

THE PURPOSE OF THIS PROJECT IS TO MILL, INLAY, AND OVERLAY APPROXIMATELY 7.677 MILES OF HIGHWAYS 49, 358, 412, AND 412B IN PARAGOULD IN GREENE COUNTY. THIS PROJECT CONSISTS OF REMOVAL AND DISPOSAL ITEMS, AGGREGATE BASE COURSE, ACHM SURFACE COURSE, COLD MILLING ASPHALT PAVEMENT, ACHM PATCHING OF EXISTING ROADWAY, APPROACH GUTTERS, MAINTENANCE OF TRAFFIC, GUARDRAIL, CONCRETE WALKS, CURB AND GUTTER, WHEELCHAIR RAMPS, MUMBLE STRIPS, LOOP WIRING, PAVEMENT MARKING, AND MISC. ITEMS. Let by Arkansas DOT on January 15, 2025, Greene. 3 bids received; low bid $3,093,681 by Atlas Asphalt, Inc..

Owner
Arkansas DOT
Letting
15 JAN 2025
Pay items
37
Data through
04 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Atlas Asphalt, Inc.$3,093,681Low
2Delta Asphalt of Arkansas, Inc.$3,579,563+16%
3Rogers Group, Inc.$4,427,716+43%
ARDOT contract A00073: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Atlas Asphalt, Inc.2. Delta Asphalt of Arkansas, Inc.3. Rogers Group, Inc.
0001Removal and disposal of curb and gutter (202003)LF1,183$58.88$11.23$13.00
0002Removal and disposal of concrete walks (202104)SY710$92.54$45.52$53.00
0003Removal and disposal of guardrail (202132)LF225$16.00$27.00$31.00
0004Aggregate base course (class 7) (303117)TON1,104$51.52$40.29$70.00
0005Tack coat (401011)GAL30,291$0.01$0.01$0.01
0006Mineral aggregate in achm surface course (1/2") (407162)TON20,871$84.10$69.00$94.50
0007Asphalt binder (PG 70-22) in achm surface course (1/2") (minimum bid $120.00) (407442)TON1,191$120.00$700.00$650.00
0008Cold milling asphalt pavement (412002)SY81,450$1.75$1.67$2.90
0009Asphalt concrete patching for maintenance of traffic (414011)TON192$150.00$168.22$210.00
0010Achm patching of existing roadway (415011)TON80$175.00$244.63$250.00
0011Approach gutters (504264)CY32.52$2,500.00$2,709.04$3,200.00
0012Maintenance of traffic (603010)LS1$131,696$135,000$208,000
0013Signs (604003)SF976$5.00$5.00$11.00
0014Construction pavement markings (604041)LF209,042$0.14$0.14$0.15
0015Guardrail (type A) (617005)LF300$35.00$32.00$37.00
0016Guardrail terminal (type 2) (617312)EACH3$3,400.00$3,200.00$3,400.00
0017Thrie beam guardrail terminal (617332)EACH3$2,500.00$2,200.00$2,300.00
0018Concrete walks (633011)SY293$198.31$149.88$175.00
0019Concrete combination curb and gutter (type A) (1' 6") (634201)LF1,183$70.08$61.47$72.00
0020Wheelchair ramps (type 1) (641018)SY53$210.56$435.62$500.00
0021Wheelchair ramps (type 4) (641021)SY40$200.09$428.29$500.00
0022Wheelchair ramps (type 6) (641023)SY323$169.36$492.55$550.00
0023Surface-applied detectable warning panels (641500)SF174$77.12$41.67$45.00
0024Mumble strips in asphalt shoulders (642301)LF27,921$0.26$0.26$0.30
0025Centerline mumble stripes in asphalt roadways (642402)LF18,100$0.26$0.26$0.30
0026Loop wiring class III (1C/16 A.W.G.) (704036)LF4,400$12.00$10.50$12.00
0027Thermoplastic pavement marking white (6") (719002)LF64,483$0.64$0.64$0.75
0028Thermoplastic pavement marking white (8") (719003)LF1,294$3.00$3.00$3.50
0029Thermoplastic pavement marking white (12") (719005)LF4,482$6.00$6.00$7.00
0030Thermoplastic pavement marking yellow (6") (719102)LF88,718$0.64$0.64$0.75
0031Thermoplastic pavement marking (words) (719201)EACH20$270.00$270.00$300.00
0032Thermoplastic pavement marking (arrows) (719202)EACH34$225.00$225.00$250.00
0033Thermoplastic rumble bar (719231)LF120$15.00$15.00$16.00
0034Raised pavement markers (type II) (721002)EACH1,039$4.00$4.00$4.50
0035Bridge end terminal (734011)EACH1$35,000$34,000$36,000
0036Reinforcing steel-roadway (grade 60) (804003)LB3,392$3.00$3.00$3.50
0037Mobilization (unit bid amount may not exceed 5% of subtotal) (601001)LS1$52,626$165,000$210,000
ARDOT contract A00073: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from ARDOT's tabulation for this contract. ARDOT monthly bid tab PDFs (morning and afternoon sessions), January 2022 to November 2026. Base bids are printed in whole dollars; on A+B and A+C jobs the base bid is kept, and the published rank follows the award amount.

Every contract let that day: ARDOT letting of January 15, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy