ARDOT contract A30036 bid tabulation
THE PURPOSE OF THIS PROJECT IS TO MILL AND OVERLAY APPROXIMATELY 3.973 MILES OF HIGHWAY 19 IN NEVADA AND PIKE COUNTIES. THIS PROJECT CONSISTS OF REMOVAL AND DISPOSAL OF GUARDRAIL, EARTHWORK, AGGREGATE BASE COURSE, ACHM SURFACE COURSE, COLD MILLING ASPHALT PAVEMENT, ACHM PATCHING OF EXISTING ROADWAY, APPROACH GUTTERS, MAINTENANCE OF TRAFFIC, GUARDRAIL, EROSION CONTROL, RUMBLE STRIPS AND STRIPES, PAVEMENT MARKING, AND MISC. ITEMS. Let by Arkansas DOT on November 5, 2025, Nevada, Pike. 3 bids received; low bid $2,314,212 by Redstone Construction Group, Inc..
- Owner
- Arkansas DOT
- Letting
- 05 NOV 2025
- Pay items
- 34
- Data through
- 04 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Redstone Construction Group, Inc. | $2,314,212 | Low |
| 2 | Cranford Construction Co. | $2,413,192 | +4.0% |
| 3 | R. K. Hall, LLC | $3,847,896 | +66% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Redstone Construction Group, Inc. | 2. Cranford Construction Co. | 3. R. K. Hall, LLC |
|---|---|---|---|---|---|---|
| 0001 | Removal and disposal of guardrail (202132) | LF | 1,704 | $12.50 | $12.50 | $13.75 |
| 0002 | Compacted embankment (210611) | CY | 200 | $82.29 | $119.20 | $53.11 |
| 0003 | Aggregate base course (class 7) (303117) | TON | 723 | $60.71 | $67.06 | $104.33 |
| 0004 | Tack coat (401011) | GAL | 30,882 | $0.01 | $0.01 | $5.78 |
| 0005 | Mineral aggregate in achm surface course (1/2") (407162) | TON | 14,191 | $112.25 | $52.88 | $167.97 |
| 0006 | Asphalt binder (PG 64-22) in achm surface course (1/2") (minimum bid $120.00) (407432) | TON | 874 | $120.00 | $1,200.00 | $200.00 |
| 0007 | Cold milling asphalt pavement (412002) | SY | 89,889 | $1.69 | $1.28 | $4.21 |
| 0008 | Asphalt concrete patching for maintenance of traffic (414011) | TON | 100 | $150.00 | $135.55 | $250.00 |
| 0009 | Achm patching of existing roadway (415011) | TON | 300 | $150.00 | $148.96 | $250.00 |
| 0010 | Approach gutters (504264) | CY | 7.24 | $7,794.63 | $4,483.74 | $4,932.11 |
| 0011 | Mobilization (unit bid amount may not exceed 5% of subtotal) (601001) | LS | 1 | $41,041 | $28,641 | $153,916 |
| 0012 | Maintenance of traffic (603009) | LS | 1 | $35,002 | $78,643 | $90,391 |
| 0013 | Signs (604003) | SF | 599 | $6.00 | $7.00 | $8.80 |
| 0014 | Traffic drums (604023) | EACH | 26 | $30.00 | $35.00 | $33.00 |
| 0015 | Construction pavement markings (604041) | LF | 85,114 | $0.14 | $0.14 | $0.17 |
| 0016 | Guardrail (type A) (617005) | LF | 1,350 | $36.50 | $36.50 | $40.15 |
| 0017 | Guardrail terminal (type 2) (617312) | EACH | 12 | $3,391.14 | $3,391.14 | $3,730.25 |
| 0018 | Thrie beam guardrail terminal (617332) | EACH | 8 | $2,478.16 | $2,478.16 | $2,725.98 |
| 0019 | Lime (620001) | TON | 1 | $125.00 | $125.00 | $137.50 |
| 0020 | Seeding (620011) | ACRE | 0.29 | $3,985.00 | $3,985.00 | $4,383.52 |
| 0021 | Mulch cover (620022) | ACRE | 0.58 | $3,364.53 | $3,364.53 | $3,700.98 |
| 0022 | Water (620030) | MGAL | 35.50 | $10.00 | $10.00 | $11.00 |
| 0023 | Temporary seeding (621001) | ACRE | 0.29 | $2,829.43 | $2,829.41 | $3,111.24 |
| 0024 | Silt fence (621021) | LF | 2,400 | $3.68 | $3.68 | $4.05 |
| 0025 | Sediment removal and disposal (621111) | CY | 49 | $19.77 | $13.73 | $66.34 |
| 0026 | Filter sock (18") (621169) | LF | 250 | $13.85 | $13.85 | $15.24 |
| 0027 | Wattle (20") (621173) | LF | 250 | $13.85 | $13.85 | $15.24 |
| 0028 | Rumble strips in asphalt shoulders (642001) | LF | 31,531 | $0.17 | $0.29 | $0.19 |
| 0029 | Centerline rumble stripes in asphalt roadways (642102) | LF | 20,541 | $0.17 | $0.29 | $0.19 |
| 0030 | Portable traffic signal system - actuated (701603) | WEEK | 12 | $950.00 | $2,247.05 | $3,516.76 |
| 0031 | Reflectorized paint pavement marking white (6") (718002) | LF | 42,557 | $0.17 | $0.17 | $0.24 |
| 0032 | Reflectorized paint pavement marking yellow (6") (718102) | LF | 42,557 | $0.17 | $0.17 | $0.24 |
| 0033 | Raised pavement markers (type II) (721002) | EACH | 266 | $5.00 | $5.00 | $7.70 |
| 0034 | Reinforcing steel-roadway (grade 60) (804003) | LB | 492 | $13.77 | $3.00 | $3.30 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ARDOT's tabulation for this contract. ARDOT monthly bid tab PDFs (morning and afternoon sessions), January 2022 to November 2026. Base bids are printed in whole dollars; on A+B and A+C jobs the base bid is kept, and the published rank follows the award amount.
Every contract let that day: ARDOT letting of November 5, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.