R. K. Hall, LLC: ARDOT bid record
R. K. Hall, LLC submitted 26 bids on Arkansas DOT contracts in the data, from 12 JAN 2022 to 04 NOV 2026, and was the low bidder on 11 of them (42%). When it was not low, its total sat a median +45% above the low bid.
- Owner
- Arkansas DOT
- Low bid volume
- $72,402,336
- Latest bid
- 04 NOV 2026
- Data through
- 04 NOV 2026
By year
| Year | Bids | Low bids | Win rate |
|---|---|---|---|
| 2022 | 6 | 5 | 83% |
| 2023 | 8 | 5 | 63% |
| 2025 | 7 | 0 | 0% |
| 2026 | 5 | 1 | 20% |
By county
| County | Bids | Low bids | Win rate |
|---|---|---|---|
| Miller | 7 | 5 | 71% |
| Sevier | 4 | 2 | 50% |
| Little River | 4 | 2 | 50% |
| Howard, Sevier | 2 | 1 | 50% |
| Polk, Scott | 1 | 0 | 0% |
| Little River, Sevier | 1 | 1 | 100% |
| Hempstead, Miller | 1 | 0 | 0% |
| Polk | 1 | 0 | 0% |
| Lafayette | 1 | 0 | 0% |
| Nevada, Pike | 1 | 0 | 0% |
| Hempstead, Nevada | 1 | 0 | 0% |
| Howard | 1 | 0 | 0% |
Pay items where it is most often lowest
| Pay item | Code | Unit | Lines bid | Lowest on the line | Its median price | All bidders' median |
|---|---|---|---|---|---|---|
| Achm patching of existing roadway | 415011 | TON | 15 | 8 (53%) | $250.00 | $250.00 |
| Asphalt binder (PG 64-22) in achm surface course (3/8") (minimum bid $120.00) | 407431 | TON | 5 | 4 (80%) | $120.00 | $120.00 |
| Cold milling asphalt pavement | 412002 | SY | 10 | 3 (30%) | $4.19 | $8.00 |
| Asphalt binder (PG 70-22) in achm surface course (1/2") (minimum bid $120.00) | 407442 | TON | 9 | 3 (33%) | $200.00 | $120.00 |
| Asphalt concrete patching for maintenance of traffic | 414011 | TON | 7 | 3 (43%) | $200.04 | $262.50 |
| Asphalt binder (PG 64-22) in achm surface course (1/2") (minimum bid $120.00) | 407432 | TON | 6 | 3 (50%) | $160.00 | $120.00 |
| Mineral aggregate in achm surface course (1/2") | 407162 | TON | 11 | 2 (18%) | $152.93 | $124.55 |
| Thermoplastic pavement marking white (6") | 719002 | LF | 8 | 2 (25%) | $0.73 | $0.90 |
| Water | 620030 | MGAL | 5 | 2 (40%) | $11.00 | $10.00 |
| Signs | 604003 | SF | 16 | 1 (6%) | $10.63 | $8.40 |
| Raised pavement markers (type II) | 721002 | EACH | 10 | 1 (10%) | $6.54 | $6.50 |
| Aggregate base course (class 7) | 303117 | TON | 10 | 1 (10%) | $96.94 | $52.19 |
A line counts when the firm priced it and at least one other bidder did too; the lowest unit price on the line counts whoever won the contract. Token prices and bids over three times the low bid are left out.
Who it meets most
| Firm | Contracts in common | That firm ranked ahead |
|---|---|---|
| Redstone Construction Group, Inc. | 9 | 7 of 9 |
| Cranford Construction Co. | 8 | 7 of 8 |
| Blackstone Construction, LLC | 7 | 7 of 7 |
| Tri State Asphalt, Inc. | 5 | 5 of 5 |
| Jet Asphalt & Rock Co., Inc. | 2 | 2 of 2 |
| Redstone Const. Group, Inc. | 1 | 1 of 1 |
| Smackover Paving Co. | 1 | 1 of 1 |
Latest bids
| Let | Contract | County | Project | Rank | Its bid | Against the low bid |
|---|---|---|---|---|---|---|
| 04 NOV 2026 | A30049 | Hempstead, Howard | THE PURPOSE OF THIS PROJECT IS TO MILL AND OVERLAY APPROXIMATELY 18.474 MILES OF HIGHWAY 73 IN HEMPSTEAD AND HOWARD COUNTIES. THIS PROJECT C | 3 of 3 | $8,354,090 | +17% |
| 20 MAY 2026 | SA4141 | Little River | THE PURPOSE OF THIS PROJECT IS TO SURFACE APPROXIMATELY 1.00 MILE OF CO. RD. 51 IN LITTLE RIVER COUNTY. THIS PROJECT CONSISTS OF AGGREGATE B | 4 of 4 | $518,762 | +60% |
| 08 APR 2026 | A30028 | Howard | THE PURPOSE OF THIS PROJECT IS TO LEVEL AND OVERLAY APPROXIMATELY 9.327 MILES OF HIGHWAY 278 IN HOWARD COUNTY. THIS PROJECT CONSISTS OF REMO | 3 of 4 | $6,040,722 | +11% |
| 08 APR 2026 | A30031 | Miller | THE PURPOSE OF THIS PROJECT IS TO MILL AND OVERLAY APPROXIMATELY 1.327 MILES OF HIGHWAY 71 IN MILLER COUNTY. THIS PROJECT CONSISTS OF ACHM S | 1 of 2 | $1,094,742 | Low, 7.0% under the second |
| 04 MAR 2026 | A30029 | Little River | THE PURPOSE OF THIS PROJECT IS TO LEVEL AND OVERLAY APPROXIMATELY 6.946 MILES OF HIGHWAY 32 IN LITTLE RIVER COUNTY. THIS PROJECT CONSISTS OF | 4 of 4 | $4,186,517 | +10% |
| 05 NOV 2025 | A30036 | Nevada, Pike | THE PURPOSE OF THIS PROJECT IS TO MILL AND OVERLAY APPROXIMATELY 3.973 MILES OF HIGHWAY 19 IN NEVADA AND PIKE COUNTIES. THIS PROJECT CONSIST | 3 of 3 | $3,847,896 | +66% |
| 05 NOV 2025 | A30038 | Hempstead, Nevada | THE PURPOSE OF THIS PROJECT IS TO MILL AND OVERLAY APPROXIMATELY 18.369 MILES OF HIGHWAY 278 IN HEMPSTEAD AND NEVADA COUNTIES. THIS PROJECT | 4 of 4 | $11,950,368 | +35% |
| 26 FEB 2025 | A30041 | Lafayette | THE PURPOSE OF THIS PROJECT IS TO LEVEL AND OVERLAY APPROXIMATELY 13.318 MILES OF HIGHWAYS 29 AND 160 IN LAFAYETTE COUNTY. THIS PROJECT CONS | 3 of 4 | $7,812,849 | +7.0% |
| 15 JAN 2025 | C46004 | Miller | THE PURPOSE OF THIS PROJECT IS TO OVERLAY APPROXIMATELY 0.50 MILE OF EUCLID STREET IN THE CITY OF TEXARKANA IN MILLER COUNTY. THIS PROJECT C | 3 of 3 | $453,617 | +45% |
| 15 JAN 2025 | C46005 | Miller | THE PURPOSE OF THIS PROJECT IS TO OVERLAY APPROXIMATELY 1.10 MILES OF WILSON STREET AND MLK JR. BLVD. IN THE CITY OF GARLAND IN MILLER COUNT | 3 of 3 | $462,884 | +65% |
| 15 JAN 2025 | C57007 | Polk | THE PURPOSE OF THIS PROJECT IS TO OVERLAY APPROXIMATELY 0.46 MILES OF 4TH STREET AND 0.07 MILES OF ADAIR STREET IN THE CITY OF VANDERVOORT I | 3 of 3 | $469,983 | +92% |
| 15 JAN 2025 | C76089 | Howard, Sevier | THE PURPOSE OF THIS PROJECT IS TO OVERLAY APPROXIMATELY 1.35 MILES OF VARIOUS CITY STREETS IN THE CITY OF BEN LOMOND IN SEVIER COUNTY, APPRO | 4 of 4 | $1,639,275 | +82% |
| 01 NOV 2023 | A30021 | Little River, Sevier | THE PURPOSE OF THIS PROJECT IS TO RETAIN AND OVERLAY WITH ACHM SURFACE COURSE APPROXIMATELY 2.088 MILES IN LITTLE RIVER COUNTY AND APPROXIMA | 1 of 1 | $7,494,388 | Low |
| 01 NOV 2023 | A30022 | Sevier | THE PURPOSE OF THIS PROJECT IS TO RETAIN AND OVERLAY WITH ACHM SURFACE COURSE APPROXIMATELY 4.460 MILES OF HIGHWAY 71 IN SEVIER COUNTY. THIS | 2 of 2 | $3,950,442 | +29% |
| 01 NOV 2023 | A30030 | Hempstead, Miller | THE PURPOSE OF THIS PROJECT IS TO MILL AND OVERLAY APPROXIMATELY 2.01 MILES OF HIGHWAY 67 IN MILLER COUNTY AND 0.04 MILES OF HIGHWAY 67 IN H | 2 of 2 | $1,909,366 | +30% |
| 01 MAR 2023 | A30013 | Miller | THE PURPOSE OF THIS PROJECT IS TO MILL RUTTED AREAS, LEVEL, AND OVERLAY WITH ACHM SURFACE COURSE ON APPROXIMATELY 6.927 MILES OF HIGHWAY 108 | 1 of 1 | $10,298,696 | Low |
| 01 MAR 2023 | A30014 | Miller | THE PURPOSE OF THIS PROJECT IS TO OVERLAY APPROXIMATELY 7.282 MILES OF ROADWAY, AND ADD 2' SHOULDERS WITH RUMBLE STRIPES TO APPROXIMATELY 4. | 1 of 1 | $5,021,969 | Low |
| 01 MAR 2023 | A30020 | Little River | THE PURPOSE OF THIS PROJECT IS TO RUT MILL AND OVERLAY WITH ACHM SURFACE COURSE ON APPROXIMATELY 4.111 MILES OF HIGHWAY 71 IN LITTLE RIVER C | 1 of 1 | $3,005,356 | Low |
| 01 MAR 2023 | A30023 | Sevier | THE PURPOSE OF THIS PROJECT IS TO COLD MILL AND OVERLAY WITH ACHM SURFACE COURSE ON APPROXIMATELY 1.646 MILES: RUT MILL AND OVERLAY WITH ACH | 1 of 1 | $6,310,835 | Low |
| 01 MAR 2023 | A40024 | Polk, Scott | THE PURPOSE OF THIS PROJECT IS TO LEVEL AND OVERLAY WITH ACHM SURFACE COURSE ON APPROXIMATELY 18.225 MILES; APPLY AN ASPHALT SURFACE TREATME | 2 of 2 | $31,989,528 | +45% |
| 29 JUN 2022 | C66004 | Sevier | THE PURPOSE OF THIS PROJECT IS TO OVERLAY APPROXIMATELY 1.17 MILES OF VARIOUS CITY STREETS IN THE CITY OF HORATIO AND APPROXIMATELY 1.14 MIL | 2 of 2 | $1,028,531 | +47% |
| 06 APR 2022 | A30012 | Little River | THE PURPOSE OF THIS PROJECT IS TO MILL AND OVERLAY APPROXIMATELY 22.912 MILES OF HIGHWAYS 32 AND 41 IN LITTLE RIVER COUNTY. THIS PROJECT CON | 1 of 1 | $15,513,109 | Low |
| 06 APR 2022 | SA4652 | Miller | THE PURPOSE OF THIS PROJECT IS TO OVERLAY APPROXIMATELY 2.10 MILES OF COUNTY ROAD 64 IN MILLER COUNTY. THIS PROJECT CONSISTS OF AGGREGATE BA | 1 of 1 | $928,034 | Low |
| 16 FEB 2022 | A30011 | Howard, Sevier | THE PURPOSE OF THIS PROJECT IS TO MILL AND OVERLAY APPROXIMATELY 14.388 MILES OF HIGHWAY 70, IN SEVIER AND HOWARD COUNTIES. THIS PROJECT CON | 1 of 1 | $10,444,074 | Low |
| 16 FEB 2022 | A30015 | Miller | THE PURPOSE OF THIS PROJECT IS TO LEVEL AND OVERLAY APPROXIMATELY 11.265 MILES OF HIGHWAY 71 AT TEXARKANA, IN MILLER COUNTY. THIS PROJECT CO | 1 of 1 | $7,354,692 | Low |
How this record was read
ARDOT monthly bid tab PDFs (morning and afternoon sessions), January 2022 to November 2026. Base bids are printed in whole dollars; on A+B and A+C jobs the base bid is kept, and the published rank follows the award amount.
- Every bid counted here matched its published total to within one dollar; ARDOT's rank decides who was low.
- The gap to the low bid is the firm's total over the low total, minus one, on contracts it did not win, leaving out bids over three times the low bid.
- A record covers the lettings in the data, not every contract the firm ever bid. Coverage by year is on the state page.
A name split in two, or a figure that does not match the owner's tabulation? Write to mehdi@miragemetrics.com and we correct it.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.