ARDOT contract SA4141 bid tabulation

THE PURPOSE OF THIS PROJECT IS TO SURFACE APPROXIMATELY 1.00 MILE OF CO. RD. 51 IN LITTLE RIVER COUNTY. THIS PROJECT CONSISTS OF AGGREGATE BASE COURSE, ACHM SURFACE COURSE, PAVEMENT MARKING, MAINTENANCE OF TRAFFIC AND MISC. ITEMS. Let by Arkansas DOT on May 20, 2026, Little River. 4 bids received; low bid $324,580 by Redstone Construction Group, Inc..

Owner
Arkansas DOT
Letting
20 MAY 2026
Pay items
9
Data through
04 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Redstone Construction Group, Inc.$324,580Low
2Cranford Construction Co.$342,932+6.0%
3Blackstone Construction, LLC$420,044+29%
4R. K. Hall, LLC$518,762+60%
ARDOT contract SA4141: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Redstone Construction Group, Inc.2. Cranford Construction Co.3. Blackstone Construction, LLC4. R. K. Hall, LLC
0001Aggregate base course (class 7) (303117)TON292$79.62$63.42$85.46$90.00
0003Mineral aggregate in achm surface course (1/2") (407162)TON1,832$144.25$157.29$194.76$233.83
0004Asphalt binder (PG 70-22) in achm surface course (1/2") (minimum bid $120.00) (407442)TON117$120.00$120.00$120.00$120.00
0005Maintenance of traffic (603009)LS1$4,071.79$8,714.27$3,500.00$15,000
0006Signs (604003)SF132$8.00$12.00$12.00$55.00
0007Reflectorized paint pavement marking yellow (4") (718101)LF10,560$0.16$0.38$0.35$0.66
0008Standard sign (726002)SF12$50.00$30.00$25.30$33.00
0009Channel post sign support (type C) (729003)EACH4$200.00$200.00$93.50$110.00
0010Mobilization (unit bid amount may not exceed 5% of subtotal) (601001)LS1$14,808$6,747.43$14,792$20,000
ARDOT contract SA4141: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from ARDOT's tabulation for this contract. ARDOT monthly bid tab PDFs (morning and afternoon sessions), January 2022 to November 2026. Base bids are printed in whole dollars; on A+B and A+C jobs the base bid is kept, and the published rank follows the award amount.

Every contract let that day: ARDOT letting of May 20, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy