ARDOT contract A40051 bid tabulation
THE PURPOSE OF THIS PROJECT IS TO OVERLAY APPROXIMATELY 18.061 MILES OF HIGHWAYS 88 AND 272 IN POLK COUNTY. THIS PROJECT CONSISTS OF REMOVAL AND DISPOSAL OF GUARDRAIL, SHAPING ROADWAY SECTION, TRENCHING AND SHOULDER PREPARATION, AGGREGATE BASE COURSE, ACHM BINDER AND SURFACE COURSES, COLD MILLING ASPHALT PAVEMENT, ACHM PATCHING OF EXISTING ROADWAY, MAINTENANCE OF TRAFFIC, GUARDRAIL, EROSION CONTROL, MUMBLE STRIPES, PAVEMENT MARKING, AND MISC. ITEMS. Let by Arkansas DOT on March 4, 2026, Polk. 1 bid received; low bid $8,887,904 by Blackstone Construction, LLC.
- Owner
- Arkansas DOT
- Letting
- 04 MAR 2026
- Pay items
- 30
- Data through
- 04 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Blackstone Construction, LLC | $8,887,904 | Low |
Bid tabulation
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ARDOT's tabulation for this contract. ARDOT monthly bid tab PDFs (morning and afternoon sessions), January 2022 to November 2026. Base bids are printed in whole dollars; on A+B and A+C jobs the base bid is kept, and the published rank follows the award amount.
Every contract let that day: ARDOT letting of March 4, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.