ARDOT contract A50037 bid tabulation

THE PURPOSE OF THIS PROJECT IS TO MILL, OVERLAY, AND PLACE ULTRATHIN BONDED WEARING COURSE ON APPROXIMATELY 16.147 MILES OF VARIOUS HIGHWAYS IN WHITE COUNTY. THIS PROJECT CONSISTS OF REMOVAL AND DISPOSAL ITEMS, AGGREGATE BASE COURSE, ASPHALT EMULSION, ACHM SURFACE COURSE, ULTRATHIN BONDED WEARING COURSE, HOT IN-PLACE RECYCLED ASPHALT CONCRETE, COLD MILLING ASPHALT PAVEMENT, ACHM PATCHING OF EXISTING ROADWAY, APPROACH GUTTERS, MAINTENANCE OF TRAFFIC, GUARDRAIL, RUMBLE STRIPS, PAVEMENT MARKING, AND MISC. ITEMS. Let by Arkansas DOT on April 9, 2025, White. 4 bids received; low bid $7,058,467 by Atlas Asphalt, Inc..

Owner
Arkansas DOT
Letting
09 APR 2025
Pay items
32
Data through
04 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Atlas Asphalt, Inc.$7,058,467Low
2CK Asphalt, LLC$7,649,417+8.0%
3Delta Asphalt of Arkansas, Inc.$7,674,456+9.0%
4Rogers Group, Inc.$8,727,599+24%
ARDOT contract A50037: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Atlas Asphalt, Inc.2. CK Asphalt, LLC3. Delta Asphalt of Arkansas, Inc.4. Rogers Group, Inc.
0001Removal and disposal of approach gutters (202052)EACH8$3,610.53$1,500.00$3,610.53$3,650.00
0002Removal and disposal of guardrail (202132)LF600$11.50$8.00$11.50$9.00
0003Aggregate base course (class 7) (303117)TON3,445$30.64$26.00$33.52$50.00
0004Tack coat (401011)GAL74,248$0.01$0.01$0.01$1.00
0005Asphalt emulsion (402600)GAL69,004$3.95$5.95$3.95$4.25
0006Mineral aggregate in achm surface course (1/2") (407162)TON40,195$83.79$89.25$88.66$76.00
0007Asphalt binder (PG 64-22) in achm surface course (1/2") (minimum bid $120.00) (407432)TON2,520$120.00$120.00$120.00$650.00
0008Ultrathin bonded wearing course (3/4"-type C) (407904)TON4,273$114.88$145.25$133.20$135.00
0009Hot in-place recycled asphalt concrete (407953)SY175,657$6.27$7.17$6.39$6.76
0010Cold milling asphalt pavement (412002)SY69,148$1.34$1.75$1.64$2.00
0011Achm patching of existing roadway (415011)TON1,500$125.00$169.00$179.17$175.00
0012Approach gutters (504264)CY104.16$2,296.89$1,820.00$2,296.89$2,300.00
0013Mobilization (unit bid amount may not exceed 5% of subtotal) (601001)LS1$104,019$297,500$325,000$400,000
0014Maintenance of traffic (603010)LS1$328,021$44,600$300,000$200,000
0015Signs (604003)SF2,938$4.00$4.00$7.00$4.00
0016Traffic drums (604023)EACH98$25.00$25.00$25.00$26.00
0017Construction pavement markings (604041)LF276,514$0.14$0.20$0.14$0.15
0018Temporary portable rumble strips (604091)EACH6$2,538.31$2,600.00$3,100.00$2,700.00
0019Guardrail (type A) (617005)LF725$32.50$30.00$32.50$32.00
0020Guardrail terminal (type 2) (617312)EACH8$3,150.00$2,800.00$3,150.00$2,900.00
0021Thrie beam guardrail terminal (617332)EACH8$2,150.00$2,000.00$2,150.00$2,100.00
0022Rumble strips in asphalt shoulders (642001)LF46,412$0.06$0.30$0.19$0.22
0023Portable traffic signal system - actuated (701603)WEEK6$1,319.92$1,000.00$950.00$1,050.00
0024Thermoplastic pavement marking white (6") (719002)LF188,206$0.63$0.65$0.63$0.68
0025Thermoplastic pavement marking white (8") (719003)LF243$3.00$3.00$3.00$3.00
0026Thermoplastic pavement marking white (12") (719005)LF627$6.00$5.10$6.00$6.00
0027Thermoplastic pavement marking yellow (6") (719102)LF188,206$0.63$0.65$0.63$0.68
0028Thermoplastic pavement marking (words) (719201)EACH5$225.00$285.00$225.00$235.00
0029Thermoplastic pavement marking (arrows) (719202)EACH7$175.00$270.00$175.00$185.00
0030Thermoplastic pavement marking (yield line) (719210)LF30$20.00$18.00$20.00$25.00
0031Raised pavement markers (type II) (721002)EACH2,390$4.50$3.50$4.50$4.50
0032Reinforcing steel-roadway (grade 60) (804003)LB9,880$3.00$3.00$3.00$3.00
ARDOT contract A50037: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from ARDOT's tabulation for this contract. ARDOT monthly bid tab PDFs (morning and afternoon sessions), January 2022 to November 2026. Base bids are printed in whole dollars; on A+B and A+C jobs the base bid is kept, and the published rank follows the award amount.

Every contract let that day: ARDOT letting of April 9, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy