ARDOT contract A50047 bid tabulation
THE PURPOSE OF THIS PROJECT IS TO MILL AND OVERLAY APPROXIMATELY 5.967 MILES OF HIGHWAYS 110 AND 210 IN CLEBURNE COUNTY. THIS PROJECT CONSISTS OF REMOVAL AND DISPOSAL ITEMS, AGGREGATE BASE COURSE, ACHM BASE, BINDER, AND SURFACE COURSES, COLD MILLING ASPHALT PAVEMENT, ACHM PATCHING OF EXISTING ROADWAY, MAINTENANCE OF TRAFFIC, MINOR DRAINAGE STRUCTURES, GUARDRAIL, EROSION CONTROL ITEMS, PAVEMENT MARKING, AND MISC. ITEMS. Let by Arkansas DOT on November 5, 2025, Cleburne. 3 bids received; low bid $1,700,424 by CK Asphalt, LLC.
- Owner
- Arkansas DOT
- Letting
- 05 NOV 2025
- Pay items
- 35
- Data through
- 04 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | CK Asphalt, LLC | $1,700,424 | Low |
| 2 | Rogers Group, Inc. | $2,080,969 | +22% |
| 3 | Delta Asphalt of Arkansas, Inc. | $2,204,105 | +30% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. CK Asphalt, LLC | 2. Rogers Group, Inc. | 3. Delta Asphalt of Arkansas, Inc. |
|---|---|---|---|---|---|---|
| 0001 | Removal and disposal of drop inlets (202093) | EACH | 1 | $8,400.00 | $1,315.00 | $2,843.91 |
| 0002 | Removal and disposal of pipe culverts (202096) | EACH | 2 | $1,250.00 | $1,315.00 | $1,421.96 |
| 0003 | Removal and disposal of guardrail (202132) | LF | 5,225 | $6.00 | $6.40 | $6.25 |
| 0004 | Aggregate base course (class 7) (303117) | TON | 170 | $27.50 | $50.00 | $91.74 |
| 0005 | Tack coat (401011) | GAL | 16,553 | $0.01 | $1.00 | $2.56 |
| 0006 | Mineral aggregate in achm base course (1 1/2") (405161) | TON | 537 | $69.75 | $55.00 | $91.35 |
| 0007 | Asphalt binder (PG 64-22) in achm base course (1 1/2") (minimum bid $120.00) (405402) | TON | 25 | $120.00 | $750.00 | $650.00 |
| 0008 | Mineral aggregate in achm binder course (1") (406161) | TON | 2,496 | $65.74 | $56.00 | $102.12 |
| 0009 | Asphalt binder (PG 64-22) in achm binder course (1") (minimum bid $120.00) (406402) | TON | 131 | $120.00 | $750.00 | $120.00 |
| 0010 | Mineral aggregate in achm surface course (1/2") (407162) | TON | 9,852 | $20.40 | $57.00 | $96.04 |
| 0011 | Asphalt binder (PG 64-22) in achm surface course (1/2") (minimum bid $120.00) (407432) | TON | 618 | $1,000.00 | $750.00 | $120.00 |
| 0012 | Cold milling asphalt pavement (412002) | SY | 61,622 | $2.32 | $2.10 | $2.67 |
| 0013 | Achm patching of existing roadway (415011) | TON | 500 | $175.00 | $185.00 | $168.96 |
| 0014 | Mobilization (unit bid amount may not exceed 5% of subtotal) (601001) | LS | 1 | $49,800 | $75,000 | $85,000 |
| 0015 | Maintenance of traffic (603009) | LS | 1 | $7,900.00 | $84,000 | $66,000 |
| 0016 | Signs (604003) | SF | 1,386 | $6.00 | $7.00 | $18.00 |
| 0017 | Traffic drums (604023) | EACH | 70 | $23.00 | $35.00 | $60.00 |
| 0018 | Construction pavement markings (604041) | LF | 47,878 | $0.15 | $0.16 | $0.17 |
| 0019 | 18" reinforced concrete pipe culverts (class V) (605604) | LF | 74 | $229.00 | $390.00 | $140.90 |
| 0020 | 18" flared end sections for reinforced concrete pipe culverts (605856) | EACH | 3 | $4,420.00 | $2,360.00 | $1,970.56 |
| 0021 | Selected pipe bedding (606994) | CY | 10 | $0.99 | $26.00 | $189.12 |
| 0022 | Drop inlets (type ST) (609138) | EACH | 1 | $9,400.00 | $6,400.00 | $11,733 |
| 0023 | Pavement repair over culverts (asphalt) (615022) | TON | 18 | $185.00 | $425.00 | $597.46 |
| 0024 | Guardrail (type A) (617005) | LF | 5,025 | $30.00 | $30.00 | $30.00 |
| 0025 | Guardrail terminal (type 2) (617312) | EACH | 4 | $3,000.00 | $3,000.00 | $3,000.00 |
| 0026 | Water (620030) | MGAL | 0.30 | $10.00 | $10.00 | $10.00 |
| 0027 | Solid sodding (624001) | SY | 25 | $20.00 | $20.25 | $20.00 |
| 0028 | Roadway construction control (635001) | LS | 1 | $24,300 | $10,000 | $30,000 |
| 0029 | Portable traffic signal system - actuated (701603) | WEEK | 4 | $2,200.00 | $2,200.00 | $1,500.00 |
| 0030 | Thermoplastic pavement marking white (6") (719002) | LF | 63,080 | $0.59 | $0.63 | $0.64 |
| 0031 | Thermoplastic pavement marking white (12") (719005) | LF | 120 | $7.00 | $8.00 | $7.00 |
| 0032 | Thermoplastic pavement marking yellow (6") (719102) | LF | 47,878 | $0.59 | $0.63 | $0.63 |
| 0033 | Thermoplastic pavement marking yellow (8") (719103) | LF | 100 | $5.00 | $5.00 | $5.20 |
| 0034 | Thermoplastic pavement marking (arrows) (719202) | EACH | 2 | $350.00 | $375.00 | $225.00 |
| 0035 | Raised pavement markers (type II) (721002) | EACH | 403 | $5.00 | $5.00 | $4.75 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ARDOT's tabulation for this contract. ARDOT monthly bid tab PDFs (morning and afternoon sessions), January 2022 to November 2026. Base bids are printed in whole dollars; on A+B and A+C jobs the base bid is kept, and the published rank follows the award amount.
Every contract let that day: ARDOT letting of November 5, 2025. Compiled by Mirage Metrics.