ARDOT contract A50047 bid tabulation

THE PURPOSE OF THIS PROJECT IS TO MILL AND OVERLAY APPROXIMATELY 5.967 MILES OF HIGHWAYS 110 AND 210 IN CLEBURNE COUNTY. THIS PROJECT CONSISTS OF REMOVAL AND DISPOSAL ITEMS, AGGREGATE BASE COURSE, ACHM BASE, BINDER, AND SURFACE COURSES, COLD MILLING ASPHALT PAVEMENT, ACHM PATCHING OF EXISTING ROADWAY, MAINTENANCE OF TRAFFIC, MINOR DRAINAGE STRUCTURES, GUARDRAIL, EROSION CONTROL ITEMS, PAVEMENT MARKING, AND MISC. ITEMS. Let by Arkansas DOT on November 5, 2025, Cleburne. 3 bids received; low bid $1,700,424 by CK Asphalt, LLC.

Owner
Arkansas DOT
Letting
05 NOV 2025
Pay items
35
Data through
04 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bid
1CK Asphalt, LLC$1,700,424Low
2Rogers Group, Inc.$2,080,969+22%
3Delta Asphalt of Arkansas, Inc.$2,204,105+30%
ARDOT contract A50047: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. CK Asphalt, LLC2. Rogers Group, Inc.3. Delta Asphalt of Arkansas, Inc.
0001Removal and disposal of drop inlets (202093)EACH1$8,400.00$1,315.00$2,843.91
0002Removal and disposal of pipe culverts (202096)EACH2$1,250.00$1,315.00$1,421.96
0003Removal and disposal of guardrail (202132)LF5,225$6.00$6.40$6.25
0004Aggregate base course (class 7) (303117)TON170$27.50$50.00$91.74
0005Tack coat (401011)GAL16,553$0.01$1.00$2.56
0006Mineral aggregate in achm base course (1 1/2") (405161)TON537$69.75$55.00$91.35
0007Asphalt binder (PG 64-22) in achm base course (1 1/2") (minimum bid $120.00) (405402)TON25$120.00$750.00$650.00
0008Mineral aggregate in achm binder course (1") (406161)TON2,496$65.74$56.00$102.12
0009Asphalt binder (PG 64-22) in achm binder course (1") (minimum bid $120.00) (406402)TON131$120.00$750.00$120.00
0010Mineral aggregate in achm surface course (1/2") (407162)TON9,852$20.40$57.00$96.04
0011Asphalt binder (PG 64-22) in achm surface course (1/2") (minimum bid $120.00) (407432)TON618$1,000.00$750.00$120.00
0012Cold milling asphalt pavement (412002)SY61,622$2.32$2.10$2.67
0013Achm patching of existing roadway (415011)TON500$175.00$185.00$168.96
0014Mobilization (unit bid amount may not exceed 5% of subtotal) (601001)LS1$49,800$75,000$85,000
0015Maintenance of traffic (603009)LS1$7,900.00$84,000$66,000
0016Signs (604003)SF1,386$6.00$7.00$18.00
0017Traffic drums (604023)EACH70$23.00$35.00$60.00
0018Construction pavement markings (604041)LF47,878$0.15$0.16$0.17
001918" reinforced concrete pipe culverts (class V) (605604)LF74$229.00$390.00$140.90
002018" flared end sections for reinforced concrete pipe culverts (605856)EACH3$4,420.00$2,360.00$1,970.56
0021Selected pipe bedding (606994)CY10$0.99$26.00$189.12
0022Drop inlets (type ST) (609138)EACH1$9,400.00$6,400.00$11,733
0023Pavement repair over culverts (asphalt) (615022)TON18$185.00$425.00$597.46
0024Guardrail (type A) (617005)LF5,025$30.00$30.00$30.00
0025Guardrail terminal (type 2) (617312)EACH4$3,000.00$3,000.00$3,000.00
0026Water (620030)MGAL0.30$10.00$10.00$10.00
0027Solid sodding (624001)SY25$20.00$20.25$20.00
0028Roadway construction control (635001)LS1$24,300$10,000$30,000
0029Portable traffic signal system - actuated (701603)WEEK4$2,200.00$2,200.00$1,500.00
0030Thermoplastic pavement marking white (6") (719002)LF63,080$0.59$0.63$0.64
0031Thermoplastic pavement marking white (12") (719005)LF120$7.00$8.00$7.00
0032Thermoplastic pavement marking yellow (6") (719102)LF47,878$0.59$0.63$0.63
0033Thermoplastic pavement marking yellow (8") (719103)LF100$5.00$5.00$5.20
0034Thermoplastic pavement marking (arrows) (719202)EACH2$350.00$375.00$225.00
0035Raised pavement markers (type II) (721002)EACH403$5.00$5.00$4.75
ARDOT contract A50047: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from ARDOT's tabulation for this contract. ARDOT monthly bid tab PDFs (morning and afternoon sessions), January 2022 to November 2026. Base bids are printed in whole dollars; on A+B and A+C jobs the base bid is kept, and the published rank follows the award amount.

Every contract let that day: ARDOT letting of November 5, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy