ARDOT contract A90034 bid tabulation

THE PURPOSE OF THIS PROJECT IS TO MILL AND OVERLAY APPROXIMATELY 8.314 MILES OF HIGHWAY 62 IN CARROLL COUNTY. THIS PROJECT CONSISTS OF AGGREGATE BASE COURSE, ACHM SURFACE COURSE, COLD MILLING ASPHALT PAVEMENT, ACHM PATCHING OF EXISTING ROADWAY, MAINTENANCE OF TRAFFIC, RUMBLE STRIPS AND STRIPES, PAVEMENT MARKING, AND MISC. ITEMS. Let by Arkansas DOT on April 9, 2025, Carroll. 2 bids received; low bid $4,660,799 by Emery Sapp & Sons, Inc..

Owner
Arkansas DOT
Letting
09 APR 2025
Pay items
20
Data through
04 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Emery Sapp & Sons, Inc.$4,660,799Low
2Atlas Asphalt, Inc.$4,823,733+3.0%
ARDOT contract A90034: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Emery Sapp & Sons, Inc.2. Atlas Asphalt, Inc.
0001Aggregate base course (class 7) (303117)TON736$32.30$29.85
0002Tack coat (401011)GAL68,780$2.91$0.01
0003Mineral aggregate in achm surface course (3/8") (407161)TON8,917$101.51$107.48
0004Mineral aggregate in achm surface course (1/2") (407162)TON27,641$99.57$106.32
0005Asphalt binder (PG 64-22) in achm surface course (3/8") (minimum bid $120.00) (407431)TON610$120.00$120.00
0006Asphalt binder (PG 64-22) in achm surface course (1/2") (minimum bid $120.00) (407432)TON1,733$120.00$120.00
0007Cold milling asphalt pavement (412002)SY88,583$1.51$1.40
0008Achm patching of existing roadway (415011)TON300$147.79$125.00
0009Maintenance of traffic (603009)LS1$60,322$198,597
0010Signs (604003)SF1,122$4.30$4.00
0011Construction pavement markings (604041)LF206,098$0.24$0.22
0012Rumble strips in asphalt shoulders (642001)LF68,281$0.05$0.25
0013Centerline rumble stripes in asphalt roadways (642102)LF600$2.02$0.25
0014Thermoplastic pavement marking white (6") (719002)LF91,004$0.75$0.70
0015Thermoplastic pavement marking white (12") (719005)LF138$3.50$3.25
0016Thermoplastic pavement marking yellow (6") (719102)LF115,094$0.75$0.70
0017Thermoplastic pavement marking (words) (719201)EACH2$306.69$285.00
0018Thermoplastic pavement marking (arrows) (719202)EACH2$290.55$270.00
0019Raised pavement markers (type II) (721002)EACH2,206$3.77$3.50
0020Mobilization (unit bid amount may not exceed 5% of subtotal) (601001)LS1$36,436$42,014
ARDOT contract A90034: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from ARDOT's tabulation for this contract. ARDOT monthly bid tab PDFs (morning and afternoon sessions), January 2022 to November 2026. Base bids are printed in whole dollars; on A+B and A+C jobs the base bid is kept, and the published rank follows the award amount.

Every contract let that day: ARDOT letting of April 9, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy