ARDOT contract AX0010 bid tabulation
THE PURPOSE OF THIS PROJECT IS TO OVERLAY APPROXIMATELY 22.059 MILES OF HIGHWAY 66 IN SEARCY AND STONE COUNTIES. THIS PROJECT CONSISTS OF REMOVAL AND DISPOSAL OF GUARDRAIL, EARTHWORK, AGGREGATE BASE COURSE, ACHM SURFACE COURSE, COLD MILLING ASPHALT PAVEMENT, ACHM PATCHING OF EXISTING ROADWAY, APPROACH GUTTERS, MAINTENANCE OF TRAFFIC, GUARDRAIL, EROSION CONTROL ITEMS, RUMBLE STRIPES, PAVEMENT MARKING, AND MISC. ITEMS. Let by Arkansas DOT on November 5, 2025, Searcy, Stone. 2 bids received; low bid $6,937,731 by Atlas Asphalt, Inc..
- Owner
- Arkansas DOT
- Letting
- 05 NOV 2025
- Pay items
- 39
- Data through
- 04 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Atlas Asphalt, Inc. | $6,937,731 | Low |
| 2 | Apac-Central, Inc. | $8,729,041 | +26% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Atlas Asphalt, Inc. | 2. Apac-Central, Inc. |
|---|---|---|---|---|---|
| 0001 | Removal and disposal of guardrail (202132) | LF | 1,266 | $11.50 | $14.45 |
| 0002 | Unclassified excavation (210213) | CY | 350 | $75.13 | $42.00 |
| 0003 | Compacted embankment (210611) | CY | 700 | $115.72 | $72.00 |
| 0004 | Aggregate base course (class 7) (303117) | TON | 18,015 | $25.00 | $45.00 |
| 0005 | Tack coat (401011) | GAL | 115,718 | $0.01 | $3.50 |
| 0006 | Mineral aggregate in achm surface course (1/2") (407162) | TON | 57,855 | $84.96 | $106.00 |
| 0007 | Asphalt binder (PG 64-22) in achm surface course (1/2") (minimum bid $120.00) (407432) | TON | 3,627 | $120.00 | $120.00 |
| 0008 | Cold milling asphalt pavement (412002) | SY | 6,556 | $3.09 | $3.44 |
| 0009 | Asphalt concrete patching for maintenance of traffic (414011) | TON | 500 | $75.00 | $200.00 |
| 0010 | Achm patching of existing roadway (415011) | TON | 200 | $75.00 | $200.00 |
| 0011 | Approach gutters (504264) | CY | 10.86 | $4,700.00 | $1,350.00 |
| 0012 | Maintenance of traffic (603009) | LS | 1 | $438,140 | $160,000 |
| 0013 | Signs (604003) | SF | 2,130 | $11.00 | $11.85 |
| 0014 | Traffic drums (604023) | EACH | 50 | $55.00 | $59.25 |
| 0015 | Construction pavement markings (604041) | LF | 191,056 | $0.15 | $0.16 |
| 0016 | Vertical panels (604083) | EACH | 30 | $65.00 | $70.02 |
| 0017 | Guardrail (type A) (617005) | LF | 1,403 | $34.00 | $35.87 |
| 0018 | Guardrail terminal (type 2) (617312) | EACH | 7 | $3,250.00 | $3,658.89 |
| 0019 | Lime (620001) | TON | 4 | $150.00 | $134.66 |
| 0020 | Seeding (620011) | ACRE | 1.80 | $1,950.00 | $2,045.39 |
| 0021 | Mulch cover (620022) | ACRE | 3.60 | $1,250.00 | $1,537.61 |
| 0022 | Water (620030) | MGAL | 220.40 | $10.00 | $10.77 |
| 0023 | Temporary seeding (621001) | ACRE | 1.80 | $1,250.00 | $1,063.97 |
| 0024 | Sand bag ditch checks (621031) | BAG | 176 | $12.00 | $14.51 |
| 0025 | Sediment basin (621071) | CY | 200 | $1.70 | $24.10 |
| 0026 | Obliteration of sediment basin (621101) | CY | 200 | $1.70 | $12.05 |
| 0027 | Sediment removal and disposal (621111) | CY | 218 | $0.76 | $11.06 |
| 0028 | Rock ditch checks (621151) | CY | 30 | $51.70 | $100.00 |
| 0029 | Filter sock (18") (621169) | LF | 1,000 | $11.19 | $13.23 |
| 0030 | Second seeding application (623001) | ACRE | 1.80 | $500.00 | $954.79 |
| 0031 | Roadway construction control (635001) | LS | 1 | $4,440.04 | $15,334 |
| 0032 | Guardrail moved and reconstructed (639001) | LF | 1,000 | $45.00 | $31.08 |
| 0033 | Rumble stripes in asphalt shoulders (642011) | LF | 183,068 | $0.09 | $0.13 |
| 0034 | Reflectorized paint pavement marking white (6") (718002) | LF | 233,282 | $0.15 | $0.16 |
| 0035 | Reflectorized paint pavement marking yellow (6") (718102) | LF | 233,282 | $0.15 | $0.16 |
| 0036 | Raised pavement markers (type II) (721002) | EACH | 1,458 | $7.00 | $7.54 |
| 0037 | Bridge end terminal (734011) | EACH | 2 | $32,500 | $42,818 |
| 0038 | Reinforcing steel-roadway (grade 60) (804003) | LB | 738 | $2.50 | $3.23 |
| 0039 | Mobilization (unit bid amount may not exceed 5% of subtotal) (601001) | LS | 1 | $81,945 | $100,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ARDOT's tabulation for this contract. ARDOT monthly bid tab PDFs (morning and afternoon sessions), January 2022 to November 2026. Base bids are printed in whole dollars; on A+B and A+C jobs the base bid is kept, and the published rank follows the award amount.
Every contract let that day: ARDOT letting of November 5, 2025. Compiled by Mirage Metrics.