ARDOT contract SA1563 bid tabulation

THE PURPOSE OF THIS PROJECT IS TO OVERLAY APPROXIMATELY 0.87 MILE OF COUNTY ROAD 55 IN CONWAY COUNTY. THIS PROJECT CONSISTS OF AGGREGATE SURFACE COURSE, ACHM SURFACE COURSE, COLD MILLING ASPHALT PAVEMENT, ACHM PATCHING, MAINTENANCE OF TRAFFIC AND MISC. ITEMS. Let by Arkansas DOT on August 13, 2025, Conway. 3 bids received; low bid $168,781 by Blackstone Construction, LLC.

Owner
Arkansas DOT
Letting
13 AUG 2025
Pay items
11
Data through
04 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Blackstone Construction, LLC$168,781Low
2Rogers Group, Inc.$193,696+15%
3Tri State Asphalt, Inc.$301,622+79%
ARDOT contract SA1563: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Blackstone Construction, LLC2. Rogers Group, Inc.3. Tri State Asphalt, Inc.
0001Aggregate surface course (class D-8) (303308)TON138$46.53$65.00$75.00
0002Tack coat (401012)GAL1,476$4.00$1.00$6.00
0003Mineral aggregate in achm surface course (1/2") (407162)TON1,504$85.37$55.00$148.00
0004Asphalt binder (PG 64-22) in achm surface course (1/2") (minimum bid $120.00) (407432)TON101$120.00$600.00$148.00
0005Cold milling asphalt pavement (412002)SY700$4.00$8.00$13.00
0006Achm patching of existing roadway (415011)TON20$150.00$200.00$250.00
0007Mobilization (unit bid amount may not exceed 5% of subtotal) (601001)LS1$2,500.00$9,000.00$14,000
0008Maintenance of traffic (603009)LS1$1,500.00$14,000$12,500
0009Signs (604003)SF304$7.50$9.00$5.00
0010Reflectorized paint pavement marking white (4") (718001)LF9,188$0.21$0.25$0.15
0011Reflectorized paint pavement marking yellow (4") (718101)LF9,188$0.21$0.25$0.15
ARDOT contract SA1563: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from ARDOT's tabulation for this contract. ARDOT monthly bid tab PDFs (morning and afternoon sessions), January 2022 to November 2026. Base bids are printed in whole dollars; on A+B and A+C jobs the base bid is kept, and the published rank follows the award amount.

Every contract let that day: ARDOT letting of August 13, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy