ARDOT contract SA6258 bid tabulation
THE PURPOSE OF THIS PROJECT IS TO OVERLAY 1.20 MILES OF COUNTY ROAD 39 IN SALINE COUNTY. THIS PROJECT CONSISTS OF ACHM SURFACE COURSE, COLD MILLING ASPHALT PAVEMENT, ACHM PATCHING OF EXISTING ROADWAY, MAINTENANCE OF TRAFFIC, PAVEMENT MARKING, AND MISC. ITEMS. Let by Arkansas DOT on April 9, 2025, Saline. 3 bids received; low bid $255,170 by Redstone Construction Group, Inc..
- Owner
- Arkansas DOT
- Letting
- 09 APR 2025
- Pay items
- 10
- Data through
- 04 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Redstone Construction Group, Inc. | $255,170 | Low |
| 2 | Cranford Construction Co. | $260,492 | +2.0% |
| 3 | Tri State Asphalt, Inc. | $405,337 | +59% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Redstone Construction Group, Inc. | 2. Cranford Construction Co. | 3. Tri State Asphalt, Inc. |
|---|---|---|---|---|---|---|
| 0001 | Tack coat (401011) | GAL | 1,650 | $0.01 | $3.72 | $6.50 |
| 0002 | Mineral aggregate in achm surface course (1/2") (407162) | TON | 1,864 | $114.49 | $104.18 | $170.00 |
| 0003 | Asphalt binder (PG 64-22) in achm surface course (1/2") (minimum bid $120.00) (407432) | TON | 108 | $120.00 | $120.00 | $170.00 |
| 0004 | Cold milling asphalt pavement (412002) | SY | 351 | $19.95 | $15.95 | $13.00 |
| 0005 | Achm patching of existing roadway (415011) | TON | 70 | $200.00 | $277.61 | $250.00 |
| 0006 | Maintenance of traffic (603009) | LS | 1 | $1,500.00 | $9,560.52 | $12,500 |
| 0007 | Signs (604003) | SF | 148 | $5.00 | $8.60 | $5.00 |
| 0008 | Reflectorized paint pavement marking white (4") (718001) | LF | 12,672 | $0.12 | $0.15 | $0.20 |
| 0009 | Reflectorized paint pavement marking yellow (4") (718101) | LF | 12,672 | $0.12 | $0.14 | $0.20 |
| 0010 | Mobilization (unit bid amount may not exceed 5% of subtotal) (601001) | LS | 1 | $2,500.00 | $7,663.06 | $19,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ARDOT's tabulation for this contract. ARDOT monthly bid tab PDFs (morning and afternoon sessions), January 2022 to November 2026. Base bids are printed in whole dollars; on A+B and A+C jobs the base bid is kept, and the published rank follows the award amount.
Every contract let that day: ARDOT letting of April 9, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.