ARDOT contract SA73A0 bid tabulation
THE PURPOSE OF THIS PROJECT IS TO OVERLAY APPROXIMATELY 3.10 MILES OF COUNTY ROADS 97 AND 149 IN WHITE COUNTY. THIS PROJECT CONSISTS OF ACHM SURFACE COURSE, AGGREGATE BASE COURSE, ACHM PATCHING OF EXISTING ROADWAY, MAINTENANCE OF TRAFFIC, AND MISC. ITEMS. Let by Arkansas DOT on May 21, 2025, White. 4 bids received; low bid $477,847 by CK Asphalt, LLC.
- Owner
- Arkansas DOT
- Letting
- 21 MAY 2025
- Pay items
- 8
- Data through
- 04 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | CK Asphalt, LLC | $477,847 | Low |
| 2 | Delta Asphalt of Arkansas, Inc. | $516,078 | +8.0% |
| 3 | Rogers Group, Inc. | $516,801 | +8.0% |
| 4 | Tri State Asphalt, Inc. | $673,810 | +41% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. CK Asphalt, LLC | 2. Delta Asphalt of Arkansas, Inc. | 3. Rogers Group, Inc. | 4. Tri State Asphalt, Inc. |
|---|---|---|---|---|---|---|---|
| 0001 | Aggregate base course (class 7) (303117) | TON | 491 | $28.96 | $53.77 | $55.00 | $60.00 |
| 0002 | Tack coat (401011) | GAL | 3,674 | $1.00 | $4.18 | $1.00 | $6.00 |
| 0003 | Mineral aggregate in achm surface course (1/2") (407162) | TON | 4,353 | $89.41 | $87.25 | $62.00 | $118.00 |
| 0004 | Asphalt binder (PG 64-22) in achm surface course (1/2") (minimum bid $120.00) (407432) | TON | 273 | $120.00 | $120.00 | $560.00 | $120.00 |
| 0005 | Achm patching of existing roadway (415011) | TON | 120 | $185.00 | $203.07 | $200.00 | $250.00 |
| 0006 | Maintenance of traffic (603009) | LS | 1 | $8,500.00 | $15,000 | $13,500 | $12,500 |
| 0007 | Signs (604003) | SF | 232 | $6.00 | $6.00 | $8.00 | $6.00 |
| 0008 | Mobilization (unit bid amount may not exceed 5% of subtotal) (601001) | LS | 1 | $5,900.00 | $21,000 | $24,000 | $32,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ARDOT's tabulation for this contract. ARDOT monthly bid tab PDFs (morning and afternoon sessions), January 2022 to November 2026. Base bids are printed in whole dollars; on A+B and A+C jobs the base bid is kept, and the published rank follows the award amount.
Every contract let that day: ARDOT letting of May 21, 2025. Compiled by Mirage Metrics.