CDOT contract C22951 bid tabulation
FEDERAL BLVD SIGNAL MULTIPLE LOCATIONS. Let by Colorado DOT on February 13, 2025, Denver, Region 1. 6 bids received; low bid $934,434 by Adiona Transportation Solutions LLC, -15% against the engineer's estimate of $1,100,000.
- Owner
- Colorado DOT
- Letting
- 13 FEB 2025
- Pay items
- 80
- Data through
- 10 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Adiona Transportation Solutions LLC | $934,434 | Low | -15% |
| 2 | Sturgeon Electric Company, Inc. | $989,996 | +6.0% | -10% |
| 3 | HCG Construction LLC | $1,029,472 | +10% | -6.0% |
| 4 | Lighthouse Transportation Group, LLC | $1,066,274 | +14% | -3.0% |
| 5 | Morton Electric, Inc. | $1,100,000 | +18% | 0.0% |
| 6 | Advanced Electrical Contracting, Inc. | $1,196,363 | +28% | +9.0% |
Engineer's estimate: $1,100,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Adiona Transportation Solutions LLC | 2. Sturgeon Electric Company, Inc. | 3. HCG Construction LLC | 4. Lighthouse Transportation Group, LLC | 5. Morton Electric, Inc. | 6. Advanced Electrical Contracting, Inc. |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Removal of tree (202-00010) | EACH | 1 | $250.00 | $648.00 | $4,700.00 | $3,500.00 | $2,500.00 | $732.00 | $648.00 |
| 2 | Removal of concrete median cover material (202-00190) | SY | 9 | $35.00 | $54.00 | $80.00 | $100.00 | $63.00 | $33.00 | $32.40 |
| 3 | Removal of sidewalk (202-00200) | SY | 128 | $40.00 | $54.00 | $58.00 | $40.00 | $63.00 | $30.00 | $28.62 |
| 4 | Removal of curb and gutter (202-00203) | LF | 125 | $28.45 | $22.00 | $25.00 | $20.00 | $25.00 | $14.00 | $13.50 |
| 5 | Removal of concrete curb ramp (202-00206) | SY | 107 | $35.00 | $54.00 | $58.00 | $40.00 | $63.00 | $30.00 | $29.16 |
| 6 | Removal of concrete pavement (202-00210) | SY | 22 | $50.00 | $60.00 | $72.00 | $75.00 | $69.00 | $42.00 | $41.04 |
| 7 | Removal of asphalt mat (planing) (202-00240) | SY | 173 | $12.00 | $30.00 | $35.00 | $40.00 | $34.00 | $36.00 | $34.56 |
| 8 | Removal of pavement marking (202-00250) | SF | 785 | $2.50 | $5.00 | $9.00 | $4.00 | $6.00 | $5.00 | $4.59 |
| 9 | Removal of ground sign (202-00810) | EACH | 1 | $250.00 | $577.00 | $250.00 | $150.00 | $235.00 | $170.00 | $500.00 |
| 10 | Removal of traffic signal equipment (202-00828) | LS | 1 | $50,000 | $10,507 | $7,000.00 | $10,000 | $10,938 | $19,400 | $15,000 |
| 11 | Clean valve box (202-04005) | EACH | 5 | $180.00 | $577.00 | $625.00 | $550.00 | $2,632.00 | $200.00 | $340.20 |
| 12 | Potholing (203-01597) | HR | 69 | $250.00 | $309.00 | $650.00 | $420.00 | $379.00 | $300.00 | $297.00 |
| 13 | Erosion log type 1 (12 inch) (208-00002) | LF | 44 | $8.00 | $24.00 | $20.00 | $20.00 | $12.00 | $5.00 | $45.05 |
| 14 | Aggregate bag (208-00035) | LF | 102 | $10.00 | $22.00 | $20.00 | $20.00 | $16.00 | $8.00 | $7.96 |
| 15 | Pre-fabricated concrete washout structure (type 1) (208-00046) | EACH | 2 | $1,500.00 | $3,058.00 | $1,800.00 | $3,500.00 | $2,948.00 | $3,500.00 | $2,642.50 |
| 16 | Vehicle tracking pad (208-00070) | EACH | 2 | $3,000.00 | $599.00 | $2,800.00 | $2,500.00 | $2,190.00 | $1,850.00 | $13,911 |
| 17 | Removal and disposal of sediment (labor) (208-00103) | HR | 24 | $70.00 | $145.00 | $130.00 | $80.00 | $79.00 | $125.00 | $50.00 |
| 18 | Removal and disposal of sediment (equipment) (208-00105) | HR | 16 | $150.00 | $73.00 | $150.00 | $250.00 | $132.00 | $150.00 | $85.00 |
| 19 | Sweeping (sediment removal) (208-00106) | HR | 16 | $150.00 | $216.00 | $300.00 | $250.00 | $206.00 | $135.00 | $125.00 |
| 20 | Reset ground sign (210-00810) | EACH | 2 | $500.00 | $1,031.00 | $375.00 | $750.00 | $634.00 | $170.00 | $500.00 |
| 21 | Reset traffic signal vehicle detector (210-00882) | EACH | 4 | $2,000.00 | $763.00 | $1,350.00 | $500.00 | $1,070.00 | $1,050.00 | $1,000.00 |
| 22 | Adjust valve box (210-04050) | EACH | 1 | $500.00 | $1,774.00 | $1,550.00 | $950.00 | $1,579.00 | $560.00 | $1,000.00 |
| 23 | Sod (212-00050) | SF | 170 | $5.50 | $14.00 | $18.00 | $10.00 | $7.00 | $8.00 | $40.00 |
| 24 | Tree retention and protection (212-00100) | LS | 1 | $5,000.00 | $2,233.00 | $10,600 | $3,500.00 | $8,520.00 | $1,650.00 | $1,250.00 |
| 25 | Aggregate base course (class 6) (304-06000) | TON | 44 | $75.00 | $65.00 | $73.00 | $125.00 | $75.00 | $168.00 | $164.16 |
| 26 | Hot mix asphalt (patching) (asphalt) (403-00720) | TON | 72 | $300.00 | $270.00 | $275.00 | $300.00 | $313.00 | $358.00 | $351.00 |
| 27 | Concrete pavement (8 inch) (412-00800) | SY | 22 | $200.00 | $117.00 | $125.00 | $150.00 | $135.00 | $160.00 | $156.60 |
| 28 | Drilled shaft (18 inch) (503-00018) | LF | 6 | $350.00 | $605.00 | $550.00 | $350.00 | $272.00 | $300.00 | $516.68 |
| 29 | Drilled shaft (36 inch) (503-00036) | LF | 76 | $750.00 | $961.00 | $550.00 | $850.00 | $917.00 | $850.00 | $1,084.45 |
| 30 | Concrete sidewalk (608-00000) | SY | 118 | $125.00 | $106.00 | $110.00 | $100.00 | $123.00 | $141.00 | $138.24 |
| 31 | Concrete curb ramp (608-00010) | SY | 190 | $280.00 | $173.00 | $175.00 | $200.00 | $200.00 | $262.00 | $257.04 |
| 32 | Curb type 2 (section B) (609-20010) | LF | 46 | $50.00 | $58.00 | $62.00 | $50.00 | $67.00 | $47.00 | $45.36 |
| 33 | Curb and gutter type 2 (section II-B) (609-21020) | LF | 56 | $45.00 | $64.00 | $68.00 | $50.00 | $74.00 | $53.00 | $51.84 |
| 34 | Median cover material (concrete) (610-00030) | SF | 80 | $20.00 | $29.00 | $33.00 | $20.00 | $33.00 | $20.00 | $19.44 |
| 35 | 2 inch electrical conduit (bored) (613-00206) | LF | 500 | $30.00 | $22.00 | $28.00 | $32.00 | $28.00 | $28.00 | $38.90 |
| 36 | 3 inch electrical conduit (bored) (613-00306) | LF | 750 | $25.00 | $25.00 | $32.00 | $38.00 | $28.00 | $29.00 | $42.13 |
| 37 | 2 inch electrical conduit (plastic) (613-01200) | LF | 10 | $50.00 | $24.00 | $41.00 | $26.00 | $1.00 | $40.00 | $9.30 |
| 38 | 3 inch electrical conduit (plastic) (613-01300) | LF | 475 | $15.00 | $29.00 | $28.00 | $38.00 | $33.00 | $29.00 | $17.28 |
| 39 | Type three pull box (613-07003) | EACH | 5 | $1,100.00 | $2,053.00 | $2,000.00 | $1,250.00 | $2,029.00 | $1,774.00 | $1,144.96 |
| 40 | Type four pull box (613-07004) | EACH | 2 | $2,000.00 | $2,948.00 | $3,200.00 | $1,600.00 | $2,748.00 | $2,140.00 | $1,641.33 |
| 41 | Wiring (613-10000) | LS | 1 | $70,000 | $25,177 | $35,000 | $20,000 | $39,570 | $34,800 | $32,560 |
| 42 | Luminaire (LED) (special) (613-13000) | EACH | 4 | $1,100.00 | $1,377.00 | $950.00 | $1,500.00 | $1,135.00 | $1,320.00 | $1,676.00 |
| 43 | Service meter cabinet (613-80130) | EACH | 2 | $10,000 | $10,562 | $9,700.00 | $12,500 | $11,371 | $8,587.00 | $7,537.00 |
| 44 | Sign panel (class I) (614-00011) | SF | 49 | $40.00 | $31.00 | $35.00 | $50.00 | $38.00 | $14.00 | $36.99 |
| 45 | Sign panel (class II) (614-00012) | SF | 51 | $50.00 | $47.00 | $45.00 | $60.00 | $44.00 | $21.00 | $48.51 |
| 46 | Sign panel (class II) (install only) (614-00029) | EACH | 4 | $120.00 | $495.00 | $195.00 | $300.00 | $330.00 | $150.00 | $150.00 |
| 47 | Steel sign support (2-inch round)(post and socket) (614-01503) | EACH | 2 | $450.00 | $428.00 | $560.00 | $750.00 | $615.00 | $275.00 | $610.87 |
| 48 | Steel sign support (2-1/2 inch round NP- 40)(post & slipbase) (614-01573) | EACH | 6 | $650.00 | $680.00 | $775.00 | $750.00 | $1,117.00 | $516.00 | $1,077.95 |
| 49 | Pedestrian signal face (16) (countdown) (614-70150) | EACH | 10 | $700.00 | $680.00 | $900.00 | $500.00 | $858.00 | $640.00 | $523.03 |
| 50 | Traffic signal face (12-12-12) (614-70336) | EACH | 18 | $900.00 | $1,259.00 | $1,500.00 | $1,400.00 | $1,277.00 | $856.00 | $924.88 |
| 51 | Traffic signal face (12-12-12-12) (614-70448) | EACH | 4 | $1,100.00 | $1,509.00 | $1,725.00 | $1,500.00 | $1,577.00 | $1,025.00 | $1,202.95 |
| 52 | Traffic signal controller cabinet (614-72855) | EACH | 2 | $30,000 | $52,079 | $49,100 | $35,000 | $55,267 | $41,000 | $45,152 |
| 53 | Pedestrian push button (614-72860) | EACH | 11 | $850.00 | $1,842.00 | $1,460.00 | $1,900.00 | $1,910.00 | $1,500.00 | $1,745.00 |
| 54 | Pedestrian push button post assembly (614-72863) | EACH | 4 | $2,000.00 | $1,440.00 | $1,750.00 | $1,500.00 | $3,167.00 | $1,136.00 | $1,135.73 |
| 55 | Fire preemption unit and timer (614-72866) | EACH | 1 | $3,200.00 | $5,902.00 | $6,040.00 | $6,250.00 | $6,814.00 | $6,053.00 | $5,108.44 |
| 56 | Vehicle detection system (single camera) (614-72895) | EACH | 4 | $10,000 | $12,152 | $10,500 | $1,500.00 | $11,655 | $10,615 | $9,760.00 |
| 57 | Traffic signal-light pole steel (1-20 foot mast arm) (614-81120) | EACH | 2 | $22,000 | $20,336 | $20,000 | $24,500 | $20,767 | $18,076 | $15,695 |
| 58 | Traffic signal-light pole steel (1-40 foot mast arm) (614-81140) | EACH | 2 | $22,000 | $21,417 | $23,500 | $27,000 | $22,518 | $20,665 | $17,726 |
| 59 | Traffic signal-light pole steel (1-45 foot mast arm) (614-81145) | EACH | 2 | $28,000 | $24,661 | $23,800 | $30,500 | $26,202 | $24,318 | $21,006 |
| 60 | Traffic signal pedestal pole aluminum (614-84100) | EACH | 1 | $2,000.00 | $2,901.00 | $1,850.00 | $2,000.00 | $2,319.00 | $2,650.00 | $1,453.98 |
| 61 | Closed circuit television (614-87320) | EACH | 2 | $6,000.00 | $5,682.00 | $7,000.00 | $8,600.00 | $5,491.00 | $5,500.00 | $6,873.58 |
| 62 | Ethernet switch (614-87690) | EACH | 2 | $6,000.00 | $5,890.00 | $4,725.00 | $6,500.00 | $5,940.00 | $5,161.00 | $4,911.00 |
| 63 | Sanitary facility (620-00020) | EACH | 1 | $3,000.00 | $1,902.00 | $3,200.00 | $4,250.00 | $1,283.00 | $2,500.00 | $3,500.00 |
| 64 | Construction surveying (625-00000) | LS | 1 | $30,000 | $14,653 | $14,500 | $25,000 | $15,750 | $13,860 | $25,920 |
| 65 | Mobilization (626-00000) | LS | 1 | $113,723 | $50,387 | $51,000 | $75,000 | $78,248 | $223,511 | $243,085 |
| 66 | Public information management (tier IV) (626-01114) | DAY | 60 | $80.00 | $59.00 | $120.00 | $200.00 | $75.00 | $88.00 | $58.32 |
| 67 | Preformed thermoplastic pavement marking (xwalk-stop line) (627-30410) | SF | 1,492 | $20.00 | $20.00 | $20.00 | $16.00 | $16.00 | $20.00 | $21.95 |
| 68 | Flagging (630-00000) | HR | 40 | $45.00 | $34.00 | $36.00 | $40.00 | $42.00 | $37.00 | $42.12 |
| 69 | Traffic control inspection (630-00007) | DAY | 8 | $250.00 | $108.00 | $215.00 | $350.00 | $250.00 | $220.00 | $358.56 |
| 70 | Traffic control management (630-00012) | DAY | 40 | $1,800.00 | $1,188.00 | $1,425.00 | $1,000.00 | $1,375.00 | $1,210.00 | $1,487.16 |
| 71 | Uniformed traffic control coordination (630-00015) | HR | 100 | $22.00 | $27.00 | $27.00 | $125.00 | $32.00 | $28.00 | $16.20 |
| 72 | Barricade (type 3 M-A) (temporary) (630-80335) | EACH | 6 | $150.00 | $54.00 | $205.00 | $400.00 | $238.00 | $209.00 | $81.00 |
| 73 | Construction traffic sign (panel size A) (630-80341) | EACH | 16 | $65.00 | $27.00 | $50.00 | $150.00 | $57.00 | $50.00 | $21.60 |
| 74 | Construction traffic sign (panel size B) (630-80342) | EACH | 16 | $75.00 | $38.00 | $50.00 | $275.00 | $57.00 | $50.00 | $27.00 |
| 75 | Vertical panel (630-80350) | EACH | 50 | $40.00 | $38.00 | $40.00 | $75.00 | $44.00 | $39.00 | $12.96 |
| 76 | Portable message sign panel (630-80355) | EACH | 2 | $6,000.00 | $1,620.00 | $2,800.00 | $6,500.00 | $3,250.00 | $2,860.00 | $3,693.60 |
| 77 | Advance warning flashing or sequencing arrow panel (A type) (630-80356) | EACH | 2 | $2,000.00 | $864.00 | $1,300.00 | $3,500.00 | $1,500.00 | $1,320.00 | $2,386.80 |
| 78 | Drum channelizing device (630-80360) | EACH | 100 | $35.00 | $38.00 | $38.00 | $100.00 | $44.00 | $39.00 | $12.96 |
| 79 | Traffic cone (630-80380) | EACH | 100 | $12.00 | $11.00 | $8.00 | $40.00 | $9.00 | $8.00 | $8.64 |
| 80 | Mobile attenuator (630-85041) | DAY | 50 | $1,200.00 | $378.00 | $650.00 | $1,000.00 | $632.00 | $660.00 | $928.80 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from CDOT's tabulation for this contract. CDOT Tabulation of Bids PDFs from its bid tab archive, May 2023 to September 2026 (each contract linked to its OnBase document), and four December 2025 lettings read by OCR. About 100 tabulations of late 2025 and 2026 are printed in a font without text and are not read yet. On A+B contracts the cost part is kept. Bids that did not match their published total are left out.
Every contract let that day: CDOT letting of February 13, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.