Morton Electric, Inc.: CDOT bid record

Morton Electric, Inc. submitted 18 bids on Colorado DOT contracts in the data, from 13 JUN 2024 to 11 SEP 2025, and was the low bidder on 5 of them (28%). When it was not low, its total sat a median +8.0% above the low bid.

Owner
Colorado DOT
Low bid volume
$8,893,671
Latest bid
11 SEP 2025
Data through
10 SEP 2026
18Bids
5Low bids
28Win rate, percent
+8.0%Median gap to the low bid when not low, 13 bids

By year

YearBidsLow bidsWin rate
20249333%
20259222%
Morton Electric, Inc., CDOT: bids and low bids by year of letting

By region

RegionBidsLow bidsWin rate
Region 1500%
Region 45120%
Region 23133%
Region 32150%
Region 511100%
Region HQ ITS in Boulder100%
Morton Electric, Inc., CDOT: bids and low bids by region

Pay items where it is most often lowest

Pay itemCodeUnitLines bidLowest on the lineIts median priceAll bidders' median
3 inch electrical conduit (bored)613-00306LF129 (75%)$25.50$34.41
Traffic signal face (12-12-12)614-70336EACH99 (100%)$883.00$1,400.00
2 inch electrical conduit (bored)613-00206LF128 (67%)$23.50$29.00
Sign panel (class I)614-00011SF127 (58%)$34.50$33.00
Type four pull box613-07004EACH127 (58%)$2,190.50$3,105.00
Sweeping (sediment removal)208-00106HR117 (64%)$150.00$200.00
Curb and gutter type 2 (section II-B)609-21020LF117 (64%)$58.00$54.00
Traffic control management630-00012DAY166 (38%)$1,272.50$1,500.00
Construction traffic sign (panel size A)630-80341EACH166 (38%)$52.50$55.00
Potholing203-01597HR166 (38%)$300.00$350.00
Traffic cone630-80380EACH156 (40%)$10.00$13.00
Aggregate bag208-00035LF116 (55%)$11.00$12.75
Morton Electric, Inc., CDOT: pay items where its unit price was the lowest on the line

A line counts when the firm priced it and at least one other bidder did too; the lowest unit price on the line counts whoever won the contract. Token prices and bids over three times the low bid are left out.

Who it meets most

FirmContracts in commonThat firm ranked ahead
Sturgeon Electric Company, Inc.96 of 9
Lighthouse Transportation Group, LLC75 of 7
Adiona Transportation Solutions LLC63 of 6
Lumin8 Transportation Technologies, LLC40 of 4
Concrete Concepts Design Inc, DBA Pyramid Construction Inc21 of 2
Rodriguez Construction Org., LLC20 of 2
Myers & Sons Construction, LLC20 of 2
Advanced Electrical Contracting, Inc.20 of 2
Goodland Construction, Inc.21 of 2
Sema Construction, Inc.11 of 1
Morton Electric, Inc., CDOT: the firms on the same contracts most often

Latest bids

LetContractRegionProjectRankIts bidAgainst the low bid
11 SEP 2025C24061Region 4Install a traffic control signal at the intersection of SH52 and WCR41.2 of 5$598,0050.0%
14 AUG 2025C25525Region 4VARIOUS LOCATIONS THROUGHOUT R44 of 4$4,019,196+68%
14 AUG 2025C26205Region 1SH 74/KERRGULCH;SH83/GILLIAN,RUSSELLVILLE;SH30/PICCADILLY3 of 4$1,472,210+1.0%
17 JUL 2025C26196Region 1WADSWORTH BLVD & EVANS AVE Installation of new traffic signal and curb ramps at the intersection of Wadsworth Blvd & Evans Ave. One dual mas3 of 4$708,679+8.0%
26 JUN 2025C25982Region HQ ITS in BoulderInstall fiber optic cable along SH-66 from I-25 to Lyons and Install cameras along US-36 from Lyons to Estes Park This project has an OPTION2 of 4$5,573,359+4.0%
17 APR 2025C23818Region 3Signal head, cabinet, and conduit replacements.1 of 1$635,240Low
10 APR 2025C26304Region 2US50/MAPLE & US287/CEDAR, LAMAR PROWERS COUNTY1 of 2$1,482,503Low, 19% under the second
13 FEB 2025C22951Region 1FEDERAL BLVD SIGNAL MULTIPLE LOCATIONS5 of 6$1,100,000+18%
30 JAN 2025C25012Region 3This project will replace the traffic signal at the CO-13 (Yampa Ave.) & 9th St in Craig, CO as well as replace the conduit and signal cabin2 of 3$1,385,962+8.0%
19 DEC 2024C24618Region 5Project 24618 US 160D Mancos Pedestrian Improvements is an ADA curb ramp and sidewalk installation project. The project proposes replacement1 of 2$2,172,250Low, 24% under the second
12 DEC 2024C26096Region 2US 50C AND BAXTER RD2 of 3$848,131+1.0%
24 OCT 2024C23021Region 1This project is located on State Highway 53 between 58th Ave and 70th Ave. The work involves the replacement of traffic signals at 62nd and 4 of 5$1,411,952+12%
24 OCT 2024C25613Region 4CO 402 & S CR 5 (MM 140.0-141.1)3 of 5$472,709+10%
29 AUG 2024C19164Region 4US 34 & US 85 INTERCHANGE IN GREELEY2 of 6$2,857,746+10%
01 AUG 2024C25205Project will updated technology and communications at 18 chain stations along I-70 from Vail to Genessee and 2 chain stations along I-25 in 1 of 1$3,801,536Low
11 JUL 2024C25140Region 1This project will be doing a full-depth replacement of the pavement of the NB chain area where trucks will be entering to de-chain only when3 of 5$2,678,576+5.0%
11 JUL 2024C25602Region 4Project will replace signal poles, mast arms, and signal equipment at two intersections in Loveland: US 34 & N Van Buren Ave and CO 402 & So1 of 5$802,143Low, 14% under the second
13 JUN 2024C25832Region 2US 85 & CARSON BLVD, FOUNTAIN, EL PASO COUNTY2 of 3$2,690,432+4.0%
Morton Electric, Inc.: latest CDOT bids in the data

How this record was read

CDOT Tabulation of Bids PDFs from its bid tab archive, May 2023 to September 2026 (each contract linked to its OnBase document), and four December 2025 lettings read by OCR. About 100 tabulations of late 2025 and 2026 are printed in a font without text and are not read yet. On A+B contracts the cost part is kept. Bids that did not match their published total are left out.

  • Every bid counted here matched its published total to within one dollar; CDOT's rank decides who was low.
  • The gap to the low bid is the firm's total over the low total, minus one, on contracts it did not win, leaving out bids over three times the low bid.
  • A record covers the lettings in the data, not every contract the firm ever bid. Coverage by year is on the state page.

A name split in two, or a figure that does not match the owner's tabulation? Write to mehdi@miragemetrics.com and we correct it.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy