CDOT contract C24061 bid tabulation

Install a traffic control signal at the intersection of SH52 and WCR41. Let by Colorado DOT on September 11, 2025, Weld, Region 4. 5 bids received; low bid $597,028 by Sturgeon Electric Company, Inc., -24% against the engineer's estimate of $785,071.

Owner
Colorado DOT
Letting
11 SEP 2025
Pay items
63
Data through
10 SEP 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Sturgeon Electric Company, Inc.$597,028Low-24%
2Morton Electric, Inc.$598,0050.0%-24%
3Adiona Transportation Solutions LLC$625,116+5.0%-20%
4Lumin8 Transportation Technologies, LLC$635,529+6.0%-19%
5Lighthouse Transportation Group, LLC$686,046+15%-13%
CDOT contract C24061: bids by rank

Engineer's estimate: $785,071.

Bid tabulation

LinePay itemUnitQuantityEstimate1. Sturgeon Electric Company, Inc.2. Morton Electric, Inc.3. Adiona Transportation Solutions LLC4. Lumin8 Transportation Technologies, LLC5. Lighthouse Transportation Group, LLC
1Clearing and grubbing (201-00000)LS1$19,011$1,700.00$2,500.00$10,778$1,438.50$5,600.00
2Removal of ground sign (202-00810)EACH2$198.46$165.00$50.00$154.00$270.00$225.00
3Combination loader (203-01594)HR40$159.48$162.00$10.00$98.00$153.50$190.00
4Potholing (203-01597)HR32$291.90$575.00$250.00$253.00$357.50$340.00
5Topsoil (onsite) (207-00700)CY40$53.10$55.00$96.00$142.00$49.00$45.00
6Erosion log type 1 (12 inch) (208-00002)LF140$8.38$6.70$6.29$7.00$4.00$8.00
7Pre-fabricated concrete washout structure (type 1) (208-00046)EACH1$1,623.61$3,150.00$4,675.00$1,284.00$1,650.50$2,215.00
8Pre-fabricated vehicle tracking pad (208-00075)EACH1$3,827.63$1,500.00$3,170.00$8,100.00$10,857$3,500.00
9Removal and disposal of sediment (labor) (208-00103)HR2$79.87$150.00$10.00$130.00$97.50$90.00
10Removal and disposal of sediment (equipment) (208-00105)HR2$152.13$290.00$10.00$130.00$152.50$150.00
11Sweeping (sediment removal) (208-00106)HR9$165.01$120.00$10.00$195.00$143.00$185.00
12Removal of trash (208-00107)HR3$112.61$150.00$10.00$104.00$98.50$90.00
13Erosion control management (208-00200)LS1$10,000$920.00$5,720.00$3,197.00$3,470.00$7,100.00
14Dewatering (211-03005)LS1$13,000$6,000.00$4,000.00$12,683$11,488$50,000
15Organic fertilizer (212-00700)LB15$12.00$32.00$36.67$36.00$15.50$5.00
16Compost (mechanically applied) (212-00701)CY3$122.13$125.00$110.00$105.00$329.00$95.00
17Mycorrhizae (212-00704)LB3$67.50$130.00$119.17$119.00$53.50$70.00
18Seeding (native) broadcast (212-00708)ACRE0.05$50,000$21,500$23,430$23,403$120,850$13,335
19Spray-on mulch blanket (213-00012)ACRE0.05$50,000$24,000$30,800$29,342$180,750$8,000.00
20Mulch tackifier (213-00061)LB10$15.00$62.00$92.11$83.00$6.00$40.00
21Herbicide treatment (217-00020)HR5$171.51$400.00$488.00$435.00$208.00$250.00
22Drilled shaft (36 inch) (503-00036)LF76$600.00$805.00$725.00$652.00$645.00$765.00
232 inch electrical conduit (bored) (613-00206)LF415$33.00$24.50$20.00$21.00$19.50$25.00
243 inch electrical conduit (bored) (613-00306)LF825$38.00$27.00$20.00$24.00$23.00$27.00
252 inch electrical conduit (plastic) (613-01200)LF145$27.25$23.00$20.00$18.00$31.50$25.00
263 inch electrical conduit (plastic) (613-01300)LF260$40.00$24.50$20.00$23.00$25.50$27.00
27Type three pull box (613-07003)EACH1$1,409.42$1,700.00$1,995.00$2,243.00$2,350.00$1,870.00
28Type four pull box (613-07004)EACH3$1,986.39$2,400.00$2,500.00$3,406.00$3,511.00$2,525.00
29Type five pull box (613-07005)EACH1$2,440.80$3,000.00$2,950.00$4,949.00$4,539.00$3,385.00
30Wiring (613-10000)LS1$60,000$24,500$17,500$24,038$20,972$22,500
31Luminaire (LED) (special) (613-13000)EACH4$2,100.00$900.00$900.00$967.00$710.50$1,225.00
32Meter power pedestal (613-50109)EACH1$13,000$13,500$10,000$11,379$11,034$11,125
33Sign panel (class I) (614-00011)SF55.50$29.04$72.00$33.59$53.00$25.00$38.00
34Signal head backplates (614-10160)EACH8$221.10$320.00$300.00$206.00$274.50$170.00
35Traffic signal face (12-12-12) (614-70336)EACH16$883.00$1,450.00$700.00$1,036.00$1,088.50$925.00
36Traffic signal controller cabinet (614-72855)EACH1$49,100$29,500$28,000$26,211$27,158$30,625
37Fire preemption unit (614-72864)EACH2$8,290.35$7,700.00$7,498.00$7,316.00$7,457.00$7,209.00
38Intersection detection system (camera) (614-72886)EACH4$12,500$12,500$12,510$13,027$14,150$9,925.00
39Traffic signal-light pole steel (1-50 foot mast arm) (614-81150)EACH2$23,000$24,000$24,170$24,309$25,153$25,155
40Traffic signal-light pole steel (1-55 foot mast arm) (614-81155)EACH2$25,000$24,500$24,805$24,752$25,875$26,225
41Traffic signal controller (type 2070LC) (614-86248)EACH1$9,500.00$8,000.00$7,523.00$8,589.00$9,223.00$8,650.00
42Uninterrupted power supply (614-86800)EACH1$12,588$7,500.00$10,339$8,671.00$9,016.00$8,875.00
43Field office (class 2) (620-00002)EACH1$39,500$22,000$30,835$28,710$16,683$45,000
44Sanitary facility (620-00020)EACH2$2,296.37$410.00$335.00$913.00$577.00$1,220.00
45Construction surveying (625-00000)LS1$40,000$4,200.00$4,630.00$6,072.00$4,997.00$4,252.00
46Mobilization (626-00000)LS1$55,000$31,000$85,000$51,933$30,475$56,856
47Preformed thermoplastic pavement marking (xwalk-stop line) (627-30410)SF154$21.46$18.00$32.71$17.00$28.00$20.00
48Flagging (630-00000)HR400$50.00$39.00$50.00$40.00$64.00$45.00
49Traffic control inspection (630-00007)DAY24$150.00$230.00$175.00$237.00$208.00$65.00
50Traffic control management (630-00012)DAY30$1,300.00$1,200.00$1,000.00$938.00$1,166.00$1,738.00
51Flashing beacon (portable) (630-80001)EACH4$734.06$170.00$385.00$171.00$486.00$91.00
52Barricade (type 3 M-A) (temporary) (630-80335)EACH5$112.88$38.00$82.00$39.00$104.00$32.00
53Construction traffic sign (panel size A) (630-80341)EACH14$47.47$20.00$27.00$20.00$34.50$26.00
54Construction traffic sign (panel size B) (630-80342)EACH22$58.94$27.00$27.00$28.00$34.50$42.00
55Construction traffic sign (panel size C) (630-80343)EACH5$73.57$38.00$27.00$39.00$34.50$56.00
56Vertical panel (630-80350)EACH20$33.31$6.50$17.00$7.00$21.00$28.00
57Portable message sign panel (630-80355)EACH2$5,105.07$2,700.00$1,850.00$2,750.00$2,776.00$3,131.00
58Advance warning flashing or sequencing arrow panel (C type) (630-80358)EACH2$1,148.60$700.00$880.00$715.00$1,110.50$244.00
59Drum channelizing device (630-80360)EACH25$28.10$8.00$22.00$8.00$28.00$34.00
60Barrier (temporary) (630-80370)LF100$54.70$52.00$65.00$107.00$58.50$55.00
61Traffic cone (630-80380)EACH50$9.30$6.00$8.25$6.00$10.50$15.00
62Impact attenuator (temporary) (630-85010)EACH2$8,800.00$2,200.00$1,100.00$5,173.00$7,773.00$1,875.00
63Impact attenuator (truck mounted attenuator) (temporary) (630-85040)EACH1$13,432$16,000$2,500.00$16,225$28,940$10,412
CDOT contract C24061: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from CDOT's tabulation for this contract. CDOT Tabulation of Bids PDFs from its bid tab archive, May 2023 to September 2026 (each contract linked to its OnBase document), and four December 2025 lettings read by OCR. About 100 tabulations of late 2025 and 2026 are printed in a font without text and are not read yet. On A+B contracts the cost part is kept. Bids that did not match their published total are left out.

Every contract let that day: CDOT letting of September 11, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy