Removal of trash, CDOT 208-00107
Low bidders on CDOT contracts carried a median of $110.00 per HR for this item, over the 24 months to 10 SEP 2026, across 61 low bids. Half of all 221 bids fell between $70.00 and $150.00.
- Owner
- Colorado DOT
- Item
- 208-00107
- Unit
- HR
- Data through
- 10 SEP 2026
CDOT prints this item as “Removal of Trash”.
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2023 | 2 | 2 | $118.31 | 2 | $118.31 |
| 2024 | 45 | 45 | $117.00 | 161 | $125.00 |
| 2025 | 28 | 27 | $94.00 | 98 | $100.00 |
| 2026 | 2 | 2 | $352.50 | 4 | $126.00 |
Bid prices as published, not adjusted for inflation.
By region
| Region | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Region 1 | 19 | $100.00 | 77 | $103.76 |
| Region 4 | 11 | $110.00 | 49 | $110.00 |
| Region 3 | 15 | $75.00 | 40 | $110.00 |
| Region 2 | 8 | $91.25 | 27 | $114.73 |
| Region 5 | 4 | $125.00 | 15 | $139.00 |
Regions with at least three low bids, over the last 24 months.
By quantity
| Quantity (HR) | Low bids | Low-bid median |
|---|---|---|
| 1 to 10 | 15 | $110.00 |
| 10 to 20 | 15 | $110.00 |
| 20 to 40 | 15 | $100.00 |
| 40 to 272 | 16 | $101.25 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Who is lowest on this line
| Bidder | Lines bid | Lowest on the line |
|---|---|---|
| Oldcastle SW Group, Inc. | 20 | 14 (70%) |
| Myers & Sons Construction, LLC | 18 | 10 (56%) |
| Morton Electric, Inc. | 7 | 4 (57%) |
| Kilgore Companies, LLC dba Elam Construction | 9 | 3 (33%) |
| Structures, Inc. | 13 | 2 (15%) |
| Kiewit Infrastructure Co. | 9 | 2 (22%) |
The lowest unit price on each line, whoever won the contract, over all lettings in the data, for firms with five lines or more.
Latest contracts with this item
| Let | Contract | Region | Quantity | Low bidder's price | Median | Estimate | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|---|
| 10 SEP 2026 | C27188 | Region 3 | 10 | $75.00 | $112.50 | $83.19 | 2 | A-1 Chipseal Company | CDOT |
| 02 MAR 2026 | C27259 | Region 1 | 24 | $630.00 | $366.00 | $75.00 | 2 | CONCRETE EXPRESS, INC.dba CEI | CDOT |
| 18 DEC 2025 | C26234 | 40 | $220.00 | $158.50 | $200.00 | 2 | Native Sun Materials Inc | CDOT | |
| 18 DEC 2025 | C26274 | 30 | $40.00 | $98.00 | $100.00 | 5 | Oldcastle SW Group, Inc. | CDOT | |
| 11 DEC 2025 | C25682 | 10 | $40.00 | $121.00 | $125.00 | 2 | Oldcastle SW Group, Inc. | CDOT | |
| 18 SEP 2025 | C25393 | Region 2 | 20 | $70.00 | $118.50 | $97.51 | 8 | Siete, Inc. | CDOT |
| 11 SEP 2025 | C24061 | Region 4 | 3 | $150.00 | $98.50 | $112.61 | 5 | Sturgeon Electric Company, Inc. | CDOT |
| 21 AUG 2025 | C26065 | Region 1 | 20 | $100.00 | $80.00 | $125.65 | 5 | Myers & Sons Construction, LLC | CDOT |
| 21 AUG 2025 | C26632 | Region 4 | 1 | $75.00 | $137.50 | $142.45 | 4 | Abco Contracting, Inc. | CDOT |
| 14 AUG 2025 | C26205 | Region 1 | 10 | $120.00 | $102.50 | $116.91 | 4 | Sturgeon Electric Company, Inc. | CDOT |
| 24 JUL 2025 | C27031 | Region 1 | 10 | $100.00 | $100.00 | $92.00 | 1 | Brannan Sand and Gravel, LLC | CDOT |
| 26 JUN 2025 | C25982 | Region HQ ITS in Boulder | 20 | n/a | $95.00 | $127.67 | 3 | Dillie and Kuhn, Inc | CDOT |
| 12 JUN 2025 | C26058 | Region 3 | 20 | $65.00 | $110.00 | $100.00 | 4 | Ridgway Valley Enterprises, Inc | CDOT |
| 05 JUN 2025 | C25575 | Region 1 | 40 | $55.00 | $55.00 | $119.30 | 5 | Myers & Sons Construction, LLC | CDOT |
| 23 MAY 2025 | C25826 | 20 | $224.22 | $224.22 | $224.22 | 1 | Jalisco International, Inc. | CDOT |
Filter this item by your own quantity, region and period, or check your price against it, in the CDOT explorer.
How these prices were read
CDOT Tabulation of Bids PDFs from its bid tab archive, May 2023 to September 2026 (each contract linked to its OnBase document), and four December 2025 lettings read by OCR. About 100 tabulations of late 2025 and 2026 are printed in a font without text and are not read yet. On A+B contracts the cost part is kept. Bids that did not match their published total are left out.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are CDOT's own: this item is compared with CDOT contracts only.
- Prices are bid prices, not paid prices. Use them as a reference range, never as a quote.
- The data runs to the CDOT letting of 10 SEP 2026 and was rebuilt on 26 NOV 2026.
Your own bid history, read the same way