CDOT contract C26065 bid tabulation
I-70 AND PENA BLVD OVERPASS. Let by Colorado DOT on August 21, 2025, Adams, Region 1. 5 bids received; low bid $818,182 by Myers & Sons Construction, LLC, -9.1% against the engineer's estimate of $900,000.
- Owner
- Colorado DOT
- Letting
- 21 AUG 2025
- Pay items
- 74
- Data through
- 10 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Myers & Sons Construction, LLC | $818,182 | Low | -9.0% |
| 2 | Edge Contracting, Inc. | $871,427 | +7.0% | -3.0% |
| 3 | W.W. Clyde & Co. | $1,028,385 | +26% | +14% |
| 4 | Abco Contracting, Inc. | $1,083,193 | +32% | +20% |
| 5 | American West Construction, LLC | $1,096,938 | +34% | +22% |
Engineer's estimate: $900,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Myers & Sons Construction, LLC | 2. Edge Contracting, Inc. | 3. W.W. Clyde & Co. | 4. Abco Contracting, Inc. | 5. American West Construction, LLC |
|---|---|---|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201-00001) | ACRE | 0.10 | $45,000 | $50,000 | $300,000 | $40,000 | $58,000 | $43,000 |
| 2 | Removal of delineator (202-00090) | EACH | 10 | $32.53 | $20.00 | $36.00 | $25.00 | $23.00 | $110.00 |
| 3 | Removal of concrete pavement (202-00210) | SY | 192 | $61.83 | $59.00 | $150.00 | $50.00 | $140.00 | $81.00 |
| 4 | Removal of pavement marking (202-00250) | SF | 4,600 | $3.05 | $1.00 | $4.00 | $1.50 | $3.50 | $1.50 |
| 5 | Removal of ground sign (202-00810) | EACH | 1 | $307.00 | $150.00 | $330.00 | $400.00 | $290.00 | $300.00 |
| 6 | Removal of concrete footing (202-00900) | EACH | 2 | $1,703.09 | $550.00 | $1,200.00 | $800.00 | $1,000.00 | $1,900.00 |
| 7 | Removal of guardrail type 3 (202-01130) | LF | 401 | $10.38 | $28.00 | $12.00 | $10.00 | $18.00 | $22.00 |
| 8 | Removal of guardrail thrie beam (202-01135) | LF | 25 | $19.76 | $25.00 | $21.00 | $30.00 | $30.00 | $22.00 |
| 9 | Removal of guardrail type 7 (202-01170) | LF | 109 | $98.51 | $70.00 | $77.00 | $48.00 | $154.00 | $92.00 |
| 10 | Removal of end anchorage (202-01300) | EACH | 6 | $398.09 | $435.00 | $650.00 | $550.00 | $500.00 | $670.00 |
| 11 | Clean culvert (202-04002) | EACH | 2 | $3,130.27 | $2,500.00 | $5,000.00 | $7,200.00 | $4,000.00 | $3,300.00 |
| 12 | Unsuitable material (203-00050) | CY | 15 | $155.16 | $71.00 | $200.00 | $125.00 | $250.00 | $130.00 |
| 13 | Embankment material (complete in place) (203-00060) | CY | 15 | $191.62 | $71.00 | $280.00 | $130.00 | $220.00 | $320.00 |
| 14 | Blading (203-01500) | HR | 20 | $287.19 | $150.00 | $220.00 | $190.00 | $225.00 | $270.00 |
| 15 | Potholing (203-01597) | HR | 20 | $314.51 | $275.00 | $450.00 | $350.00 | $495.00 | $300.00 |
| 16 | Structure excavation (206-00000) | CY | 419 | $63.07 | $63.00 | $50.00 | $30.00 | $75.00 | $99.00 |
| 17 | Structure backfill (class 1) (206-00100) | CY | 361 | $104.41 | $92.00 | $110.00 | $32.00 | $72.00 | $100.00 |
| 18 | Topsoil (onsite) (207-00700) | CY | 484 | $72.48 | $20.00 | $15.00 | $27.00 | $35.00 | $31.00 |
| 19 | Subgrade soil preparation (207-00704) | SY | 1,090 | $4.86 | $9.00 | $5.00 | $5.00 | $6.00 | $21.00 |
| 20 | Erosion log type 1 (12 inch) (208-00002) | LF | 750 | $8.23 | $9.00 | $11.00 | $9.00 | $7.00 | $4.00 |
| 21 | Aggregate bag (208-00035) | LF | 200 | $13.87 | $12.00 | $12.00 | $17.00 | $14.00 | $19.00 |
| 22 | Pre-fabricated concrete washout structure (type 1) (208-00046) | EACH | 1 | $2,834.43 | $1,700.00 | $2,500.00 | $3,600.00 | $2,215.00 | $3,400.00 |
| 23 | Storm drain inlet protection (type III) (208-00056) | EACH | 1 | $422.04 | $390.00 | $1,300.00 | $1,000.00 | $250.00 | $190.00 |
| 24 | Pre-fabricated vehicle tracking pad (208-00075) | EACH | 2 | $4,222.17 | $2,100.00 | $2,800.00 | $14,500 | $2,500.00 | $5,000.00 |
| 25 | Sweeping (sediment removal) (208-00106) | HR | 20 | $183.44 | $150.00 | $115.00 | $207.00 | $190.00 | $190.00 |
| 26 | Removal of trash (208-00107) | HR | 20 | $125.65 | $100.00 | $45.00 | $139.00 | $80.00 | $66.00 |
| 27 | Erosion control management (208-00207) | DAY | 32 | $383.47 | $150.00 | $100.00 | $1,500.00 | $470.00 | $410.00 |
| 28 | Modify inlet (210-04020) | EACH | 1 | $5,097.58 | $6,000.00 | $3,000.00 | $17,000 | $8,000.00 | $8,400.00 |
| 29 | Organic fertilizer (212-00700) | LB | 180 | $2.60 | $4.00 | $9.00 | $1.50 | $0.50 | $4.00 |
| 30 | Compost (mechanically applied) (212-00701) | CY | 39 | $122.58 | $60.00 | $100.00 | $139.00 | $85.00 | $130.00 |
| 31 | Mycorrhizae (212-00704) | LB | 24 | $19.02 | $35.00 | $23.00 | $19.00 | $12.00 | $51.00 |
| 32 | Seeding (native) drill (212-00706) | ACRE | 0.60 | $2,779.16 | $3,500.00 | $5,000.00 | $4,990.00 | $3,920.00 | $4,100.00 |
| 33 | Mulching (weed free straw) (213-00004) | ACRE | 0.60 | $2,250.73 | $2,200.00 | $8,000.00 | $4,140.00 | $3,290.00 | $6,300.00 |
| 34 | Mulch tackifier (213-00061) | LB | 120 | $7.48 | $12.00 | $9.00 | $12.00 | $8.00 | $6.00 |
| 35 | Reconditioning (306-01000) | SY | 148 | $40.39 | $30.00 | $45.00 | $10.00 | $47.00 | $63.00 |
| 36 | Hot mix asphalt (patching) (asphalt) (403-00720) | TON | 45 | $435.97 | $600.00 | $230.00 | $1,020.00 | $475.00 | $530.00 |
| 37 | Concrete pavement (10 inch) (412-01000) | SY | 148 | $180.00 | $235.00 | $280.00 | $225.00 | $190.00 | $290.00 |
| 38 | 12 inch reinforced concrete pipe (603-01120) | LF | 543 | $60.11 | $120.00 | $110.00 | $180.00 | $200.00 | $100.00 |
| 39 | Inlet special (trench drain) (12 inch width) (604-19712) | LF | 204 | $285.00 | $400.00 | $590.00 | $620.00 | $690.00 | $190.00 |
| 40 | Manhole slab base (5 foot) (604-30005) | EACH | 2 | $6,398.71 | $8,500.00 | $5,800.00 | $15,000 | $20,000 | $8,200.00 |
| 41 | Guardrail type 3 (31 inch midwest guardrail system) (606-00302) | LF | 388 | $50.00 | $34.50 | $75.00 | $40.00 | $40.00 | $81.00 |
| 42 | Guardrail type 9 (style CA) (606-00910) | LF | 137 | $297.67 | $350.00 | $400.00 | $480.00 | $275.00 | $450.00 |
| 43 | End anchorage type 3D (606-01340) | EACH | 2 | $2,070.95 | $1,750.00 | $1,900.00 | $2,100.00 | $2,000.00 | $4,000.00 |
| 44 | Transition type 3G (606-01370) | EACH | 2 | $4,320.93 | $4,250.00 | $4,800.00 | $5,100.00 | $5,000.00 | $6,700.00 |
| 45 | End anchorage (flared) (606-02005) | EACH | 4 | $3,960.08 | $4,150.00 | $4,500.00 | $5,000.00 | $4,870.00 | $7,300.00 |
| 46 | Fence (plastic) (607-11525) | LF | 500 | $4.62 | $3.25 | $3.00 | $5.00 | $3.00 | $4.00 |
| 47 | Delineator (type I) (612-00001) | EACH | 8 | $42.54 | $55.00 | $80.00 | $54.00 | $53.00 | $60.00 |
| 48 | Delineator (type III) (612-00003) | EACH | 2 | $78.23 | $85.00 | $85.00 | $54.00 | $53.00 | $61.00 |
| 49 | Sign panel (class II) (614-00012) | SF | 16 | $46.49 | $35.00 | $60.00 | $48.00 | $47.00 | $54.00 |
| 50 | Steel sign support (2-1/2 in round SCH 80) (post & slipbase) (614-01583) | EACH | 1 | $731.13 | $650.00 | $1,000.00 | $884.00 | $870.00 | $990.00 |
| 51 | Sanitary facility (620-00020) | EACH | 2 | $2,632.71 | $900.00 | $500.00 | $478.00 | $865.00 | $530.00 |
| 52 | Construction surveying (625-00000) | LS | 1 | $29,791 | $14,199 | $15,000 | $28,000 | $17,000 | $27,000 |
| 53 | Mobilization (626-00000) | LS | 1 | $82,732 | $80,000 | $87,000 | $100,000 | $95,000 | $175,000 |
| 54 | Public information management (tier IV) (626-01114) | DAY | 70 | $85.00 | $55.00 | $95.00 | $75.00 | $65.00 | $94.00 |
| 55 | Modified epoxy pavement marking (627-00008) | GAL | 29 | $531.76 | $125.00 | $340.00 | $165.00 | $310.00 | $170.00 |
| 56 | Pavement marking paint (high build) (627-00013) | GAL | 62 | $412.93 | $60.00 | $230.00 | $80.00 | $264.00 | $82.00 |
| 57 | Uniformed traffic control (630-00003) | HR | 20 | $173.95 | $129.00 | $120.00 | $154.00 | $150.00 | $170.00 |
| 58 | Uniformed traffic control (vehicle) (630-00006) | HR | 20 | $46.22 | $40.00 | $60.00 | $48.00 | $47.00 | $54.00 |
| 59 | Traffic control inspection (630-00007) | DAY | 20 | $300.00 | $237.00 | $250.00 | $283.00 | $280.00 | $320.00 |
| 60 | Traffic control management (630-00012) | DAY | 32 | $1,000.00 | $1,446.00 | $1,525.00 | $1,730.00 | $1,695.00 | $2,000.00 |
| 61 | Barricade (type 3 M-A) (temporary) (630-80335) | EACH | 4 | $139.73 | $75.00 | $100.00 | $89.00 | $88.00 | $100.00 |
| 62 | Construction traffic sign (panel size A) (630-80341) | EACH | 15 | $47.44 | $25.00 | $47.00 | $30.00 | $29.00 | $34.00 |
| 63 | Construction traffic sign (panel size B) (630-80342) | EACH | 11 | $60.19 | $30.00 | $50.00 | $36.00 | $35.00 | $40.00 |
| 64 | Construction traffic sign (panel size C) (630-80343) | EACH | 8 | $77.15 | $30.00 | $55.00 | $36.00 | $35.00 | $40.00 |
| 65 | Vertical panel (630-80350) | EACH | 20 | $33.31 | $12.00 | $20.00 | $14.00 | $14.00 | $16.00 |
| 66 | Portable message sign panel (630-80355) | EACH | 2 | $5,116.89 | $3,030.00 | $2,800.00 | $3,620.00 | $3,500.00 | $4,100.00 |
| 67 | Advance warning flashing or sequencing arrow panel (C type) (630-80358) | EACH | 1 | $1,140.11 | $1,790.00 | $2,000.00 | $2,140.00 | $2,100.00 | $2,400.00 |
| 68 | Drum channelizing device (630-80360) | EACH | 15 | $31.35 | $10.00 | $25.00 | $12.00 | $12.00 | $13.00 |
| 69 | Barrier (temporary) (630-80370) | LF | 2,520 | $60.00 | $46.00 | $6.25 | $33.00 | $55.00 | $61.00 |
| 70 | Reset concrete barrier (temporary) (630-80371) | LF | 950 | $13.01 | $5.00 | $3.30 | $5.00 | $5.00 | $14.00 |
| 71 | Traffic cone (630-80380) | EACH | 20 | $9.84 | $6.00 | $15.00 | $7.00 | $7.00 | $8.00 |
| 72 | Impact attenuator (temporary) (630-85010) | EACH | 1 | $4,950.47 | $9,640.00 | $7,500.00 | $11,500 | $11,300 | $13,000 |
| 73 | Impact attenuator (temporary)(reset only) (630-85013) | EACH | 1 | $1,607.58 | $2,120.00 | $2,100.00 | $2,530.00 | $2,500.00 | $2,900.00 |
| 74 | Mobile attenuator (630-85041) | DAY | 25 | $981.69 | $480.00 | $1,000.00 | $570.00 | $1,160.00 | $650.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from CDOT's tabulation for this contract. CDOT Tabulation of Bids PDFs from its bid tab archive, May 2023 to September 2026 (each contract linked to its OnBase document), and four December 2025 lettings read by OCR. About 100 tabulations of late 2025 and 2026 are printed in a font without text and are not read yet. On A+B contracts the cost part is kept. Bids that did not match their published total are left out.
Every contract let that day: CDOT letting of August 21, 2025. Compiled by Mirage Metrics.