Pre-fabricated vehicle tracking pad, CDOT 208-00075

Low bidders on CDOT contracts carried a median of $5,000.00 per EACH for this item, over the 24 months to 10 SEP 2026, across 54 low bids. Half of all 194 bids fell between $3,117.59 and $11,850.

Owner
Colorado DOT
Item
208-00075
Unit
EACH
Data through
10 SEP 2026

CDOT prints this item as “Pre-fabricated Vehicle Tracking Pad”.

$5,000.00Low bidder's median, per EACH
$5,471.71Median of all bids, per EACH
54Contracts in the window
$5,000.00Engineer's estimate, median per EACH

By year of letting

Pre-fabricated vehicle tracking pad, CDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
202311$17,6841$17,684
20244343$7,500.00146$6,635.97
20252424$4,827.7391$5,000.00
202611$13,7852$10,360

Bid prices as published, not adjusted for inflation.

By region

RegionLow bidsLow-bid medianAll bidsMedian, all bids
Region 113$5,949.2455$6,500.00
Region 411$3,850.0040$4,162.86
Region 210$2,500.0036$2,602.88
Region 59$12,90034$9,122.50
Region 36$7,900.0019$15,000
Pre-fabricated vehicle tracking pad, CDOT: unit prices by region, last 24 months

Regions with at least three low bids, over the last 24 months.

By quantity

Quantity (EACH)Low bidsLow-bid median
1 to 113$9,000.00
1 to 214$3,625.00
2 to 313$12,900
3 to 4214$5,400.00
Pre-fabricated vehicle tracking pad, CDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Who is lowest on this line

BidderLines bidLowest on the line
Martin Marietta Materials, Inc.126 (50%)
Myers & Sons Construction, LLC164 (25%)
Kiewit Infrastructure Co.64 (67%)
Morton Electric, Inc.83 (38%)
Siete, Inc.73 (43%)
W.W. Clyde & Co.73 (43%)
Pre-fabricated vehicle tracking pad, CDOT: bidders most often lowest on this line

The lowest unit price on each line, whoever won the contract, over all lettings in the data, for firms with five lines or more.

Latest contracts with this item

LetContractRegionQuantityLow bidder's priceMedianEstimateBidsLow bidderSource
02 MAR 2026C27259Region 12$13,785$10,360$4,500.002CONCRETE EXPRESS, INC.dba CEICDOT
18 DEC 2025C248462$13,400$4,508.94$3,867.523Martin Marietta Materials, Inc.CDOT
18 SEP 2025C23069-COMBORegion 53$3,270.00$7,500.00$14,0005W.W. Clyde & Co.CDOT
18 SEP 2025C25393Region 26$5,000.00$6,375.00$3,102.568Siete, Inc.CDOT
11 SEP 2025C24061Region 41$1,500.00$3,500.00$3,827.635Sturgeon Electric Company, Inc.CDOT
21 AUG 2025C26065Region 12$2,100.00$2,800.00$4,222.175Myers & Sons Construction, LLCCDOT
24 JUL 2025C26934comboRegion 14$5,949.24$6,724.62$4,752.744Structures, Inc.CDOT
11 JUL 2025C259607$12,683$12,683$14,2931Kraemer North America, LLCCDOT
26 JUN 2025C25982Region HQ ITS in Boulder2$5,000.00$5,717.00$4,642.524Dillie and Kuhn, IncCDOT
12 JUN 2025C26058Region 32$24,000$11,629$5,000.004Ridgway Valley Enterprises, IncCDOT
05 JUN 2025C25575Region 13$1,500.00$6,000.00$3,200.005Myers & Sons Construction, LLCCDOT
23 MAY 2025C258262$14,637$14,637$14,6371Jalisco International, Inc.CDOT
08 MAY 2025C25862Region 42$1,200.00$5,500.00$2,325.003Castle Rock Construction Company of Colorado, LLCCDOT
01 MAY 2025C25564Region 51$8,864.00$8,932.00$5,000.004Structures, Inc.CDOT
24 APR 2025C26766Region 41$3,850.00$3,850.00$10,0003Martin Marietta Materials, Inc.CDOT
Latest CDOT contracts carrying Pre-fabricated vehicle tracking pad

Filter this item by your own quantity, region and period, or check your price against it, in the CDOT explorer.

How these prices were read

CDOT Tabulation of Bids PDFs from its bid tab archive, May 2023 to September 2026 (each contract linked to its OnBase document), and four December 2025 lettings read by OCR. About 100 tabulations of late 2025 and 2026 are printed in a font without text and are not read yet. On A+B contracts the cost part is kept. Bids that did not match their published total are left out.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are CDOT's own: this item is compared with CDOT contracts only.
  • Prices are bid prices, not paid prices. Use them as a reference range, never as a quote.
  • The data runs to the CDOT letting of 10 SEP 2026 and was rebuilt on 26 NOV 2026.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy