CDOT contract C25960 bid tabulation
CO 119 (MM 44.237-55.5). Let by Colorado DOT on July 11, 2025. 1 bid received; low bid $19,859,813 by Kraemer North America, LLC, -1.3% against the engineer's estimate of $20,126,783.
- Owner
- Colorado DOT
- Letting
- 11 JUL 2025
- Pay items
- 300
- Data through
- 10 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Kraemer North America, LLC | $19,859,813 | Low | -1.0% |
Engineer's estimate: $20,126,783.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Kraemer North America, LLC |
|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201-00000) | LS | 1 | $12,355 | $11,244 |
| 2 | Removal of structures and obstructions (202-00000) | LS | 1 | $14,338 | $14,338 |
| 3 | Removal of tree (202-00010) | EACH | 4 | $1,272.55 | $2,593.79 |
| 4 | Removal of inlet (202-00019) | EACH | 2 | $2,750.33 | $2,750.33 |
| 5 | Removal of pipe (202-00035) | LF | 332 | $421.31 | $77.68 |
| 6 | Removal of end section (202-00037) | EACH | 6 | $738.32 | $738.32 |
| 7 | Removal of electrical conduit (202-00040) | LF | 200 | $13.26 | $22.10 |
| 8 | Removal of concrete median cover material (202-00190) | SY | 175 | $18.69 | $18.69 |
| 9 | Removal of sidewalk (202-00200) | SY | 1,524 | $11.68 | $11.68 |
| 10 | Removal of curb and gutter (202-00203) | LF | 711 | $12.14 | $12.14 |
| 11 | Removal of concrete curb ramp (202-00206) | SY | 51 | $45.35 | $45.35 |
| 12 | Removal of asphalt mat (202-00220) | SY | 5,386 | $12.44 | $12.44 |
| 13 | Removal of pavement marking (202-00250) | SF | 26,600 | $2.24 | $2.24 |
| 14 | Removal of light standard (202-00700) | EACH | 6 | $817.70 | $817.70 |
| 15 | Removal of light standard foundation (202-00705) | EACH | 6 | $1,149.20 | $1,149.20 |
| 16 | Removal of ground sign (202-00810) | EACH | 21 | $336.55 | $336.55 |
| 17 | Removal of sign panel (202-00821) | EACH | 2 | $140.24 | $140.24 |
| 18 | Removal of traffic signal head (202-00831) | EACH | 27 | $138.13 | $138.13 |
| 19 | Removal of traffic signal pole (202-00840) | EACH | 4 | $3,397.88 | $3,397.88 |
| 20 | Removal of traffic signal controller cabinet (202-00855) | EACH | 2 | $1,099.48 | $1,099.48 |
| 21 | Removal of pedestal pole (202-00858) | EACH | 2 | $1,657.50 | $1,657.50 |
| 22 | Removal of fence (202-01000) | LF | 752 | $2.80 | $2.80 |
| 23 | Removal of guardrail type 3 (202-01130) | LF | 1,027 | $3.91 | $3.91 |
| 24 | Removal of end anchorage (202-01300) | EACH | 5 | $457.62 | $457.62 |
| 25 | Clean culvert (202-04002) | EACH | 5 | $3,315.00 | $3,315.00 |
| 26 | Clean inlet (202-04010) | EACH | 1 | $773.50 | $773.50 |
| 27 | Sawing asphalt material (10 inch) (202-05030) | LF | 7,535 | $3.45 | $3.45 |
| 28 | Unsuitable material (203-00050) | CY | 1,070 | $38.98 | $38.98 |
| 29 | Embankment material (complete in place) (203-00060) | CY | 39,220 | $48.24 | $45.93 |
| 30 | Embankment material (complete in place) (special) (203-00062) | CY | 206 | $64.83 | $64.83 |
| 31 | Embankment material (complete in place) (R40) (203-00066) | CY | 864 | $65.67 | $65.67 |
| 32 | Potholing (203-01597) | HR | 200 | $334.64 | $334.64 |
| 33 | Structure excavation (206-00000) | CY | 1,502 | $49.93 | $49.93 |
| 34 | Structure excavation (special) (206-00010) | CY | 118 | $231.69 | $240.39 |
| 35 | Structure backfill (flow-fill) (206-00065) | CY | 154 | $1,877.68 | $371.61 |
| 36 | Structure backfill (class 1) (206-00100) | CY | 1,346 | $75.29 | $75.29 |
| 37 | Mechanical reinforcement of soil (206-00360) | CY | 596 | $16.51 | $13.37 |
| 38 | Filter material (special) (206-00505) | CY | 116 | $158.56 | $124.35 |
| 39 | Filter material (class A) (206-00510) | CY | 56 | $160.17 | $160.17 |
| 40 | Shoring (area 3) (206-01783) | LS | 1 | $32,343 | $32,343 |
| 41 | Shoring (area 4) (206-01784) | LS | 1 | $23,689 | $23,690 |
| 42 | Stockpile topsoil (207-00210) | CY | 16,000 | $5.73 | $5.73 |
| 43 | Stockpile wetland topsoil (207-00310) | CY | 1,016.40 | $44.23 | $44.23 |
| 44 | Topsoil (onsite) (207-00700) | CY | 16,000 | $11.59 | $11.59 |
| 45 | Topsoil (wetland) (207-00703) | CY | 1,016.40 | $27.01 | $27.01 |
| 46 | Subgrade soil preparation (207-00704) | SY | 61,178 | $1.30 | $1.30 |
| 47 | Erosion log type 1 (12 inch) (208-00002) | LF | 4,005 | $5.22 | $5.22 |
| 48 | Silt fence (208-00020) | LF | 7,000 | $1.39 | $1.39 |
| 49 | Silt fence (reinforced) (208-00021) | LF | 100 | $3.59 | $6.10 |
| 50 | Aggregate bag (208-00035) | LF | 150 | $12.53 | $9.12 |
| 51 | Concrete washout structure (208-00045) | EACH | 2 | $9,009.47 | $9,009.47 |
| 52 | Pre-fabricated concrete washout structure (type 1) (208-00046) | EACH | 4 | $2,806.51 | $2,806.51 |
| 53 | Storm drain inlet protection (type I) (208-00051) | LF | 200 | $12.53 | $9.12 |
| 54 | Storm drain inlet protection (type II) (208-00052) | LF | 100 | $45.57 | $41.58 |
| 55 | Pre-fabricated vehicle tracking pad (208-00075) | EACH | 7 | $14,293 | $12,683 |
| 56 | Erosion control management (208-00200) | LS | 1 | $168,282 | $168,282 |
| 57 | Reset pre-fabricated vehicle tracking pad (210-00075) | EACH | 4 | $1,965.57 | $1,965.57 |
| 58 | Reset ground sign (210-00810) | EACH | 12 | $224.37 | $224.37 |
| 59 | Reset traffic signal head (210-00831) | EACH | 8 | $1,353.63 | $1,353.63 |
| 60 | Reset traffic signal controller cabinet (210-00855) | EACH | 2 | $9,779.25 | $9,779.25 |
| 61 | Reset intersection detection system (camera) (210-00890) | EACH | 4 | $1,685.13 | $1,685.13 |
| 62 | Relay riprap (210-02900) | CY | 310 | $160.94 | $160.94 |
| 63 | Adjust manhole (210-04010) | EACH | 1 | $6,439.48 | $6,439.48 |
| 64 | Dewatering (boulder county) (211-03005) | LS | 0.46 | $141,184 | $160,208 |
| 65 | Dewatering (cdot) (211-03005) | LS | 0.42 | $141,184 | $160,208 |
| 66 | Dewatering (RTD) (211-03005) | LS | 0.12 | $141,184 | $160,208 |
| 67 | Organic fertilizer (212-00700) | LB | 5,056 | $0.91 | $0.91 |
| 68 | Compost (mechanically applied) (212-00701) | CY | 306 | $91.13 | $91.13 |
| 69 | Biotic soil amendments (hydraulically applied) (212-00702) | LB | 8,504 | $1.20 | $1.37 |
| 70 | Mycorrhizae (212-00704) | LB | 252.80 | $11.39 | $24.49 |
| 71 | Seeding (native) drill (212-00706) | ACRE | 10.20 | $592.37 | $535.42 |
| 72 | Seeding (native) hydraulic (212-00707) | ACRE | 2.40 | $1,258.79 | $1,258.79 |
| 73 | Seeding (wetland) broadcast (212-00711) | ACRE | 0.60 | $2,141.66 | $2,141.66 |
| 74 | Mulching (weed free straw) (213-00004) | ACRE | 10.20 | $1,150.57 | $1,150.57 |
| 75 | Spray-on mulch blanket (213-00012) | ACRE | 2.40 | $3,987.12 | $3,987.12 |
| 76 | Mulch tackifier (213-00061) | LB | 2,040 | $3.91 | $3.91 |
| 77 | Rock mulch (weed free) (213-00067) | SF | 2,364 | $5.40 | $5.40 |
| 78 | Bonded fiber matrix (213-00150) | ACRE | 5 | $3,987.12 | $3,987.12 |
| 79 | Landscape boulder (213-00700) | EACH | 33 | $985.38 | $985.38 |
| 80 | Soil retention blanket (straw-coconut) (biodegradable class 1) (216-00201) | SY | 6,776 | $2.41 | $2.41 |
| 81 | Soil retention blanket (straw-coconut) (biodegradable class 2) (216-00202) | SY | 1,767 | $2.41 | $2.96 |
| 82 | Turf reinforcement mat (class 2) (216-00302) | SY | 458 | $5.41 | $7.72 |
| 83 | Herbicide treatment (217-00020) | HR | 40 | $143.51 | $143.51 |
| 84 | Noxious weed management (218-00000) | LS | 1 | $47,115 | $29,106 |
| 85 | Wildlife biologist (240-00000) | HR | 16 | $149.25 | $149.25 |
| 86 | Removal of nests (240-00010) | HR | 40 | $143.51 | $143.51 |
| 87 | Prairie dog management (240-00100) | LS | 1 | $68,034 | $29,717 |
| 88 | Aggregate base course (class 6) (304-06007) | CY | 4,344 | $105.42 | $105.42 |
| 89 | Aggregate base course (class 6) (special) (304-06008) | CY | 293 | $132.06 | $132.06 |
| 90 | Hot mix asphalt (patching) (asphalt) (403-00720) | TON | 421 | $357.58 | $357.58 |
| 91 | Hot mix asphalt (grading S) (100) (PG 64- 22) (403-33841) | TON | 4,657 | $118.31 | $126.40 |
| 92 | Hot mix asphalt (grading SX) (100) (PG 64- 28) (403-34851) | TON | 1,514 | $155.14 | $159.89 |
| 93 | Furnish concrete pavement (412-00000) | CY | 35 | $231.51 | $453.95 |
| 94 | Concrete pavement (10-1/2 inch) (412-01050) | SY | 1,493 | $136.10 | $136.10 |
| 95 | Geomembrane (420-00000) | SY | 303 | $14.62 | $23.75 |
| 96 | Geotextile (erosion control) (class 1) (420-00102) | SY | 79 | $22.84 | $25.95 |
| 97 | Drilled shaft (18 inch) (503-00018) | LF | 25 | $497.25 | $497.25 |
| 98 | Drilled shaft (24 inch) (503-00024) | LF | 10 | $574.60 | $574.60 |
| 99 | Drilled shaft (36 inch) (503-00036) | LF | 164 | $729.73 | $858.54 |
| 100 | Drilled shaft (42 inch) (503-00042) | LF | 225 | $854.62 | $872.28 |
| 101 | Crosshole sonic logging testing (503-00310) | EACH | 10 | $2,210.00 | $2,210.00 |
| 102 | Precast panel facing (504-04420) | SF | 1,258 | $131.82 | $131.82 |
| 103 | Soil nail wall (504-06400) | SF | 3,468 | $153.74 | $157.86 |
| 104 | Verification testing (504-06410) | EACH | 5 | $2,821.76 | $2,821.76 |
| 105 | Stone landscape wall (504-08050) | SF | 100 | $214.06 | $214.06 |
| 106 | Riprap (9 inch) (506-00209) | CY | 41 | $288.76 | $288.76 |
| 107 | Riprap (12 inch) (506-00212) | CY | 391 | $151.78 | $151.78 |
| 108 | Soil riprap (12 inch) (506-00412) | CY | 82 | $235.35 | $235.35 |
| 109 | Void-filled riprap (506-00700) | CY | 100 | $214.26 | $214.26 |
| 110 | Concrete slope and ditch paving (reinforced) (507-00100) | CY | 13 | $1,619.92 | $1,619.92 |
| 111 | Concrete lined ditch (507-00555) | CY | 163 | $959.67 | $959.67 |
| 112 | Structural steel (509-00000) | LB | 8,056 | $6.04 | $6.04 |
| 113 | Bearing device (type II) (512-00102) | EACH | 8 | $1,960.28 | $1,960.28 |
| 114 | Bridge drain (special) (513-00690) | EACH | 6 | $11,478 | $11,478 |
| 115 | Pedestrian railing (steel)(special) (514-00201) | LF | 803 | $207.59 | $207.59 |
| 116 | Hand and bikeway railing (514-01050) | LF | 207 | $207.92 | $207.92 |
| 117 | Concrete sealer (515-00400) | SY | 514 | $16.41 | $16.41 |
| 118 | Bridge expansion device (0-4 inch) (518-01004) | LF | 56 | $647.03 | $647.03 |
| 119 | Concrete class B (601-01000) | CY | 4 | $2,710.16 | $2,710.16 |
| 120 | Concrete class D (miscellaneous) (601-03020) | CY | 112 | $1,371.99 | $1,342.28 |
| 121 | Concrete class D (miscellaneous) (colored) (601-03025) | CY | 101 | $1,104.09 | $2,198.77 |
| 122 | Concrete class D (box culvert) (601-03030) | CY | 103 | $1,628.39 | $1,616.21 |
| 123 | Concrete class D (bridge) (601-03040) | CY | 336 | $1,741.30 | $1,782.10 |
| 124 | Concrete class D (wall) (601-03050) | CY | 129 | $1,599.95 | $1,616.35 |
| 125 | Structural concrete coating (601-40301) | SF | 18,016 | $1.66 | $1.77 |
| 126 | Structural concrete coating (anti-graffiti) (601-40302) | SF | 18,016 | $1.77 | $1.77 |
| 127 | Reinforcing steel (epoxy coated) (602-00020) | LB | 103,172 | $1.36 | $1.36 |
| 128 | Culvert lining (31X17 inch) (uvcip) (603-00000) | LF | 140 | $407.63 | $407.63 |
| 129 | 18 inch reinforced concrete pipe (complete in place) (603-01185) | LF | 784 | $180.53 | $180.53 |
| 130 | 24 inch reinforced concrete pipe (complete in place) (603-01245) | LF | 220 | $224.97 | $222.31 |
| 131 | 36 inch reinforced concrete pipe (complete in place) (603-01365) | LF | 232 | $319.14 | $313.29 |
| 132 | 18 inch reinforced concrete end section (603-05018) | EACH | 8 | $3,286.84 | $2,982.97 |
| 133 | 24 inch reinforced concrete end section (603-05024) | EACH | 6 | $3,554.25 | $3,250.38 |
| 134 | 6 inch plastic pipe (603-50006) | LF | 245 | $41.74 | $42.00 |
| 135 | 10 inch plastic pipe (603-50010) | LF | 50 | $97.58 | $95.11 |
| 136 | Inlet type C (5 foot) (604-00305) | EACH | 3 | $11,800 | $11,831 |
| 137 | Inlet type D (5 foot) (604-00505) | EACH | 1 | $11,582 | $13,042 |
| 138 | Inlet type D (10 foot) (604-00510) | EACH | 2 | $11,836 | $13,297 |
| 139 | Inlet type 13 (triple) (5 foot) (604-13605) | EACH | 1 | $18,105 | $18,129 |
| 140 | Inlet special (5 foot) (604-19005) | EACH | 2 | $5,847.63 | $3,352.21 |
| 141 | Inlet type R L 5 (5 foot) (604-19105) | EACH | 1 | $14,547 | $14,568 |
| 142 | Inlet type R L 10 (5 foot) (604-19205) | EACH | 1 | $20,491 | $18,884 |
| 143 | Inlet type R L 10 (10 foot) (604-19210) | EACH | 1 | $20,491 | $22,138 |
| 144 | Inlet special (trench drain) (12 inch width) (604-19712) | LF | 7 | $6,057.86 | $865.41 |
| 145 | Outlet structure (detention basin) (604-20000) | EACH | 1 | $50,601 | $50,879 |
| 146 | Detention basin forebay (includes energy dissipator) (604-20015) | EACH | 3 | $18,080 | $17,982 |
| 147 | Manhole slab base (10 foot) (604-30010) | EACH | 4 | $12,986 | $13,080 |
| 148 | Manhole slab base (15 foot) (604-30015) | EACH | 1 | $15,730 | $15,730 |
| 149 | Pipe edge drain (special) (605-82105) | LF | 456 | $49.87 | $49.87 |
| 150 | Geocomposite drain without pipe (605-83001) | SY | 58 | $119.49 | $128.93 |
| 151 | Guardrail type 3 (31 inch midwest guardrail system) (606-00302) | LF | 2,688 | $40.63 | $40.74 |
| 152 | Guardrail type 9 (style CE) (606-00940) | LF | 439 | $391.09 | $402.19 |
| 153 | End anchorage type 3D (606-01340) | EACH | 2 | $1,757.96 | $1,668.66 |
| 154 | Transition type 3L (606-01395) | EACH | 2 | $2,243.49 | $2,288.13 |
| 155 | End anchorage (nonflared) (606-02003) | EACH | 2 | $4,431.16 | $4,464.65 |
| 156 | Fence (plastic) (607-11525) | LF | 1,100 | $2.03 | $2.03 |
| 157 | Fence (special) (prairie dog fence) (607-11530) | LF | 345 | $132.27 | $132.27 |
| 158 | Fence chain link (special) (607-53005) | LF | 398 | $61.81 | $61.81 |
| 159 | Fence chain link (42 inch) (607-53142) | LF | 95 | $47.22 | $47.22 |
| 160 | Concrete sidewalk (6 inch) (608-00006) | SY | 2,058 | $76.31 | $76.31 |
| 161 | Concrete curb ramp (608-00010) | SY | 293 | $228.19 | $228.19 |
| 162 | Detectable guidance directional indicator (608-00014) | SF | 9 | $221.00 | $221.00 |
| 163 | Detectable warnings (608-00015) | SF | 60 | $207.54 | $207.54 |
| 164 | Concrete bikeway (6 inch) (608-00026) | SY | 8,114 | $73.28 | $73.28 |
| 165 | Concrete bikeway (special) (608-00040) | SY | 648 | $148.45 | $148.45 |
| 166 | Concrete sidewalk (colored) (608-00350) | SY | 84 | $132.74 | $132.74 |
| 167 | Curb and gutter type 2 (section II-M) (special) (609-20004) | LF | 16 | $105.45 | $105.45 |
| 168 | Curb type 2 (section B) (609-20010) | LF | 35 | $50.49 | $50.49 |
| 169 | Curb and gutter type 2 (section I-B) (609-21010) | LF | 987 | $36.07 | $36.07 |
| 170 | Curb and gutter type 2 (section I-M) (special) (609-21013) | LF | 104 | $45.34 | $45.34 |
| 171 | Curb and gutter type 2 (section II-B) (609-21020) | LF | 774 | $41.70 | $41.70 |
| 172 | Curb and gutter type 2 (section II-M) (609-21021) | LF | 20 | $47.12 | $47.12 |
| 173 | Curb and gutter type 2 (section II-B) (special) (609-21023) | LF | 746 | $130.32 | $130.32 |
| 174 | Curb and gutter type 2 (section I-B) (special) (609-21110) | LF | 602 | $106.78 | $106.78 |
| 175 | Gutter type 2 (special) (609-24000) | LF | 283 | $48.43 | $48.43 |
| 176 | Gutter type 2 (2 foot) (609-24002) | LF | 80 | $66.83 | $66.83 |
| 177 | Gutter type 2 (8 foot) (609-24008) | LF | 48 | $176.84 | $176.84 |
| 178 | Curb type 4 (section M) (609-40011) | LF | 22 | $35.90 | $35.90 |
| 179 | Median cover material (4 inch patterned concrete) (610-00024) | SF | 6,864 | $22.38 | $22.38 |
| 180 | Median cover material (stone) (610-00055) | SF | 3,150 | $4.81 | $6.23 |
| 181 | Delineator (type I) (612-00001) | EACH | 33 | $56.09 | $56.09 |
| 182 | Delineator (type II) (612-00002) | EACH | 21 | $56.09 | $56.09 |
| 183 | Delineator (type III) (612-00003) | EACH | 1 | $56.09 | $56.09 |
| 184 | Location marker (fiber optic)(dome) (612-00260) | EACH | 5 | $176.80 | $187.85 |
| 185 | 1/2 inch electrical conduit (613-00050) | LF | 825 | $44.20 | $46.41 |
| 186 | 3/4 inch electrical conduit (613-00075) | LF | 160 | $123.76 | $123.76 |
| 187 | 2 inch electrical conduit (bored) (613-00206) | LF | 2,255 | $23.21 | $23.21 |
| 188 | 3 inch electrical conduit (bored) (613-00306) | LF | 3,590 | $28.73 | $28.73 |
| 189 | 3/4 inch electrical conduit (plastic) (613-01075) | LF | 210 | $14.37 | $14.37 |
| 190 | 1 inch electrical conduit (plastic) (613-01100) | LF | 355 | $17.68 | $17.68 |
| 191 | 1-1/2 inch electrical conduit (plastic) (613-01150) | LF | 20 | $19.89 | $22.10 |
| 192 | 2 inch electrical conduit (plastic) (613-01200) | LF | 10,420 | $17.68 | $17.68 |
| 193 | 3 inch electrical conduit (plastic) (613-01300) | LF | 200 | $23.21 | $23.21 |
| 194 | Electrical conduit (plastic)(multiduct)(bored) (3-2") (613-03492) | LF | 270 | $35.36 | $35.36 |
| 195 | 1-1/4 inch electrical conduit (liquidtight flexible metal) (613-04125) | LF | 8 | $138.13 | $138.13 |
| 196 | Type two pull box (613-07002) | EACH | 56 | $1,574.63 | $1,640.93 |
| 197 | Type three pull box (613-07003) | EACH | 3 | $2,071.88 | $2,165.80 |
| 198 | Type four pull box (613-07004) | EACH | 27 | $3,171.35 | $3,287.38 |
| 199 | Type five pull box (613-07005) | EACH | 2 | $4,127.18 | $4,292.93 |
| 200 | Wiring boulder county (613-10000) | LS | 1 | $40,195 | $54,815 |
| 201 | Wiring cdot (613-10000) | LS | 1 | $177,236 | $177,236 |
| 202 | Wiring RTD (613-10000) | LS | 1 | $78,289 | $78,289 |
| 203 | Luminaire (LED) (special) (613-13000) | EACH | 28 | $10,912 | $10,912 |
| 204 | Luminaire (LED) (3,000 lumens) (613-13007) | EACH | 4 | $839.80 | $1,005.55 |
| 205 | Luminaire (LED) (8,000 lumens) (613-13008) | EACH | 18 | $1,906.13 | $2,033.20 |
| 206 | Luminaire (LED) (11,000 lumens) (613-13011) | EACH | 23 | $1,906.13 | $2,033.20 |
| 207 | Luminaire (LED) (14,000 lumens) (613-13014) | EACH | 28 | $674.05 | $1,016.60 |
| 208 | Luminaire (special) (613-16000) | EACH | 3 | $2,281.83 | $2,342.60 |
| 209 | Light standard steel (25 foot) (613-32250) | EACH | 9 | $4,199.00 | $4,199.00 |
| 210 | Light standard steel (25 foot) (2-arm) (613-32252) | EACH | 7 | $4,392.38 | $4,392.38 |
| 211 | Light standard steel (40 foot) (613-32400) | EACH | 27 | $4,668.63 | $4,768.08 |
| 212 | Light standard metal (14 foot) (613-34140) | EACH | 18 | $3,530.48 | $3,530.48 |
| 213 | Light standard metal (15 foot) (613-34150) | EACH | 4 | $3,530.48 | $885.11 |
| 214 | Concrete foundation pad (bike shelter) (613-40000) | EACH | 1 | $9,647.71 | $9,647.71 |
| 215 | Concrete foundation pad (power pedestals) (613-40000) | EACH | 6 | $5,210.08 | $5,491.85 |
| 216 | Light standard foundation (613-40010) | EACH | 65 | $4,944.88 | $4,944.88 |
| 217 | Meter power pedestal (boulder county LTG) (613-50109) | EACH | 2 | $13,592 | $13,592 |
| 218 | Meter power pedestal (cdot ITS) (613-50109) | EACH | 1 | $12,404 | $12,404 |
| 219 | Meter power pedestal (cdot LTG) (613-50109) | EACH | 1 | $14,332 | $14,332 |
| 220 | Meter power pedestal (cdot signals) (613-50109) | EACH | 1 | $13,293 | $13,293 |
| 221 | Meter power pedestal (RTD LTG) (613-50109) | EACH | 1 | $15,724 | $15,967 |
| 222 | Control center box (613-50125) | EACH | 14 | $2,016.63 | $2,016.63 |
| 223 | Local control station (613-50127) | EACH | 1 | $11,934 | $12,431 |
| 224 | Temporary lighting (solar) (613-50211) | EACH | 4 | $5,497.38 | $5,497.38 |
| 225 | Safety switch NEMA 3R, 30 ampere, 2- pole, 240 volt (613-81699) | EACH | 2 | $1,475.18 | $1,475.18 |
| 226 | Sign panel (class I) (614-00011) | SF | 212 | $33.66 | $33.66 |
| 227 | Sign panel (class I) (wayfinding) (614-00011) | SF | 262 | $147.76 | $147.76 |
| 228 | Sign panel (class II) (614-00012) | SF | 367 | $44.87 | $44.87 |
| 229 | Sign panel (special) (gate marker - PNR ID sign) (614-00037) | EACH | 2 | $38,679 | $38,679 |
| 230 | Sign panel (special) (mile marker) (614-00037) | EACH | 18 | $3,305.31 | $3,305.31 |
| 231 | Sign panel (special) (NZMS) (614-00037) | EACH | 3 | $1,892.62 | $1,892.62 |
| 232 | Sign panel (special) (pylon) (614-00037) | EACH | 6 | $20,237 | $20,237 |
| 233 | Sign panel (special) (wayfinding type C) (614-00037) | EACH | 7 | $5,234.04 | $8,552.01 |
| 234 | Sign panel (special) (wayfinding type D) (614-00037) | EACH | 3 | $5,116.81 | $7,547.88 |
| 235 | Sign panel (special) (wayfinding) (614-00037) | EACH | 67 | $1,781.27 | $1,781.27 |
| 236 | Steel signpost (2X2 inch tubing) (614-00216) | LF | 1,137 | $27.90 | $9.64 |
| 237 | Steel signpost (2.5X2.5 inch tubing) (614-00220) | LF | 312 | $14.73 | $26.09 |
| 238 | Steel sign support (2-inch round)(post) (614-01512) | LF | 207 | $56.09 | $44.81 |
| 239 | Steel sign support (2-inch round)(socket) (614-01522) | EACH | 19 | $448.73 | $481.50 |
| 240 | Steel sign support (2-1/2 inch round NP- 40)(post) (614-01575) | LF | 281 | $56.09 | $56.09 |
| 241 | Steel sign support (2-1/2 inch round NP- 40)(slipbase) (614-01578) | EACH | 38 | $673.10 | $673.10 |
| 242 | 1310NM SFP optic module (614-70024) | EACH | 4 | $723.78 | $723.78 |
| 243 | 1310NM SFP optic module (hpe aruba J4859D 10KM) (614-70024) | EACH | 4 | $723.78 | $723.78 |
| 244 | 1310NM SFP optic module (hpe aruba J4860D 70KM) (614-70024) | EACH | 4 | $723.78 | $723.78 |
| 245 | CWDM SFP optic module (614-70028) | EACH | 3 | $1,547.00 | $1,547.00 |
| 246 | Optical attenuator (614-70030) | EACH | 15 | $491.73 | $491.73 |
| 247 | Optical filter (614-70032) | EACH | 10 | $1,663.03 | $1,663.03 |
| 248 | Pedestrian signal face (16) (countdown) (614-70150) | EACH | 9 | $1,044.23 | $1,044.23 |
| 249 | Accessible pedestrian signal (614-70200) | EACH | 8 | $2,873.00 | $2,873.00 |
| 250 | Traffic signal face (12-12-12) cdot (614-70336) | EACH | 22 | $1,723.80 | $1,723.80 |
| 251 | Traffic signal face (12-12-12) RTD (614-70336) | EACH | 3 | $1,867.45 | $1,867.45 |
| 252 | Blank out sign(LED)(single faced) (614-72740) | EACH | 1 | $4,674.15 | $4,674.15 |
| 253 | Communications cabinet (614-72830) | EACH | 3 | $38,316 | $38,316 |
| 254 | Communications cabinet (type 2) (614-72832) | EACH | 1 | $26,990 | $26,990 |
| 255 | Traffic signal controller cabinet (614-72855) | EACH | 2 | $46,852 | $46,852 |
| 256 | Pedestrian push button post assembly (614-72863) | EACH | 1 | $1,668.55 | $1,668.55 |
| 257 | Fire preemption unit (614-72864) | EACH | 4 | $4,773.60 | $4,773.60 |
| 258 | Emergency telephone (614-72894) | EACH | 3 | $5,552.63 | $5,552.63 |
| 259 | Flashing beacon (solar powered) (614-80001) | EACH | 4 | $9,143.88 | $9,143.88 |
| 260 | Traffic signal-light pole steel (2 mast arm) (614-81020) | EACH | 2 | $57,460 | $57,460 |
| 261 | Traffic signal pedestal pole steel (614-84000) | EACH | 5 | $2,502.83 | $2,502.83 |
| 262 | Impact attenuator (low maintenance) (614-85003) | EACH | 2 | $38,688 | $39,351 |
| 263 | Weather monitoring system (614-86741) | EACH | 1 | $87,627 | $87,627 |
| 264 | Fiber optic cable (single mode) (12 fiber) (614-87010) | LF | 1,470 | $11.05 | $11.05 |
| 265 | Fiber optic cable (single mode) (24 fiber) (614-87011) | LF | 3,580 | $11.05 | $11.05 |
| 266 | Fiber optic termination panel (12 fiber) (614-87012) | EACH | 3 | $1,768.00 | $1,768.00 |
| 267 | Fiber optic termination panel (24 fiber) (614-87024) | EACH | 3 | $2,431.00 | $2,431.00 |
| 268 | Closed circuit television (614-87320) | EACH | 1 | $2,099.50 | $2,210.00 |
| 269 | Closed circuit television (fixed) (614-87320) | EACH | 6 | $2,707.25 | $2,873.00 |
| 270 | Closed circuit television (fixed) (2 lens) (614-87320) | EACH | 1 | $3,038.75 | $3,204.50 |
| 271 | Closed circuit television (fixed) (for shelter/etel) (614-87320) | EACH | 7 | $2,221.05 | $2,320.50 |
| 272 | Closed circuit television (PTZ) (614-87320) | EACH | 2 | $5,226.65 | $8,066.50 |
| 273 | Closed circuit television pole (50 feet) (614-87325) | EACH | 1 | $39,034 | $39,034 |
| 274 | Test fiber optic cable (614-87350) | LS | 1 | $37,432 | $74,864 |
| 275 | Breakaway tapered ITS pole steel (30 feet) (cdot) (614-87400) | EACH | 1 | $14,243 | $17,903 |
| 276 | Ethernet switch (RST916P) (614-87690) | EACH | 3 | $7,641.08 | $7,641.08 |
| 277 | Ethernet switch type II (3962) (614-87692) | EACH | 1 | $8,840.00 | $8,840.00 |
| 278 | Ethernet aggregation switch type II (5142) (614-87698) | EACH | 2 | $7,679.75 | $7,679.75 |
| 279 | Embankment protector type 5 (615-00050) | EACH | 1 | $9,386.80 | $9,386.80 |
| 280 | Prestressed concrete box (depth less than 32 inches) (618-01992) | SF | 3,576 | $86.91 | $86.91 |
| 281 | Detour pavement (621-00450) | SY | 400 | $107.28 | $107.28 |
| 282 | Bicycle rack (622-00010) | EACH | 6 | $967.60 | $967.60 |
| 283 | Shade shelter (tolar BRT) (31 foot) (622-00100) | EACH | 2 | $77,187 | $89,028 |
| 284 | Bench (622-00250) | EACH | 10 | $2,083.65 | $2,321.57 |
| 285 | Bollard (622-00270) | EACH | 5 | $1,822.12 | $874.32 |
| 286 | Trash receptacle (622-00350) | EACH | 4 | $1,685.85 | $2,127.85 |
| 287 | Construction surveying (625-00000) | LS | 1 | $281,926 | $370,277 |
| 288 | Construction surveying (lomr requirements) (625-00000) | LS | 1 | $9,814.61 | $31,690 |
| 289 | Construction surveying (PWQ) (625-00000) | LS | 1 | $18,265 | $19,657 |
| 290 | Mobilization (without autopay) (626-00100) | LS | 1 | $2,083,577 | $2,082,603 |
| 291 | Modified epoxy pavement marking (627-00008) | GAL | 213 | $224.37 | $224.37 |
| 292 | Pavement marking paint (high build) (cdot) (627-00013) | GAL | 300 | $84.13 | $84.13 |
| 293 | Preformed plastic pavement marking (type I)(inlaid) (627-01010) | SF | 2,370 | $24.69 | $24.69 |
| 294 | Preformed thermoplastic pavement marking (word-symbol) (627-30405) | SF | 2,690 | $41.50 | $41.50 |
| 295 | Preformed thermoplastic pavement marking (xwalk-stop line) (627-30410) | SF | 1,202 | $15.70 | $15.70 |
| 296 | Bridge girder and deck unit (180 feet to 185 feet) 37000 37 (628-00180) | EACH | 1 | $1,145,296 | $936,537 |
| 297 | Barrier (temporary) (630-80370) | LF | 500 | $46.09 | $46.09 |
| 298 | Reset concrete barrier (temporary) (630-80371) | LF | 8,450 | $20.40 | $20.40 |
| 299 | Impact attenuator (temporary) (narrow) (630-85010) | EACH | 10 | $9,899.53 | $10,409 |
| 300 | Impact attenuator (temporary)(reset only) (630-85013) | EACH | 1 | $2,838.99 | $2,838.99 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from CDOT's tabulation for this contract. CDOT Tabulation of Bids PDFs from its bid tab archive, May 2023 to September 2026 (each contract linked to its OnBase document), and four December 2025 lettings read by OCR. About 100 tabulations of late 2025 and 2026 are printed in a font without text and are not read yet. On A+B contracts the cost part is kept. Bids that did not match their published total are left out.
Every contract let that day: CDOT letting of July 11, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.