Clean culvert, CDOT 202-04002

Low bidders on CDOT contracts carried a median of $3,307.50 per EACH for this item, over the 24 months to 10 SEP 2026, across 34 low bids. Half of all 116 bids fell between $2,500.00 and $6,240.16.

Owner
Colorado DOT
Item
202-04002
Unit
EACH
Data through
10 SEP 2026

CDOT prints this item as “Clean Culvert”.

$3,307.50Low bidder's median, per EACH
$3,900.00Median of all bids, per EACH
34Contracts in the window
$3,595.68Engineer's estimate, median per EACH

By year of letting

Clean culvert, CDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
20242323$3,687.2090$4,081.98
20251616$3,112.5051$3,615.00
202611$3,735.002$7,615.00

Bid prices as published, not adjusted for inflation.

By region

RegionLow bidsLow-bid medianAll bidsMedian, all bids
Region 19$3,381.3139$3,735.00
Region 28$3,593.6031$3,687.20
Region 46$2,712.5022$4,000.00
Region 35$2,500.0012$7,893.12
Region 53$3,300.008$5,267.50
Clean culvert, CDOT: unit prices by region, last 24 months

Regions with at least three low bids, over the last 24 months.

By quantity

Quantity (EACH)Low bidsLow-bid median
1 to 28$3,867.50
2 to 49$2,500.00
4 to 138$3,763.12
15 to 619$2,100.00
Clean culvert, CDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Who is lowest on this line

BidderLines bidLowest on the line
Subsurface, Inc54 (80%)
Myers & Sons Construction, LLC92 (22%)
Oldcastle SW Group, Inc.82 (25%)
Kiewit Infrastructure Co.62 (33%)
Native Sun Materials Inc52 (40%)
Jalisco International, Inc.61 (17%)
Clean culvert, CDOT: bidders most often lowest on this line

The lowest unit price on each line, whoever won the contract, over all lettings in the data, for firms with five lines or more.

Latest contracts with this item

LetContractRegionQuantityLow bidder's priceMedianEstimateBidsLow bidderSource
02 MAR 2026C27259Region 11$3,735.00$7,615.00$4,000.002CONCRETE EXPRESS, INC.dba CEICDOT
18 DEC 2025C262347$4,567.20$5,383.60$5,000.002Native Sun Materials IncCDOT
18 SEP 2025C25393Region 21$3,500.00$4,350.00$2,916.998Siete, Inc.CDOT
11 SEP 2025C26564Region 234$2,725.00$3,500.00$1,000.005Insituform Technologies, LLCCDOT
21 AUG 2025C26065Region 12$2,500.00$4,000.00$3,130.275Myers & Sons Construction, LLCCDOT
14 AUG 2025C23872Region 44$2,500.00$5,295.00$6,912.793Subsurface, IncCDOT
17 JUL 2025C26207Region 420$3,800.00$7,100.00$2,751.633Subsurface, IncCDOT
11 JUL 2025C259605$3,315.00$3,315.00$3,315.001Kraemer North America, LLCCDOT
05 JUN 2025C26391Region 161$1,740.00$2,500.00$5,000.003Insituform Technologies, LLCCDOT
23 MAY 2025C2582625$1,111.15$1,111.15$1,111.151Jalisco International, Inc.CDOT
08 MAY 2025C25862Region 47$2,925.00$3,000.00$3,637.003Castle Rock Construction Company of Colorado, LLCCDOT
08 MAY 2025C26425Region 36$12,000$12,000$10,0001American West Construction, LLCCDOT
08 MAY 2025C26580Region 520$3,300.00$3,300.00$4,500.003American West Construction, LLCCDOT
17 APR 2025C23818Region 33$2,500.00$2,500.00$3,000.001Morton Electric, Inc.CDOT
27 MAR 2025C23177Region 127$3,381.31$3,772.99$1,545.084Oldcastle SW Group, Inc.CDOT
Latest CDOT contracts carrying Clean culvert

Filter this item by your own quantity, region and period, or check your price against it, in the CDOT explorer.

How these prices were read

CDOT Tabulation of Bids PDFs from its bid tab archive, May 2023 to September 2026 (each contract linked to its OnBase document), and four December 2025 lettings read by OCR. About 100 tabulations of late 2025 and 2026 are printed in a font without text and are not read yet. On A+B contracts the cost part is kept. Bids that did not match their published total are left out.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are CDOT's own: this item is compared with CDOT contracts only.
  • Prices are bid prices, not paid prices. Use them as a reference range, never as a quote.
  • The data runs to the CDOT letting of 10 SEP 2026 and was rebuilt on 26 NOV 2026.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy